3 0 93 KB
HSE-ICG/PCJ-3075-CA/JSA.002
PetroChina International Jabung Ltd. Job: Stringging Pipa 6” Sabar#2 PAD
Department : PT. IndoCipta Gemilang
Date: Tanggal :
Job Safety Analysis Title of person who does the job: Operator, HSE, Supervisor, Rigger, Flag Man
Section: Construction
Reviewed by: Work Crew Supv:
Area Supv:
F/S Supv:
Analyzed by:
Work Crew Leader Approved by:
Construction Manager
Personal protective equipment (PPE) : 1. Safety hat / helmet 2. Safety glasses 3. Goggles – ordinary 4. Goggles – tinted lenses 5. Goggles – Chemicals
√ √ √
Put
6. Face shield 7. Ear plugs / muffs 8. Dust mask
11. SCBA 12. Gloves – Ordinary 13.Gloves - Chemicals
9. Air-purifying respirator
14. Gloves – Thermal
10. Air-line respirator
15. Rubber gloves
Sequence of Basic Job Steps 1) Team Work & Communication
Write down correct specifications of personal protective equipment required (Consult HSE Dept) :
on PPE required for a safe job. 16. Safety shoes / boots 17. Rubber boots 18. Prot. Clothing / Apron 19. Body harnesses, Lline 20. Life vest
Potential Hazards
√
Protective Equipment
Safe Procedures
Misscommunication Missunderstanding Failure
1) Kerjasama dan Komunikasi
2) Prepare Document, Tools and Equipment
2) Mempersiapkan dokumen dan alat –
Kesalahan komunikasi Kesalahpahaman Terjadi kegagalan
Pinch Point Miss Comunication Missunderstanding Failure
Use hand Gloves
Terjepit
Gunakan Sarung Tangan
Page 1 of 3
Pre – Job safety meeting Discuss JSA to workers before job Discuss emergency respons preparedness to workers if emmergency situation happen Good Communication with personel Everyone has permission to stop the job Melakukan rapat keselamatan sebelum melakukan pekerjaan Membicarakan JSA kepada pekerja sebelum bekerja Membicarakan tanggap darurat ke pekerja jika terjadi situasi darurat
Be careful when pick up tools Every one must pay attention at all times Stay focused Ensure tools ready to use Ensure all document already accepted and reviewed by PCI Berhati – hati ketika mengambil
alat
Miskomunikasi Kesalahpahaman Terjadi Kegagalan
3) Secure area
Unauthorized personel Other activity in the same area
Barricade tape/safety line Warning sign
3)Mengamankan area kerja
Personil tidak berkepentingan Kegiatan lain di area kerja
Garis barricade Tanda bahaya
4) Unloading material pipe 6” from trailler by long arm excavator
Pipe fall Sling broke up Trailler reversed Pinch by pipe Excavtor Collapse
Stopper Barricade Hand gloves
4) Menurunkan material pipa 6” dari Trailler menggunakan Long Arm Excavator
Kejatuhan material Sling putus Terbalik Terjepit Excavator Amblas/Terperosok
Stopper Barricade Sarung tangan
Page 2 of 3
peralatan Setiap orang harus memperhatikan pekerjaannya dan lingkungannya setiap waktu Tetap fokus Memastikan semua peralatan siap untuk digunakan Memastikan semua dokumen telah disetujui dan dan ditinjau kembali oleh pihak PCI Supervisor must know area for work To ensure area safe for work Barricade area with tag line and give warning sign for unauthorized personel Supervisor harus mengetahui area kerja yang akan dikerjakan Memastikan area kerja aman untuk bekerja Barrikade area dengan garis barikade dan tanda bahaya Install stopper so the pipe are not lose and fall from trailler Ensure unauthorized personel do not at work location Make sure sling refer to safe load Make sure hand position do not pinch point Make sure position of trailler and excavator on safe location Make sure the material is tied properly Ensure unloding pipe 6” is directed by personel trainned Pasang stopper pada pipa Pastikan tidak ada pekerja yang tidak berkepentingan Pastikan kekuatan sling aman untuk digunakan dan tidak melebihi beban Tangan tidak berada pada titik jepit Trailler dan Excavator diposisikan di tempat aman dan rata Pastikan material terikat dengan benar Memberikan tug line untuk memandu
5) Stringging pipe 6” schedule 40 on its position
Pinch of pipe Hit by pipe Sling Broke Up
Hand Gloves
5) Menempatkan pipa 6 “ schedule 40 pada tempatnya
Terjepit pipa Tertimpa pipa Sling Putus
6) Housekeeping
Garbage
Trash bag
6) Merapikan area kerja
Sampah
Tempat Sampah
Sarung tangan
Remarks:
Page 3 of 3
mengarahkan pipa Pastikan penurunan pipa 6” material diarahkan oleh personel yang terlatih Make sure hand position do not under the pipe Use sand bag to blocks to prop Wear hand gloves Ensure the workers are at safe distance Workers unauthorized are not allowed at lifting radius Pastikan posisi tangan tidak di bawah pipa Gunakan karung pasir sebagai ganjal Gunakan sarung tangan Pekerja berada dalam jarak yang aman Pekerja yang tidak berkepentingan tidak diperbolehkan berada di radius pengangkatan Ensure there is no trash Ensure the worker use handgloves Ensure work area is clean from trash. Separate organic non-organic and Dangerous goods waste Pastikan tidak ada sampah Pastikan pekerja menggunakan sarung tangan Pastikan area kerja bersih dari sampah dan memisahkan sampah organic, non organic dan B3.