Inspection and Test Plan For Waterproofing Works [PDF]

  • 0 0 0
  • Suka dengan makalah ini dan mengunduhnya? Anda bisa menerbitkan file PDF Anda sendiri secara online secara gratis dalam beberapa menit saja! Sign Up
File loading please wait...
Citation preview

CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast



REF NO.



INSPECTION AND TEST PLAN FOR WATERPROOFING WORKS PROJECT: NORTH-SOUTH COMMUTER RAILWAY EXTENSION (NSCREX)



SUBCONTRACTOR INVOLVE IN THE WORK : HCC



REF. DOCUMENT: NSCR-PSC-N05-CRKDPT-MST-X-00002- METHOD STATEMENT FOR WATERPROOFING WORKS



PLACE OF CONSTRUCTION/INSPECTION: DEPOT



ITEM NO.



FREQUENCY OF DESCRIPTION OF INSPECTION/TESTING ACTIVITIES INSPECTION AND/OR TESTING



C



DATE



12-Apr-21



INSPECTION CARRIED OUT ACCEPTANCE CRITERIA



SUBCONTRACTOR



POSCO E&C



CONSTR



QC



CONSTR



QC



ENGINEER



VALIDATING REPORT/DOCUMENTS



1.0



PRELIMINARIES/APPROVAL



1.1



Manufacturer



Prior to start of work



TS 514.1.9



Minimum 3 years documented experience



HP



HP



HP



R



R



Approved Method Statement



1.2



Applicator



Prior to start of work



TS 514.1.9



Minimum 3 years documented experience and certified by manufacturer



HP



HP



HP



HP



HP



Approved Method Statement



Method Statement



Prior to start of work



TS 514.1 and TS 514.3



Approved Method Statement



HP



HP



HP



HP



R



Approved Method Statement



Material Approval



Prior to start of work



TS 514.1 , TS 514.1.1, TS 514.1.4



Approved Materials as per specs



HP



HP



HP



HP



R



Approved Method Statement



Data sheet, Test report, certificates, and material compliance



Prior to start of work



TS 514.1.4



Approved Documents



HP



HP



HP



HP



R



Approved Method Statement



Shop Drawing



Prior to start of work



TS 514.1.4



Approved Method Statement



HP



HP



HP



HP



HP



Approved Method Statement



Mock-up



Prior to start of work



TS 514.1.5



Approved MS and Specs



HP



HP



HP



HP



R



Approved Method Statement/TS



Pre-installation meeting



Prior to start of work



TS 514.1.5, TS 514.1.10



Approved MS, and Shop Drawing



HP



HP



HP



HP



R



Approved Method Statement/ TS



2.0



MATERIAL



2.1



Cementitous Waterproofing



Prior to start of work



TS 514.1.6



Approved MS, Approved material, and TS



HP



HP



HP



HP



R



certificates/test report



2.2



Elastomeric Fluid-applied Cold membrane



Prior to start of work



TS 514.1.6



Approved MS, Approved material, and TS



HP



HP



HP



HP



R



certificates/test report



Prior to start of work



TS 514.1.6



Approved MS, Approved material, and TS



HP



HP



HP



HP



R



certificates/test report



each location



TS 514.3.2, Method Statement



Checking thru visual inspection



HP



HP



HP



HP



WP



Approved Inspection report



each location



TS 514.3.2, Method Statement



Checking thru visual inspection



HP



HP



HP



HP



WP



Approved Inspection report



HP



HP



HP



HP



R



Approved Inspection report



MS/TS, approved shop drawing



Asphat membrane waterproofing



2.0



EXECUTION AND IMPLEMTENTATION Cementitious water Proofing



2.1.1



2.1



FORM NO. CPN05-POSCO-QA-002



APPLICABLE REFERENCE DOCUMENTS, SPECIFICATION & CLAUSE



ITP-0007



REV.



Conduct post concreting survey after clearing the area to verify any concrete defects



2.1.2



Surface Preparation



each location



TS 514.3.2, Method Statement



visual inspection, mask surface not receiving waterproofing to prevent over spray affecting other construction, apply two(2) coats of joint detailing mastic, 90 degrees terminations, vertical and and horizontal 300mm on each side. Penetrations, drains, sleeve:150mm radius around penetration and 75mm onto penetrating object. Joints and cracks: 150mm wide on each side of joint/crack



2.1.3



Application



each location



TS 514.3.3, Method Statement



Apply only when technical representative is present( for the 1st application only) Spray application 1 coat roller application - 2 coats



HP



HP



HP



HP



HP



Elestomeric fluid-applied cold membrane waterproofing



each location



TS 514.3.2, Method Statement



Checking thru visual inspection



HP



HP



HP



HP



WP



Approved Inspection report



2.2.1



each location



TS 514.3.2, Method Statement



Penetration through the structural slab shall be in place and and sleeves are place through the slab and made it water tight



HP



HP



HP



HP



WP



Approved Inspection report



Flashing



INSPECTION AND TEST PLAN FORM(ITPF) REV.C



Page 1 of 8



CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast



REF NO.



INSPECTION AND TEST PLAN FOR WATERPROOFING WORKS PROJECT: NORTH-SOUTH COMMUTER RAILWAY EXTENSION (NSCREX)



SUBCONTRACTOR INVOLVE IN THE WORK : HCC



REF. DOCUMENT: NSCR-PSC-N05-CRKDPT-MST-X-00002- METHOD STATEMENT FOR WATERPROOFING WORKS



PLACE OF CONSTRUCTION/INSPECTION: DEPOT



ITEM NO.



FREQUENCY OF DESCRIPTION OF INSPECTION/TESTING ACTIVITIES INSPECTION AND/OR TESTING



APPLICABLE REFERENCE DOCUMENTS, SPECIFICATION & CLAUSE



C



DATE



12-Apr-21



INSPECTION CARRIED OUT ACCEPTANCE CRITERIA



SUBCONTRACTOR



POSCO E&C



CONSTR



QC



CONSTR



QC



ENGINEER



VALIDATING REPORT/DOCUMENTS



2.2.2



Drains



each location



TS 514.3.2, Method Statement



Apply a full elestomeric sheet around the drain. The elastomeric shhet shall be adhered a minimum of 100mm into the horizontal deck.



HP



HP



HP



HP



WP



Approved Inspection report



2.2.3



Other penetration and Projections



each location



TS 514.3.2, Method Statement



Flash the penetrations and projections including vents and service pipes, thru the slab with an elastomeric sheet. Leave the elastomeric sheet un-adhered for 25mm over the joint between the penetration anf slab.



HP



HP



HP



HP



WP



Approved Inspection report



2.2.4



Walls and vertical surfaces



each location



TS 514.3.2, Method Statement



Flash wall intersections which are not of monolithic pour or constructed with reinforce concrete joints with an elastomeric sheet. Cover the elastomeric sheet with fluid-applied waterproofing during application.



HP



HP



HP



HP



WP



Approved Inspection report



2.2.5



Cracks and joints



each location



TS 514.3.2, Method Statement



Cracks that show movement shall receive a 50mm bond breaker follwed by an elastomeric sheet adhered to the deck. Non-moving cracks shall be double coated with the fluid appiled waterproofing.



HP



HP



HP



HP



WP



Approved Inspection report



2.2.6



Priming



each location



TS 514.3.2, Method Statement



HP



HP



HP



HP



WP



Approved Inspection report



2.2.6



Application



each location



TS 514.3.3, Method Statement



HP



HP



HP



HP



WP



Approved Inspection report



2.2



FORM NO. CPN05-POSCO-QA-002



ITP-0007



REV.



Prime surfaces to receive the fluidapplied waterproofing membrane. Apply the primer as required by the membrane manufacturer’s printed instructions. Over the primed surfaces, provide a uniform, monolithic coating of fluidapplied membrane, 60 mils thick, plus or minus 5 mils thick, by following the manufacturer’s printed instructions. Apply material by trowel, roller, brush, spray apparatus, or other method acceptable. Check wet film thickness as specified under Field Tests, and adjust application rate as necessary to provide a uniform coating of the thickness specified. Where possible, mark off the surface to be coated in even units to facilitate proper coverage. At expansion joints, control joints, prepared cracks, and termination, carry the membrane over the preformed elastomeric sheet in uniform 60 mils thick, plus or minus 5 mils, wet thickness to provide a monolithic coating. When work has stopped long enough for the membrane to cure, begin the next application by wiping the previously applied materials with a solvent so that accumulated dirt and dust, which could inhibit adhesion of the overlapping membrane coat, is removed. Use solvent recommended by the membrane manufacturer, as approved.



INSPECTION AND TEST PLAN FORM(ITPF) REV.C



Page 2 of 8



CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast



REF NO.



INSPECTION AND TEST PLAN FOR WATERPROOFING WORKS PROJECT: NORTH-SOUTH COMMUTER RAILWAY EXTENSION (NSCREX)



SUBCONTRACTOR INVOLVE IN THE WORK : HCC



REF. DOCUMENT: NSCR-PSC-N05-CRKDPT-MST-X-00002- METHOD STATEMENT FOR WATERPROOFING WORKS



PLACE OF CONSTRUCTION/INSPECTION: DEPOT



ITEM NO.



FREQUENCY OF DESCRIPTION OF INSPECTION/TESTING ACTIVITIES INSPECTION AND/OR TESTING



C



DATE



12-Apr-21



INSPECTION CARRIED OUT ACCEPTANCE CRITERIA



SUBCONTRACTOR



POSCO E&C



CONSTR



QC



CONSTR



QC



ENGINEER



VALIDATING REPORT/DOCUMENTS



3.0



FIELD QUALITY CONTROL



3.1



Thickness for cementitious waterproofing



each location



TS 514.3.3, Method Statement



Spray application - 1 coat roller application - 2 coats



HP



HP



HP



WP



RI



Approved drawings



3.2



Thickness for Elestomeric fluid-applied cold membrane waterproofing



each location



TS 514.3.3, Method Statement



60 mils plus or minus 5 mils using lightly oiled, neddle nose depth guage



HP



HP



HP



WP



RI



Approved Method Statement/approved drawing



3.3



Flood test



each location



TS 514.3.5, Method Statement



48hrs curing time before testing, 50mm depth of water for 24hrs, checking thru measurement.



HP



HP



HP



WP



RI



Approved Method Statement/ts



3.4



Moisture test



each location



TS 514.3.5, Method Statement



indicated "DRY" in the DELMHORST MOISTURE METER



HP



HP



HP



WP



WP



Approved Specs, Method statement



2.0



RECTIFICATION (IF ANY) each location



TS 514.3.5, Method Statement



Approved Inspection Report



HP



HP



HP



HP



WP



Approved Specs, Method statement, test result and approved methodology



Repair or replace damaged and re-test



FORM NO. CPN05-POSCO-QA-002



APPLICABLE REFERENCE DOCUMENTS, SPECIFICATION & CLAUSE



ITP-0007



REV.



INSPECTION AND TEST PLAN FORM(ITPF) REV.C



Page 3 of 8



CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast



REF NO.



INSPECTION AND TEST PLAN FOR WATERPROOFING WORKS PROJECT: NORTH-SOUTH COMMUTER RAILWAY EXTENSION (NSCREX)



SUBCONTRACTOR INVOLVE IN THE WORK : HCC



REF. DOCUMENT: NSCR-PSC-N05-CRKDPT-MST-X-00002- METHOD STATEMENT FOR WATERPROOFING WORKS



PLACE OF CONSTRUCTION/INSPECTION: DEPOT



ITEM NO.



2.0



FREQUENCY OF DESCRIPTION OF INSPECTION/TESTING ACTIVITIES INSPECTION AND/OR TESTING



APPLICABLE REFERENCE DOCUMENTS, SPECIFICATION & CLAUSE



ITP-0007



REV.



C



DATE



12-Apr-21



INSPECTION CARRIED OUT ACCEPTANCE CRITERIA



SUBCONTRACTOR



POSCO E&C



CONSTR



QC



CONSTR



QC



HP



HP



HP



HP



ENGINEER



VALIDATING REPORT/DOCUMENTS



FINAL ACCEPTANCE



Hand over of works



Each Area



Approved method statement



Approved Inspection Report



WP



Approved Inspection report



TYPE OF INSPECTION (RI) : RANDOM INSPECTION



(HP) : HOLD POINT



(WP) : WITNESS POINT



(NA) : NOT APPLICABLE



DEFINITION OF CHECKING POINTS



FORM NO. CPN05-POSCO-QA-002



REVIEW (R) = documents to be reviewed, no signature required on the Inspection Request or its accompanying documentation.



WITNESS POINT (WP) = attendance at the site is expected, the signature is required on check sheet of Inspection



HOLD POINT (H) = attendance at the site is mandatory and signature is required on the check sheet of Inspection Request at the time of the inspection to release the following work.



RANDOM INSPECTION (RI) = random attendance at site, no signature required on the Inspection Request ( IR ) or its accompanying documentation



INSPECTION AND TEST PLAN FORM(ITPF) REV.C



Page 4 of 8



North-South Commuter Railway Extension Project CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)



INSPECTION REPORT INPECTION AND TEST PLAN FOR BORED PILES LOCATION:



REPORT NO:



DATE:



LINE OR STRUCTURE:



DOCUMENT REF & REV NO:



IR REF. NO: ITP NO:



DESCRIPTION 1. PRELIMINARIES Permit to work Subcontractor / Personnel qualification and The Engineer shall approve or reject the Contractor's qualifications and field personnel Materials approvals / Work shall not begin until all the required submittals have been accepted Measuring equipment calibration from manufacturer



Availability of approved drawings, Method Statements and Work shall not begin until all the required submittals have been accepted 2. ACTIVITIES 1



Mock up 2. ACTIVITIES 3 Installation of steel casing (length, Dia. And verticality / All permanent structural casing shall be of steel conforming to ASTM A36/A36M or ASTM A252 Gr. 2 unless specified otherwise in the Drawings /All splicing of permanent structural casing shall be in accordance with Article 6.13.3, "Welded Connections," of the AASHTO LRFD Bridge Design Specifications. Borehole drilling and cleanliness / The Contractor shall use appropriate means, such as a cleanout bucket, air lift, or hydraulic pump, to clean the bottom of the excavation of all bored piles



Drilling depth / tape with a heavy weight attached to the end of the tape, or other means acceptable to the Engineer to determine that the shaft bottom meets the requirements in the Contract Bentonite slurry testing (spec. gravity., marsh viscosity, PH, dosage / Bentonite Suspension must conform to the following specifications stated in TS 204.3.7 Drilling depth / the base of the excavation shall be covered with not more than 12.5mm for 50 percent of the base area of sediment or loose or disturbed material just prior to placing concrete. Placing of sediments or Disturd material / or wet bored pile excavations in soils, the base of the excavation shall be covered with not more than 75mm of sediment or loose or disturbed material just prior to placing concrete. For dry bored pile excavations in soils, the base of the excavation shall be covered with not more than 37.5mm sediment or loose or disturbed material just prior to placing concrete 2. ACTIVITIES 3 Delivery of reinforcement / Reinforcing steel used in the construction of bored piles shall conform to Section 207 / Reinforcing steel shall be bundled in order to meet the clear spacing requirements between the vertical reinforcement bars Assembly of reinforcement / pre-assembly Check the availability of the connectors, clamps, spacers, and other fittings Installation of steel cage Check the type, number and the position of spacers 2. ACTIVITIES 4 Material/Concrete used in the construction of bored piles shall conform to Section 206.4



SUBCONTRACTOR CONSTRUCTION



QC



POSCO E&C CONSTRUCTION



QC



ENGINEER



REMARKS



Delivery of concrete and testing of fresh concrete and Concrete used in the construction of bored piles shall conform to Section 206.4 Laboratory testing cylinder Placing of concrete / The concrete shall be placed such that the free fall is vertical down the center of the shaft without hitting the sides, the steel reinforcing bars, or the steel reinforcing bar cage bracing. Curing / After placement, the temporarily exposed surfaces of the shaft concrete shall be cured in accordance with the provision in Section 206.13



Removal of steel casing / Casing extraction shall be at a slow, uniform rate with the pull in line with the axis shaft. Excessive rotation of the casing shall be avoided to limit deformation of the reinforcing steel cage. 2. ACTIVITIES 5



Crosshole sonic tubes( number, diameter and cleanliness of tubes) / Access tubes for crosshole sonic log testing shall be steel pipe of 3.6mm minimum wall thickness and at least 38.1mm inside diameter. Crosshole sonic logging test on hardened bored pile / The access tubes shall have a round, regular inside diameter free of defects and obstructions Grouting of crosshole sonic tubes / Grout for filling the access tubes at the completion of the cross-hole sonic log tests shall be a neat cement grout with a maximum water/cement ratio of 0.45. All bleed water is to be removed and the access tubes topped up with grout. 2. ACTIVITIES 6



Initial load testing / The initial load test shall be cyclic load test for the test piles deriving strength from end bearing and side friction. The maintained load test can be performed for end bearing piles which do not rely on friction and for piles socketed in rock. Initial load test shall be referred to Static Load Test in Section 204.2.6.2. Static load testing / The static load test shall follow the procedures specified in ASTM D1143/D1143M, and the loading procedure should follow the Quick Load Test Method, unless detailed longer-term load-settlement data are needed, in which case the standard loading procedure should be used



3. FINAL ACCEPTANCE OTHER REMARKS:



INITIALS REFERENCE BOX : (WRITE DOWN YOUR INITIALS AS SIGNED ABOVE AND NAME) SIGNATURE NAME POSITION DATE: CONSTRUCTION



QC



CONSTRUCTION



QC



ENGINEER SUBCONTRACTOR



POSCO E&C



LEGEND: HP : HOLD POINT



WP : WITNESS POINT



RI : RANDOM INSPECTION



R: REVIEW



NA : NOT APPLICABLE



North-South Commuter Railway Extension Project CP N-05 : Building and Civil Engineering Work for Depot Building Including Related Infrastructure and Track Work Ballast (Contract No : NSCREX-03-N05)



INSPECTION REPORT BORED PILING WORKS INSPECTION CHECKLIST LOCATION:



REPORT NO:



DATE:



LINE OR STRUCTURE:



DOCUMENT REF & REV NO:



IR REF. NO: ITP NO: ITP-005



SUBCONTRACTOR



DESCRIPTION



POSCO E&C



ENGINEER



CONSTRUCTION



QC



CONSTRUCTION



QC



of tubes) / Access tubes for cross-hole sonic log testing shall be steel pipe of 3.6mm minimum wall thickness and at least 38.1mm inside diameter. Crosshole sonic logging test on hardened bored pile / The access tubes shall have a round, regular inside diameter free of defects Grouting of crosshole and obstructions sonic tubes / Grout for filling the access tubes at the completion of the cross-hole sonic log tests shall be a neat cement grout with a maximum water/cement ratio of 0.45. All bleed water is to be removed and the access tubes topped up with grout.



HP



HP



HP



WP



WP



HP



HP



HP



WP



WP



HP



HP



HP



WP



WP



1. Acceptance of the survey establishment and reference



HP



HP



HP



RI



RI



2. Setting-out



HP



HP



HP



RI



RI



REMARKS



4. TESTING Crosshole sonic tubes( number, diameter and cleanliness



2. BOREHOLE



OTHER REMARKS:



INITIALS REFERENCE BOX : (WRITE DOWN YOUR INITIALS AS SIGNED ABOVE AND NAME) SIGNATURE NAME POSITION DATE: CONSTRUCTION



QC



CONSTRUCTION



QC



ENGINEER SUBCONTRACTOR



LEGEND:



POSCO E&C



HP : HOLD POINT



WP : WITNESS POINT



RI : RANDOM INSPECTION



R: REVIEW



NA : NOT APPLICABLE