KEGIATAN PEMBANGUNAN SARANA PRASARANA DESA ENSA
SALURAN DRAINASE RT 1 RW 1 PANJANG (M): 100.0
2017 PROVINSI Sulawesi tengah 0.30
PLASTERAN 1:4
KABUPATEN Morowali utara KECAMATAN Mori atas DESA Ensa LOKASI
SULING- SULING
RT 1 RW 1
0.30
JENIS SARANA
0.50
PAS. BATU BELAH 1:5 0.20
Saluran Drainase GAMBAR
PASIR URUG
POTONGAN
0.05
DIBUAT OLEH 0.35
PELAKSNA KEGIATAN DIPERIKSA OLEH
DETAIL SALURAN DRAINASE
DPL IRNOVIA B.PAKPAHAN,ST.,M.Eng DIKETAHUI OLEH KADES
Kabupaten :Morowali utara Kecamatan :Mori atas Desa :Ensa
Jenis Prasaran Saluran Drainase Lokasi RT 1 RW 1 Volume 100 M
Take Off Sheet a
b
c
d
Volume galian tanah Talud no. 1 P= 100m Panjang = 100.00 m Lebar = 0.35 m Tebal = 0.20 m Volume galian = 100 X 0.35 X 0.2 Talud no. 2 P= 100m Panjang = 100.00 m Lebar = 0.35 m Tebal = 0.20 m Volume galian = 100 X 0.35 X 0.2 Volume galian total Volume urugan pasir Talud no. 1 P= 100m Panjang = 100.00 m Lebar = 0.35 m Tebal = 0.05 m Volume urugan = 100 X 0.35 X 0.05 Talud no. 2 P= 100m Panjang = 100.00 m Lebar = 0.35 m Tebal = 0.05 m Volume urugan = 100 X 0.35 X 0.05 Volume urugan total Volume batu belah Talud no. 1 P= 100m Panjang = 100.00 Lebar atas = 0.30 Lebar bawah = 0.35 Tinggi talud = 0.30 Tinggi pondasi = 0.20 Volume batu belah {(0.3 + 0.35)/2} x 0.3 x 100 0.35 x 0.2 x 100 Talud no. 2 P= 100m Panjang = 100.00 Lebar atas = 0.30 Lebar bawah = 0.35 Tinggi talud = 0.30 Tinggi pondasi = 0.20 Volume batu belah {(0.3 + 0.35)/2} x 0.3 x 100 0.35 x 0.2 x 100 Volume total Volume plesteran Talud no. 1 P= 100m Panjang = 100.00
m
=
7.0
m³
= =
7.0 14.0
m³ m³
=
1.8
m³
= =
1.8 3.5
m³ m³
= =
9.8 7.0
m³ m³
= = =
9.8 7.0 33.5
m³ m³ m³
m m m m m
m m m m m
Lebar = 0.30 Volume plesteran (0,1 + 0.3) x 100 Talud no. 2 P= 100m Panjang = 100.00 Lebar = 0.30 Volume plesteran (0,1 + 0.3) x 100 Volume plesteran total f
Tanggal Survei :02-Okober-2022
m =
40.0
m²
= =
40.0 80.0
m² m²
=
32.1
HOK
m m
Langsiran material Pekerja langsiran (1 m³ = 0,5 HOK) Bahan = 64.3 m³ Pekerja
Dibuat oleh : Mahasiswa KKPT
PERHITUNGAN VOLUME PEKERJAAN, ANALISA HARGA SATUAN & BIAYA Uraian Pekerjaan I
Volume
Satuan
Pekerjaan galian tanah (Analisa P.02.a) 0.563 Pekerja 0.025 Mandor Total biaya
14.0
m³
7.9 0.4
HOK HOK
Pekerjaan urugan pasir (Analisa T.14.c) 1.2 Pasir urug 0.4 Pekerja 0.04 Mandor Total biaya
3.5
m³
4.2 1.4 0.14
m³ HOK HOK
III Pasangan batu belah 1 : 5 (Analisa P.01.C.a.1) 1.17 Batu belah 2.352 Semen 50 Kg 0.5654 Pasir muntilan 1.18 Pekerja 0.59 Tukang 0.1 Kepala tukang 0.1 Mandor Total biaya
33.5
m³
39.2 78.8 18.9 39.5 19.8 3.4 3.4
m³ Zak m³ HOK HOK HOK HOK
IV Plesteran 1 PC : 4 PS, 15 mm (SNI 03 - 2837 - 2008) 0.125 Semen 50 Kg 0.024 Pasir muntilan 0.3 Pekerja 0.15 Tukang 0.015 Kepala tukang 0.015 Mandor Total biaya
80.0
m²
10.0 1.9 24.0 12.0 1.2 1.2
Zak m³ HOK HOK HOK HOK
II
Harga Satuan
120,000 150,000
120,000 150,000
Total Biaya
948,000 60,000 1,008,000
168,000 21000 189,000
290,000 63,000 360,000 120,000 150,000 180,000 150,000
11,366,550 4,963,896 6,818,724 4.740.000 2.970.000 612,000 510,000 1.152,85917
63,000 360,000 120,000 150,000 180,000 150,000
630,000 691,200 2.880.000 1.800.000 216.000 180,000 810.910,08
REKAP KEBUTUHAN BAHAN, ALAT DAN UPAH No 1 2 3 4 5 6 7 8 9
Uraian Pasir urug Batu belah Semen 50 Kg Pasir muntilan Pekerja Tukang Kepala tukang Mandor Pekerja langsiran
Volume 4.2 39.2 88.8 20.9 72.8 31.8 4.6 5.0 32.1
= = = = = = = = =
Satuan 5.0 40.0 89.0 21.0 73.0 32.0 5.0 6.0 33.0
m³ m³ Zak m³ HOK HOK HOK HOK HOK
RENCANA ANGGARAN BIAYA DESA ENSA KECAMATAN MORI ATAS TAHUN ANGGARAN 2022 Bidang Kegiatan Lokasi
: : :
Pelaksanaan Pembangunan Desa Saluran Drainase Desa Ensa
Rincian Pendanaan
Uraian
Volume
Satuan
Harga Satuan Rp
Saluran Drainase RT 1 RW 1 Vol= 100 m Belanja Barang dan Jasa Upah Tenaga Kerja Pekerja Tukang Kepala tukang Mandor Pekerja langsiran Belanja Modal Matrial Pasir urug Batu belah Semen 50 Kg Pasir muntilan
73.0 32.0 5.0 6.0 33.0
5.0 40.0 89.0 21.0
Jumlah Rp 35,143,000
HOK HOK HOK HOK HOK
120,000 150,000 180,000 150,000 100,000
8,990,000 8,990,000 8.760.000 4.800.000 900.000 900.000 3.300.000
1.800.016,86
m³ m³ Zak m³
170,000 290,000 63,000 360,000
26,153,000 25,617,000 850,000 11,600,000 5,607,000 7,560,000
Alat Cetok Ember plastik (5 liter) Sekop Cangkul
1.0 2.0 1.0 1.0
Set Buah Buah Buah
14,000 10,000 91,000 91,000
216,000 14,000 20,000 91,000 91,000
Sewa molen Prasasti Papan Proyek
1.0 1.0
Hari Ls Ls
250,000 300,000 20,000
300,000 20,000
DISETUJUI OLEH: Kades
Yan Ferdinand Suade
87,129,00
DISETUJUI OLEH: pelaksana
Mahasiswa KKPT