Introduction to Oilfield, Primary & Remedial Cementing



Agenda Introduction to the oil field Type of drilling rigs, rig equipment Oilwell Cementing 



Step of Primary Cementation







Objectives of Primary Cementation







Execution of a Cement Job







Remedial Cementing







Cementing Equipment



Schlumberger Private



2







Types of Drilling Rig Basically two types of drilling rig: Offshore-based drilling platform – Floating – Fixed 



Land-based drilling platform



Schlumberger Private







Types of Drilling Rig (Offshore) • Mobile Jack-up type • Used in shallow water – up to 100m • Found all over the world



Schlumberger Private



• Rig has three legs for stability



Types of Drilling Rig (Offshore) • Platform type • Used in oil production • Can have steel or concrete legs • Can drill and produce oil concurrently



Schlumberger Private



• Permanently fixed to sea floor



Types of Drilling Rig (Offshore) • Mobile semi-submersible type • Held in position with tensioned chains and anchors • Can be self-propelling • Widely used worldwide



6



Schlumberger Private



• Float on pontoons



Drilling Rig Equipment



Schlumberger Private



BOPs



Derrick



Casing



Mud System



Steps to Cementation 1. Drill the hole for each string of casing 2. Run casing as per hole size 4. Perform cement job(s): •



Conductor (~ 30 ft deep)







Surface Casing (~ 800ft deep)







Intermediate Casing (~ 3000 ft deep)







Production Casing (~ 9000 ft deep)







Liner (~ 10000 to 20000 ft deep)



Schlumberger Private



3. Circulate and condition drilling fluid (mud)



Objectives of Cement Job There are three main objectives: Provide complete isolation of zones







Support the casing / Wellbore stability







Protect casing string



Schlumberger Private







Executing a cement job



Casin g



Drilling Fluid



Flow inside the Casin g Spacer



Open Hole



Schlumberger Private



Cement is pumped down inside the casing. Cement then passes in the gap (or annulus) between the casing and open hole. It is displaced into position with drilling fluid. Spacers are often pumped ahead and behind to clean the hole and protect the cement.



Cement Slurry



Executing a cement job Cement mixed by two methods ‘on-the-fly’ or ‘batch’ mixed Pumped from the cement unit to the drill floor. Cement passes through a cement head Top Plug containing wiper plugs. Two types of plug – bottom and top – for specific reasons



Casing







Schlumberger Private



Bottom Plug



Cement



Primary Cementing Animations Single Stage Job Liner job Stab-in job Double stage job



Schlumberger Private



• • • •



Remedial Cementing : Cement Plug







To side track (fish or DD)







To plug back a zone







To plug back a well (P&A))







To solve a lost-circulation



Schlumberger Private



A relatively small volume of cement slurry placed in the wellbore Common Purposes:



Squeeze Cementing packer



tubing FORMATION casing DEHYDRATED CEMENT



cement slurry



cement nodes



PRIMARY CEMENT



CHANNEL BEHIND CASING



Schlumberger Private



Primary cement job repair Unwanted Water Production High Gas-Oil Ratio (GOR) Casing Splits or Leaks Nonproductive or Depleted Zones



Effect of Fluid Loss Control Node build-up after 45 min, slurries with different fluid-loss, dP=1000psi 800 ml/30min



150 ml/30min



Partially bridged casing



50 ml/30min



Completely filled perforations



15 ml/30min



Partially filled perforations



Schlumberger Private



Completely bridged casing



Squeeze Cementing - Methods Pumping technique – Hesitation – Running – High pressure - above formation frac pressure – Low pressure - below formation frac pressure



Tools – Packer/Retainer – Bradenhead



Coiled tubing



Schlumberger Private



Placement technique



Running Squeeze



Pressure ( psi )



Schlumberger Private



Time (min) •



Time (min..)



Usually a large volume of slurry is pumped with this technique



Hesitation Squeeze



Pressure (psi)



A



10-20 min. intervals B



C



D



A



Time (min)



D



Schlumberger Private



Pressure (psi)



Rate of 0.25 - 0.5 bpm



Cement Units Onshore (1) The cement units are truck-mounted and mobile. Performs cementing operations







Performs other pumping jobs



Schlumberger Private







Cement Units Onshore (2) Trucks come in a variety of forms to cater for different landbased environments. Schlumberger Private



Cement Units Offshore (1) The cement unit is permanently fixed on each rig. Performs cementing operations







Performs other pumping jobs



Schlumberger Private







Cement Units Offshore (2) Each cement unit consists of: 2 x pump units







2 x engines







Mixing system







Liquid Additive system







Back up systems



Schlumberger Private







Schlumberger Private



Questions?



Drilling Rig Equipment - Derrick The main structure through which all the drilling operations are performed.







It can suspend many millions of pounds in weight, and is used to apply weight to the drill string.







All drilling rigs will have a derrick of some form or another



Schlumberger Private







Drilling Rig Equipment – Mud System



Schlumberger Private



Drilling Rig Equipment - BOPs Subsea Blow-out Preventor (BOP) stacks are specially designed to operate under water at great depths.







They are located on the sea bed, rather than above water on the rig.







Subsea BOPs are used only on floating rigs.







They are a very important safety device to prevent the well ‘blowing’ oil



Schlumberger Private







Casing Function •



from each other and the surface.



Schlumberger Private



A series of casing strings is necessary to complete a well and produce the desired fluid successfully. Casing is large pipe run into the wellbore to protect the integrity of the hole and to isolate various parts of the formation



Cement Head • • •



Used to hold the top and bottom plugs. Fixed to top of casing during cement job. Pumping sequence:



Pump spacer ahead Drop bottom plug Pump cement slurry Drop top plug Displace cement with drilling fluid



Schlumberger Private



• • • • •



Cement Head – Operation



Schlumberger Private



Cement Unit Schematic



Schlumberger Private