RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN
: RENOVASI RUMAH TANGGA
LOKASI
: JL. BUKIT WATUWILA III D IX/10
NO
JENIS PEKERJAAN
VOL/SAT
HARGA SATUAN
1 unit
JUMLAH HARGA (Rp)
1
Pekerjaan bongkar upah tenaga bongkaran
II
PEKERJAAN ATAP
1
Pasang rangka atap baja ringan
98.65 M2
185,000
18,250,250
2
Pasang alumunium voil
98.65 M2
35,000
3,452,750
3
Pasang genteng + cat genteng
98.65 M
90,000
8,878,500
4
Pasang kardus + ban banan
5
Ganti Genteng
6
Pasang atap teras
2
28 M
10,000,000
145,000
4,060,000
2
120,000
5,918,400
30 M2
250,000
7,500,000
49.32 M
Jumlah III
48,059,900
PEKERJAAN PASANGAN, PLESTERAN, BETON
1
Pasangan Batu
114.25 M2
120,000
13,710,000
2
Plesteran + Acian
228.50 M2
75,000
17,137,500
3
Pek. Cor beton bertulang (slot, kolom, ring ball, talang)
2.86 M
3
4,500,000
12,870,000
4
Pasang lantai keramik 30x30
83.75 M2
235,000
19,681,250
Jumlah IV
63,398,750
PEKERJAAN LISTRIK
1
Pasang instalasi listrik komplit
8,500,000
V
PEKERJAAN PLAFON + CAT
1
Pek. Plafon + Lis
110.25 M2
190,000
20,947,500
2
Pek. Cat tembok
478.37 M
2
55,000
26,310,350
3
Pek. Melamin pintu jendela
20.40 M2
180,000
3,672,000
4
Pek. Cat melamin kusen
17.40 M
120,000
2,088,000
5
Pek. Cat pintu
12.80 M2
70,000
896,000
6
Pek. Cat kusen
37.15 M
50,000
1,857,500
7
Pek. Lesplang
17.15 M
90,000
1,543,500
Jumlah VI
57,314,850
PEKERJAAN KAYU
1
Pek. Pintu + daun jendela
14.55 M2
950,000
13,822,500
2
Pek. Kusen 6/5
16.50 M2
300,000
4,950,000
3
Loster kayu
12 biji
15,000
180,000
Jumlah
18,952,500
VII PEKERJAAN LAIN-LAIN 1
Tutup bak tandon
2
Pembersihan dan lain-lain
1 unit
450,000 13,000,000 Jumlah
13,450,000