19 0 821 KB
1) C1 MEASUREMENT UST-R MODE :P1
P2
C1 UST-R
HV TERMINAL
G R
B
TAN DELTA POINT
G FIG-1
1. 2. 3. 4.
Connect Tan Delta Kit HV terminal to CT main HV Point as shown in FIG-1. Connect Tan delta kit Red measuring Terminal to CT tan delta Point. Secondary of CT’s must be shorted or connected to secondary instruments. Take reading on 2 KV, 5KV and 10 KV on UST-R mode through Delta 4000 kit.
Prepared By: Electrical Lab Team
1|Page Approved By: Mr. Bhupendra Vala Rev: 00 Doc No: 01
2) C2 MEASUREMENT GSTg-R MODE :P1
P2
HV TERMINAL
G
C2 GSTg-R
R
B
TAN DELTA POINT
G
FIG-2
1. Connect Tan Delta Kit HV terminal to CT Tandelta Point as shown in Fig-2. 2. Connect Tan delta kit Red measuring Terminal to CT main HV Point as shown in fig-2. 3. Secondary of CT’s must be shorted or connected to secondary instruments. 4. Take reading on 0.5 KV and 1 KV on GSTg-R mode through Delta 4000 kit. Don’t go beyond 1 KV while measuring C2 Measurement. Prepared By: Electrical Lab Team
2|Page Approved By: Mr. Bhupendra Vala Rev: 00 Doc No: 01