RENCANA ANGGARAN BIAYA - TWP PEKERJAAN PEMBANGUNAN RUMAH TYPE 30/72



NO.



URAIAN PEKERJAAN



VOLUME



SAT.



HARGA SAT



JUMLAH



1



2



3



4



Rp. 5



Rp. 6



I.



BOBOT PER ITEM 7



BOBOT TOTAL 8



PEKERJAAN PERSIAPAN 1



Pembersihan lokasi



72.0000



m2



740.00



53,280.00



19.68%



2



Pemasangan bouwplank & pengukuran



29.0000



m1



7,500.00



217,500.00 270,780.00



80.32% 100.00%



8.70%



Sub total



II



1.09%



PEKERJAAN TANAH DAN PONDASI 1



Pek. Galian Tanah 85 cm



14.1750



m3



15,000.00



212,625.00



2



Pek. Rucuk Bambu



16.8000



m2



6,000.00



100,800.00



4.12%



3



Pas. Pondasi batu kali 1:5



6.7270



m3



305,000.00



2,051,735.00



83.94%



4



Pek. Pondasi Conblok Rabat Beton



1.4400



m2



30,000.00



43,200.00



1.77%



5



Pek. Urugan tanah Kembali



4.7250



m3



7,600.00



35,910.00 2,444,270.00



1.47% 100.00%



Sub total



III



9.86%



PEKERJAAN BETON 1



Pek. Beton Sloof 15/20



1.0470



m3



1,200,000.00



1,256,400.00



28.98%



2



Pek. Beton kolom praktis 15/15



1.0920



m3



1,200,000.00



1,310,400.00



30.22%



3



Pek. Beton ringbalk 15/15



1.1500



m3



1,200,000.00



1,380,000.00



31.83%



4



Pek. Beton Variasi Depan



0.2240



m3



1,200,000.00



268,800.00



6.20%



5



Pek. Meja Dapur Beton



0.0720



m3



700,000.00



50,400.00



1.16%



6



Pek. Inrit Beton



0.1000



m3



700,000.00



70,000.00 4,336,000.00



Sub total



IV



1.61% 100.00%



17.48%



PEKERJAAN KUSEN DAN PINTU 1



Pek Kusen Pintu, Jendela& Bouvenlicht



0.3400



m3



2,000,000.00



680,000.00



37.86%



2



Pek Daun Pintu Double Triplek(1.6 m2)



4.0000



bh



150,000.00



600,000.00



33.41%



3



Kusen & Pintu PVC + kunci



1.0000



bh



125,000.00



125,000.00



6.96%



4



Pek. Daun Jendela (2.6416m2)



4.0000



bh



35,000.00



140,000.00



5



Pas. Rouster Kayu (lubang angin) 20 x 20



10.0000



bh



25,100.00



251,000.00 1,796,000.00



13.98% 100.00%



Sub total



V



7.80% 7.24%



PEKERJAAN DINDING 1



Pas. Dinding conblok 1:5



103.5380



m2



33,500.00



3,468,523.00



58.02%



2



Pek. Plester & acian 1: 5



146.0000



m2



14,500.00



2,117,000.00



35.41%



3



Pas. keramik dinding meja dapur 20 x 20



3.9300



m2



33,000.00



129,690.00



2.17%



4



Pas. Keramik dinding kamar mandi 20 x 25



7.0000



m2



37,500.00



262,500.00 5,977,713.00



4.39% 100.00%



24.10%



430,000.00 45,000.00 1,848,000.00 1,056,000.00 180,000.00 180,000.00 3,739,000.00



11.50% 1.20% 49.42% 28.24% 4.81% 4.81% 100.00%



15.08%



887,100.00 248,388.00 86,850.00 1,222,338.00



72.57% 20.32% 7.11% 100.00%



4.93%



Sub total VI 1 2 3 4 5 6



VII 1 2 3



PEKERJAAN ATAP Pek. Kuda-kuda + gording kayu Borneo Super Papan Ruiter, sejenis Borneo 2/15 Pek. Rangka atap Pas. Genteng beton pelat Pek. Lisplank 3/20 + tumpang sari , borneo / sejenis Pek. Bubungan Sub total PEKERJAAN PLAFOND Pek. Rangka plafond 4/6 kayu Borneo/ sejenis Pas. Plafond Eternit 1x 0.5 m 4,5mm Pas. List Plafond 3 cm



0.3440 6.0000 52.8000 52.8000 12.0000 6.0000



35.4840 35.4840 57.9000 Sub total



m3 m1 m2 m2 m1 m1



m2 m2 m1



1,250,000.00 7,500.00 35,000.00 20,000.00 15,000.00 30,000.00



25,000.00 7,000.00 1,500.00



1



2



VIII



3



4



5



1



Pek. Perataan tanah/pemadatan



2



Pek. Rabat Beton



3



Pas. keramik 30 x 30



4



Pas. keramik 20 x20 / sejenis, lantai km/WC



1 2 3



X 1 2 3



1 2 3 4 5



m2



3,500.00



105,000.00



m3



250,000.00



33,750.00



3.21%



28.6800



m2



30,000.00



860,400.00



81.81%



1.5000



m2



35,000.00



52,500.00 1,051,650.00



4.99% 100.00%



4.24%



PEKERJAAN INSTALASI AIR BERSIH - KOTOR Pek. Instalasi Air Bersih Pek. Instalasi Air Kotor PIPA PVC 4" Pek. Instalasi Air Kotor PIPA PVC 3" Sub total



10,000.00 58,500.00 50,000.00 118,500.00



8.44% 49.37% 42.19% 100.00%



0.48%



PEKERJAAN INSTALASI LISTRIK Pas. Instalasi Ttk lampu + kabel NYM Pas. Instalasi Stop kontak Pas. Box Sekering



350,000.00 250,000.00 50,000.00



53.85% 38.46% 7.69%



650,000.00



100.00%



2.62%



100,000.00 20,000.00 125,000.00 75,000.00 300,000.00 620,000.00



16.13% 3.23% 20.16% 12.10% 48.39% 100.00%



2.50%



102,510.00 45,000.00 90,000.00 45,000.00 37,500.00 25,000.00 345,010.00



29.71% 13.04% 26.09% 13.04% 10.87% 7.25% 100.00%



1.39%



1,022,000.00 311,688.00 212,904.00 1,546,592.00



66.08% 20.15% 13.77% 100.00%



6.24%



182,200.00 500,000.00 682,200.00



26.71% 73.29% 100.00%



2.75%



4.0000 9.0000 10.0000



7.0000 5.0000 1.0000



m1 m1 m1



ttk ttk bh



2,500.00 6,500.00 5,000.00



50,000.00 50,000.00 50,000.00



PEKERJAAN SANITAIR Pas. Kloset jongkok Pas. Kran 1/2 Pas. Bak Fiber Ekspos Kitchen sink Septictank + rembesan



1.0000 2.0000 1.0000 1.0000 1.0000



bh bh bh unit Unit



100,000.00 10,000.00 125,000.00 75,000.00 300,000.00



Sub total XII 1 2 3 4 5 6



PEKERJAAN GANTUNGAN Pemasangan Kaca T = 3 mm Pas. Kunci Pintu Depan Pas. Kunci Pintu Kamar & Ruang Dalam Lainnya Pas. Engsel pintu Pas. Slot & Hak angin Pas. Engsel jendela, standar



2.2780 1.0000 3.0000 6.0000 5.0000 5.0000



m2 bh bh psg set set



45,000.00 45,000.00 30,000.00 7,500.00 7,500.00 5,000.00



Sub total XIII 1 2 3



PEKERJAAN FINISHING & PENGECATAN Pek. Cat Tembok Pek. Cat Kusen/daun pintu/ jendela Pek. Cat plafond



146.0000 31.1688 35.4840



m2 m2 m2



7,000.00 10,000.00 6,000.00



Sub total XIV 1 2



8



0.1350



Sub total XI



7



30.0000



Sub total IX



6



PEKERJAAN LANTAI



PEKERJAAN TAMBAHAN Pas. Tempat sampah Pompa sumur pantek



1.0000 1.0000



bh ls



182,200.00 500,000.00



Sub total



TOTAL



24,800,053.00



(dibulatkan)



24,800,000.00



9.98%



100%



REKAPITULASI - TWP PEKERJAAN PEMBANGUNAN RUMAH TYPE 30/72 NO



URAIAN PEKERJAAN



JUMLAH



BOBOT



I



PEKERJAAN PERSIAPAN



II



PEKERJAAN TANAH DAN PONDASI



2,444,270.00



270,780.00



1.09% 9.86%



III



PEKERJAAN BETON



4,336,000.00



17.48%



IV



PEKERJAAN KUSEN DAN PINTU



1,796,000.00



7.24%



V



PEKERJAAN DINDING



5,977,713.00



24.10%



VI



PEKERJAAN ATAP



3,739,000.00



15.08%



VII



PEKERJAAN PLAFOND



1,222,338.00



4.93%



VIII



PEKERJAAN LANTAI



1,051,650.00



4.24%



IX



PEKERJAAN INSTALASI AIR BERSIH - KOTOR



118,500.00



0.48%



XI



PEKERJAAN INSTALASI LISTRIK



650,000.00



2.62%



X



PEKERJAAN SANITAIR



620,000.00



2.50%



XI



PEKERJAAN GANTUNGAN



345,010.00



1.39%



XII



PEKERJAAN FINISHING & PENGECATAN



1,546,592.00



6.24%



XIII



PEKERJAAN TAMBAHAN



682,200.00 24,800,053.00 24,800,000.00



2.75%



JUMLAH DIBULATKAN



100.00%



HARGA JUAL TYPE 30 / 72 HARGA BANGUNAN HARGA TANAH 72 m2 x Rp 525000



24,800,000.00



TOTAL HARGA JUAL TYPE 30 / 72



62,600,000.00



TERBILANG : Enam Puluh Dua Juta Enam Ratus Ribu Rupiah



37,800,000.00