DAFTAR HARGA PELAKSANAAN BARANG DAN JASA
TAHUN ANGGARAN 2013
No
Uraian
Spesifikasi
Satuan
1
2
3
4
Harga Satuan 5
Harga Pelaksanaan
UPAH KERJA 1
Buruh / Pekerja
Orang/Hari
41,500.00
2
Tukang
Orang/Hari
63,000.00
3
Mandor
Orang/Hari
69,000.00
4
Kepala Tukang
Orang/Hari
66,000.00
1
Batu Kali / Batu Gunung
M3
129,000.00
2
Kerikil Sungai Pilihan
M3
138,000.00
3
Kerikil Sungai Tersaring
M3
138,000.00
4
Kerikil Sungai tak Tersaring
M3
138,000.00
5
Pasir Pasang/pasir beton
M3
209,200.00
6
Pasir Urug
M3
209,200.00
7
Material Timbunan
M3
85,000.00
8
Sirtu
M3
150,000.00
BAHAN / MATERIAL
9
Batu Pecah 5-7 cm
M3
229,600.00
10
Batu Pecah 3-5 cm
M3
229,600.00
11
Batu Pecah 2-3 cm
M3
229,600.00
12
Batu Pecah 1-2 cm
M3
229,600.00
13
Batu Pecah 0,5-1 cm
M3
229,600.00
14
Balok 5/7 x 4 ( Klas II)
M3
15
Balok 6/16 x 4 ( Klas I)
M3
1,800,000.00 2,500,000.00
16
Balok 6/16 x 4 ( Klas II )
M3
1,800,000.00
17
Balok 8/12 x 4 ( Klas II)
M3
1,800,000.00
18
Papan kates
M3
4,062,500.00
19
Papan Palapi
M3
2,437,500.00
20
Kayu Kls I
M3
2,500,000.00
21
Kayu Kls II
M3
1,800,000.00
22
Papan Mal Kayu Kls III
M3
1,400,000.00
23
Balok/ Kayu Kls III
M3
1,400,000.00
24
Kayu Bekisting
M3
1,929,688.00
25
Batu Bata 12 cm
Bh
731.00
26
Batu Bata 9 cm
Bh
650.00
27
Batu Bata 7 cm
Bh
650.00
28
Bataco Pres 12 cm
Bh
1,650.00
29
Bataco Pres 9 cm
Bh
1,500.00
30
Semen PC
Zak
95,700.00
1,914
31
Semen warna/Putih
Zak
120,000.00
2,400
32
Seng Gelombang BJLS 0,20
Lbr
65,000.00
33
Seng Gelombang BJLS 0,18
Lbr
60,000.00
34
Seng Plat BJLS 0,20
Lbr
75,000.00
35
Seng Plastik Gelombang Besar
Lbr
105,625.00
36
Teakwood 122 x 244 cm
Lbr
146,250.00
37
Teakwood 90 x 210 cm
Lbr
138,125.00
38
Tripleks uk. 122 x 244 cm
Lbr
70,000.00
39
Kapur
m3
195,313.00
40
Besi beton Polos / Baja Tulangan Beton
Kg
13,000.00
41
Besi beton Ø 24 mm
Kg
12,250.00
42
Besi beton Ø 32 mm ( Ulir )
Kg
14,250.00
43
Besi beton Ø 6 mm
btg
35,000.00
44
Besi beton Ø 8 mm
btg
65,000.00
45
Besi beton Ø 10 mm
btg
95,000.00
46
Besi beton Ø 12 mm
btg
125,000.00
47
Besi beton Ø 16 mm
btg
220,000.00
48
Marmerkalk
Kg
5,175.00
49
Kawat Beton / Bendrat
Kg
26,000.00
50
Kawat Bronjong
Kg
20,313.00
No
Uraian
Spesifikasi
2
3
1
Satuan 4 dos
Harga Satuan 5 150,000.00
Harga Pelaksanaan
51
Kawat Las
52
Kawat Las Listrik
Kg
40,000.00
53
Kawat Duri
Roll
156,250.00
54
Paku 2-5 cm
Kg
27,000.00
55
Paku 4-10 cm
Kg
24,375.00
56
Paku Seng Kepala Kecil
Kg
28,500.00
57
Paku Seng Kepala Besar
Kg
25,000.00
58
Paku Tripleks
Kg
28,000.00
59
Paku Jembatan
Kg
19,000.00
60
Tegel Keramik uk. 40x40 cm
Dos
69,063.00
11,050.08
61
Tegel Keramik uk. 30x30 cm
Dos
56,875.00
5,118.75
62
Tegel Keramik uk. 20x20 cm
Dos
65,000.00
2,600.00
63
Tegel Keramik uk. 20x25 cm
dos
65,000.00
3,250.00
64
Tegel Keramik uk. 10x20 cm
dos
73,125.00
1,462.50
65
Tegel Keramik Uk. 60x60 cm
Bh
125,000.00
66
Tegel Keramik Uk. 60x60 cm Biasa
Bh
67,500.00
67
Tegel Keramik Uk. 60x60 cm Permukaan Kasar
Bh
81,000.00
68
Tegel Keramik Uk. 30x30 cm Permukaan Kasar
Bh
5,750.00
69
Tegel Keramik uk. 20x25 cm
Bh
2,990.00
70
Tegel Keramik uk. 10x20 cm Ex Roman
Bh
1,196.00
71
Tegel Keramik List uk. 7.5x20 cm Ex Roman
Bh
1,196.00
72
Tegel Keramik uk. 10x30 cm Ex Roman
Bh
4,290.00
73
List keramik uk. 20x25 cm
Bh
5,000.00
74
Kuku Keramik Uk. 2x10 cm
Bh
1,500.00
75
Kaca Rayben 5mm
M2
357,500.00
76
Kaca Es 5 mm
M2
200,000.00
77
Kaca One Way 5 mm
M2
281,250.00
78
Kaca One Way 8 mm
M2
406,250.00
79
Glass Block
M2
27,812.50
80
Kunci Pintu 2 Slag
Merk Dekson
Set
187,500.00
81
Engsel Pintu 4 "
Khusus
Psg
47,500.00
23,750.00
82
Engsel Jendela 3 "
Khusus
Psg
35,000.00
17,500.00
83
Engsel Pivot
Psg
75,000.00
84
Grendel Jendela
Khusus
Bh
35,000.00
85
Hag Angin
Khusus
Psg
35,000.00
86
Kait Angin
Khusus
Psg
35,000.00
87
Full Handle Pintu
Bh
250,000.00
88
Lockset + handle
Bh
250,000.00
89
Besi Stainless Still
M1
162,500.00
90
Besi Relling Firkan
M1
406,250.00
91
Aluminium Kusen 4 " x 1.3/4 ( YKK )
M1
165,262.50
92
Paku Sekrup 3 - 5"
Dos
9,375.00
93
Gypsum Board Polos 9 mm
Lbr
75,000.00
94
List Profil Gypsum
M1
25,000.00
95
Profil Archicraf
M1
65,000.00
96
Profil Beading
M1
34,375.00
97
Closet duduk monoblock
Bh
3,687,500.00
98
Bathup Sudut
Bh
61,250,000.00
99
Bathup Panjang
Bh
17,875,000.00
100
Bidet
Bh
3,125,000.00
101
Bak Air Viber
Bh
500,000.00
102
Wastafel Under Counter
Bh
6,500,000.00
103
Zink
Bh
350,000.00
104
urinoir
Bh
500,000.00
105
Floor Drain
Bh
21,840.00
106
Floor Drain Stainless
Bh
105,000.00
107
Kran panas Dingin Shower
Unit
250,000.00
108
Kran Wudhu
Unit
275,000.00
109
Jet Shower ( Closet )
Unit
318,750.00
110
Hanger Curtain + Ring 2m
Unit
893,750.00
111
Exhaust Ø 20 cm
Unit
350,000.00
112
Soap Tray
Unit
85,000.00
EX China
merk Totto
No
Uraian
Spesifikasi
2
3
1
Satuan
113
Towel Hanger
Unit
5 350,000.00
114
Avour
Unit
371,250.00
115
Pintu Saft
Unit
250,000.00
116
Bath Up panjang
Unit
16,625,000.00
117
Kitchen Zink ( Twin )
Unit
275,000.00
118
Kran Leher angsa
Unit
325,000.00
Bh
187,500.00 437,500.00
119
Kran Shower
4
Harga Satuan
120
Kran Shower Panas Dingin
Bh
121
The Dos
Bh
3,250.00
122
Saklar tunggal
merk Brocco
Bh
43,750.00
123
Saklar ganda
merk Brocco
Bh
62,500.00
124
Saklar + Stop Kontak
merk Brocco
Bh
68,750.00
125
Stop Kontak
merk Brocco
Bh
43,750.00
126
Stop Kontak Lantai
Bh
281,250.00
127
Saklar hotel
Bh
65,625.00
128
Stop Kontak TV + Telpon
Bh
65,625.00
129
Lampu TL biasa 20 watt
Bh
37,500.00
130
Lampu TL biasa 40 watt
Bh
100,000.00
131
lampu Pijar 60 - 100 watt
Bh
6,500.00
132
Lampu TL type 52 20 watt + Frame
Bh
156,875.00
133
Lampu Philps 18 watt
Hemat Energi
Bh
43,750.00
134
Lampu Philps 8 watt
Hemat Energi
Bh
240,000.00
135
Lampu Downlight 18 watt
Bh
75,000.00
136
Lampu Downlight 14 watt
Bh
45,000.00
137
Lampu Downlight TL 2 x 20 watt RMI + frame
Bh
250,000.00
138
Lampu baret lengkap
Bh
131,250.00
139
Lampu Spot light lengkap
Bh
7,800,000.00
140
Lampu Gantung industrialight lengkap
Bh
225,000.00
141
Panel Distribusi
Bh
6,500,000.00
142
Kabel NYY 3 x 2.5 mm
Roll
1,250,000.00
143
Kabel NYY 2 x 1.5 mm
Roll
718,750.00
144
Pipa Paralon 5/8
Ljr
4,500.00
145
T DOOS PVC
Bh
3,250.00
146
Las doof
Bh
1,000.00
147
Penangkal Petir
Bh
93,750.00
148
Door Closer
Bh
450,000.00
149
Door Stoper
Bh
62,500.00
150
Batu Alam Palimanan
M2
247,500.00
151
Batu alam Paras Alur
M2
253,000.00
152
Pearl Stone Tille Ukuran 40 x 60
Bh
109,200.00
153
Accesoris Plafond
Bh
75,000.00
154
Rooster
M2
165,000.00
155
Cat Tembok
kg
45,000.00
156
Cat Ducco
kg
87,000.00
157
Cat Coating clear
kg
56,000.00
158
Bambu
Btg
10,400.00
159
Isolator
Bh
10,000.00
160
Pipa C 5/8
161
Galvalum Hollow 40 x 40
162
Atap genteng Zincalumb Type USR
163
Rumput Lamur
M2
20,000.00
164
Lantai Granit China Ukuran 60 x60 cm
Bh
357,500.00
165
Kaca Polos 3 mm
M2
121,875.00
166
Kaca Polos 5 mm
M2
146,250.00
167
Kaca Polos 3 mm ( Rayben )
M2
138,125.00
168
Kaca Polos 5 mm ( rayben )
M2
162,500.00
169
Kaca Nako Bening
Set
284,375.00
170
Kaca Nako Rayben
Set
211,250.00
171
Kunci Pintu 2 slag
Merk Kuda terbang
Bh
90,625.00
172
Kunci Pintu 2 slag
Merk Royal
Bh
73,125.00
173
Kunci Pintu Tanam
Merk yale
Bh
148,438.00
174
Engsel Pintu Nilon
psg
14,625.00
merk Catylac merk Glotex
Unico single Rib
Lonjor
4,500.00
Btg
45,000.00
M2
125,000.00
Harga Pelaksanaan
7,187.50
No
Uraian
Spesifikasi
2
3
1
Satuan
psg
5 13,000.00
Grendel Jendela
Bh
9,750.00
Hag Angin
psg
9,750.00
178
Kait Angin
psg
4,875.00
179
gagang jendela
Bh
10,313.00
180
Cat Tembok
catylac
Kg
45,000.00
181
Cat Tembok
Belmas
Kg
13,000.00
182
Cat Tembok
Paragon 20 kg
Kaleng
357,000.00
183
cat Politur
Liter
65,000.00
184
Cat marka ( Non Thermoplas )
Kg
54,688.00
185
Cat Besi
Kg
33,000.00
186
Meni kayu
Kg
23,425.00
187
Meni Besi / seng
Kg
27,325.00
188
Minyak Cat / afdunner
Ltr
31,250.00
189
Minyak Bekisting
Ltr
26,400.00
190
Plamur Tembok
Kg
13,500.00
191
Plamur Kayu
Kg
32,500.00
192
Cat Atap dan genteng
Kg
24,375.00
193
Dempul jadi
Kg
23,425.00
194
Pisau dempul
Set
24,375.00
195
Kertas pasir
Lbr
4,875.00
196
Kuas 5 "
Bh
21,125.00
197
Kuas 4 "
Bh
15,000.00
198
Kuas 3 "
Bh
8,000.00
199
Kuas 2 "
Bh
5,650.00
200
Tinner A
kg
39,000.00
201
Kuas Roll
Bh
24,375.00
202
Closet Jongkok Biasa
Merk INA
Bh
203,125.00
203
Closet Jongkok Standar
Merk INA
Bh
186,875.00
204
Closet duduk Standar
Merk INA
Bh
650,000.00
205
Kawat harmonika
M2
60,938.00
206
Krain Air 1/2"
Bh
40,625.00
207
wastafel
Bh
487,500.00
208
PIPA PVC 1/2" - 4M
Btg
34,125.00
8,531.25
209
PIPA PVC 3/4" - 4M
Btg
48,750.00
12,187.50
210
PIPA PVC 3" - 6M
Btg
570,000.00
95,000.00
211
PIPA PVC 4" - 6M
Btg
850,313.00
141,718.83
212
Pipa Besi 3/4"
Btg
75,000.00
213
Pipa Besi 4"
Btg
450,000.00
214
Besi Beugel / baut
Bh
3,906.00
215
Besi Siku Ukuran 30 x 3 mm - 6M'
Btg
121,875.00
216
Besi Siku Ukuran 40 x 3 mm - 6M'
Btg
159,250.00
217
Besi Siku Ukuran 40 x 4 mm - 6M'
Btg
227,500.00
218
Besi Siku Ukuran 50 x 4 mm - 6M'
Btg
260,000.00
219
Besi Siku Ukuran 50 x 5 mm - 6M'
Btg
316,875.00
220
Listplank ornamen
Lbr
121,875.00
221
Papan lembarseri 8 cm
btg
28,425.00
222
List profil 10 cm
Btg
56,875.00
223
List profil 6 cm
Btg
35,750.00
224
Saklar double
Bh
13,813.00
225
saklar tunggal
Bh
10,157.00
226
saklar + stop Kontak
Bh
28,425.00
227
Stop Kontak
Bh
13,813.00
228
Fitting Plafond
Bh
15,000.00
229
lampu pijar 25 watt
Bh
12,500.00
230
Lampu Neon TL 20 watt
Bh
43,125.00
231
Lampu Neon TL 40 watt ( Bambu )
Bh
115,000.00
232
Lampu Philps
Bh
43,750.00
233
lampu mercury 400 watt + stavolt
Set
481,250.00
234
Kabel NYY 2 x 1.5 mm
Roll
826,500.00
235
Kabel Listrik 50 mm 2 x4 Cok
Set
300,000.00
236
MCB 360 A Dan Accesoris
Bh
4,000,000.00
175
Engsel Jendela Nilon
176 177
4
Harga Satuan Harga Pelaksanaan
No
Uraian
Spesifikasi
2
3
1
Satuan 4
Harga Satuan
237
Box Sekring 1 fase
Bh
5 24,375.00
238
Box Sekring 2 fase
Bh
32,500.00
239
Lem kayu
kg
24,375.00
240
Besi Strip
Btg
56,875.00
241
Besi Strip
kg
10,000.00
242
Paku Sekrup 3 - 5"
Dos
11,700.00
243
Kayu Biulat Ø 8-10cm - 4m'
Btg
8,125.00
244
Kunci Tanam kamar mandi
Bh
148,425.00
245
Kunci Slot
Bh
37,500.00
246
cat residu/ter
kg
19,531.00
247
Besi Plat 3 mm
Lbr
1,625,000.00
248
Besi Plat 2 mm
Lbr
1,300,000.00
249
Besi Plat 1.2 mm
Lbr
690,625.00
250
Besi Plat 1.4 mm
Lbr
804,375.00
251
Tripleks Lapis Alumunium
Lbr
142,175.00
252
engsel Per
Bh
97,500.00
253
Kunci tanam Antik
Bh
390,625.00
254
papan Flooring
Lbr
121,875.00
255
Foons
M2
20,313.00
256
Lem Profil
Kg
97,500.00
257
Sakura Roof 2 susun
Lbr
56,875.00
258
Nok Sakura Roof
Bh
48,750.00
259
batu Alam
M2
398,125.00
260
Filler
Kg
1,300.00
261
Rooster
M2
171,875.00
262
Gypsum Polos
Lbr
89,375.00
263
Profil Gypsum
M1
20,313.00
264
Atap Aspal shet/ ondoluline
Lbr
86,125.00
265
Nok Aspal Shet
Bh
37,375.00
266
Paku Aspal shet
Bh
325.00
267
baja Profil IWF
Kg
20,313.00
268
baut baja
BH
35,750.00
269
Aspal Cement ( Grade 60/70 )
Kg
10,300.00
270
Kayu bakar
M3
150,000.00
271
Minyak diesel solar
Ltr
9,667.00
272
Minyak bensin ( Premium )
Ltr
7,721.00
273
Pelumas
Ltr
28,750.00
274
Minyak Tanah
Ltr
8,950.00
275
Air
M3
500.00
276
Formit ( Penjaga Jarak bekisting )
Bh
5,000.00
277
Paving Blok
Bh
1,200.00
278
Kawat Las LB
Kg
640,000.00
279
Kawat las RB
Kg
460,000.00
280
klem 3 x50 mm
Kg
15,000.00
281
EAL Waterproofing Epoxy
Kg
160,000.00
282
Thinner WTP
Kg
69,000.00
283
Polymide
Kg
218,500.00
284
cat residu/ter
Ltr
12,000.00
285
Baja Gelombang ( Corugated steel pipe )
286
Type Nesatble flange E-100 Ø 600 mm tebal 2 mm
M1
1,782,500.00
287
Type Nesatble flange E-100 Ø 800 mm tebal 2 mm
M1
241,250.00
288
Type Nesatble flange E-100 Ø 1000 mm tebal 2 mm
M1
2,357,500.00
Harga Pelaksanaan
Salakan ,..................2012 Penawar, PT/ CV. ...........................................
Materai 6000 .................................... Direktur / direktris
RENCANA ANGGARAN BIAYA ( RAB ) PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO.
URAIAN PEKERJAAN
SAT
VOLUME
HARGA SATUAN
JUMLAH
1
2
4
5
6
7
A 1 2 3 4 5 6 7
PEKERJAAN PENDAHULUAN Pembersihan Lokasi Pek. Pengukuran & Bowplank Pek. Kantor Direksi Pek. Bangsal Kerja Papan Nama Proyek Pek. Stelingan Mobilisasi
ls Ls m2 m2 ls ls ls
1.00 1.00 4.00 4.00 1.00 1.00 1.00
250,000.00 500,000.00 916,710.70 630,835.50 300,000.00 250,000.00 650,000.00
250,000 500,000 3,666,843 2,523,342 300,000 250,000 650,000 8,140,185
B I 1 2 3 4 5 6 7
PEKERJAAN GARASI RUJAB PEKERJAAN TANAH & BATU Pek. Galian Tanah Pondasi Garis Pek. Urugan Tanah Kembali Pek. Urugan Pasir Pondasi Garis Pek. Pas. Batu kosong Pek. Pasangan Batu Gunung 1 : 5 Pek. Urugan Tanah Bawah Lantai Pek. Urugan Pasir Bawah Lantai
m3 m3 m3 m3 m3 m3 m3
14.88 3.72 1.40 4.19 23.56 9.22 27.66
19,360.00 10,924.80 266,730.00 286,395.00 637,943.80 116,225.00 266,730.00
288,077 40,640 372,088 1,198,563 15,029,956 1,071,595 7,377,752
II 1 2 3 4 5 6
PEKERJAAN BETON Pek. Cor Lantai 1 : 3 : 5 Pek. Cor Sloof 02 15 / 20 1 : 2 : 3 Pek. Kolom K01 (25 x 25 cm) 1 : 2 : 3 Pek. Kolom K03 (15 x 15 cm) Kolom Praktis 1 : 2 : 3 Pek. Cor RingBalok RB 15 x 20 1 : 2 : 3 Pek. Cor Canopy Keliling t = 8 cm 1 : 2 : 3
m3 m3 m3 m3 m3 m3
4.61 0.93 1.88 0.20 1.25 0.22
737,491.00 3,519,837.41 3,654,744.24 4,390,471.68 3,519,837.41 4,254,012.03
III 1 2 3 3 5 7
PEKERJAAN DINDING , PLESTERAN DAN LANTAI Pek. Pas. Dinding 1/2 Batu Batako 1 : 5 Pek. Plesteran halus t = 1,5 cm 1 : 5 Pek. Plesteran Pondasi 1 : 5 Pek. Acian Pek. Pas . Lt.Keramik uk. 40 x 40 cm ( Permukaan Kasar ) Pek. Pas. Keramik Plint Uk. 10 x 40 cm
m2 m2 m2 m2 m2 m1
79.95 159.90 11.83 159.90 92.20 23.00
164,716.52 32,300.88 32,300.88 9,271.30 110,814.64 65,072.24
IV 1
PEKERJAAN KAYU, ALAT PENGGANTUNG DAN ACCESORIES TANGGA Pintu Garasi ( 15 Buah ) Pek. Kusen Kayu Kls II Pek. Pas . Daun Pintu Panil Pas.Lockset Pas. Engsel 4 " Pas. Grendel Pintu V04 Rooster (28 Buah) Pek. Kusen Kayu Kls II
25,378,671 3,399,834 3,273,449 6,852,645 889,071 4,382,198 951,197
19,748,393 13,169,086 5,164,911 381,958 1,482,481 10,217,110 1,496,662
31,912,207 2 -
m3 m2 unit Bh Bh
0.16 18.00 3.00 45.00 30.00
3,641,700.00 290,950.00 282,920.00 34,864.25 49,819.00
573,568 5,237,100 848,760 1,568,891 1,494,570 76,476 9,799,365
m3
0.02
3,641,700.00
V 1 2 3
PEKERJAAN PLAFOND Pek. Rangka Plafond 60x120 Pek. Plafond Pek. Lis Plafond
m2 m2 m'
133.88 133.88 79.60
75,320.00 37,166.50 68,594.50
10,083,842 4,975,851 5,460,122 20,519,815
VIII 1 2 3 4 5 6 7
PEKERJAAN PENGECETAN Pek. Cat Kusen Pek. Cat Daun Pintu Pek. Cat ventilasi Pek. Cat Dinding Pek. Cat pondasi Pek. Cat Plafon + Profil Pek. Cat Beton Canopy
m2 m2 m2 m2 m2 m2 m2
5.25 18.00 0.33 159.90 11.83 133.88 87.56
42,916.50 42,916.50 42,916.50 11,417.30 11,417.30 11,417.30 11,417.30
225,312 772,497 13,948 1,825,626 135,010 1,528,548 999,699
IX 1 2 3 4 5 6 7
PEKERJAAN KUDA-KUDA Kuda-kuda Rangka Atap Gording Pek. Ventilasi jalusi pek. Atap Multiroof Pas. Bumbungan pek. Lisplank 2x25X3 cm
m3 m2 m3 m3 m2 m1 m1
1.09 142.52 0.69 0.04 142.52 12.35
3,166,600.00 32,550.00 3,166,600.00 3,166,600.00 148,229.00 76,652.50 41,372.00
X 1 2 3 4 5
PEKERJAAN M/E Pek. Titik Lampu Pek. Stop Kontak Pek. Saklar Ganda Pek. Pas. Lampu Downlight Pek. Pas. MCB
titik titik bh bh bh
5.00 1.00 1.00 5.00 1.00
150,000.00 13,813.00 13,813.00 131,250.00 45,000.00
XI 1
PEKERJAAN AKHIR Pek. Pembersihan Akhir
ls
1.00
509,000.00
5,500,639
REAL COST PPN / PPH JUMLAH DIBULATKAN
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
3,465,527 4,638,993 2,190,021 120,381 21,125,449 946,658 32,487,030 750,000 13,813 13,813 656,250 45,000 1,478,876 509,000 509,000
155,474,180 15,547,418 171,021,597 171,021,000.00
REKAPITULASI PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO
URAIAN PEKERJAAN
1
A 1
I II III IV V VI VII VIII 2
2
3
PEKERJAAN PENDAHULUAN GARASI
8,140,184.80
PEK. TANAH & BATU PEK. BETON PEK. DINDING , PLESTERAN DAN LANTAI PEK. KAYU, ALAT PENGGANTUNG & ACC. TANGGA PEK. PLAFOND PEK. PENGECETAN PEKERJAAN KUDA-KUDA PEK. M/E
25,378,670.71 19,748,392.92 31,912,206.59 9,799,364.70 20,519,814.82 5,500,639.24 32,487,029.74 1,478,876.00 509,000.00
PEK. AKHIR
146,824,994.73 8,649,184.80 155,474,179.53 15,547,417.95 171,021,597.48 171,020,000.00
1. REAL COST LT I ( I + II + III +IV + V + VI + VII + VIII + IX ) 2. PEKERJAAN PENDAHULUAN + PEKERJAAN AKHIR JUMLAH ( 1 + 2 ) PPN / PPH TOTAL DIBULATKAN
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
Salakan ,..................2012 Penawar, PT/ CV. ...........................................
MATERAI 6000
Direktur/ Direktris
OWNER'S ESTIMATE ( OE ) PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO.
URAIAN PEKERJAAN
SAT
VOLUME
HARGA SATUAN
JUMLAH
1
2
4
5
6
7
A 1 2 3 4 5 6 7
PEKERJAAN PENDAHULUAN Pembersihan Lokasi Pek. Pengukuran & Bowplank Pek. Kantor Direksi Pek. Bangsal Kerja Papan Nama Proyek Pek. Stelingan Mobilisasi
ls Ls m2 m2 ls ls ls
1.00 1.00 4.00 4.00 1.00 1.00 1.00
150,000.00 500,000.00 916,710.70 630,835.50 250,000.00 150,000.00 250,000.00
150,000 500,000 3,666,843 2,523,342 250,000 150,000 250,000 7,490,185
B I 1 2 3 4 5 6 7
PEKERJAAN GARASI RUJAB PEKERJAAN TANAH & BATU Pek. Galian Tanah Pondasi Garis Pek. Urugan Tanah Kembali Pek. Urugan Pasir Pondasi Garis Pek. Pas. Batu kosong Pek. Pasangan Batu Gunung 1 : 5 Pek. Urugan Tanah Bawah Lantai Pek. Urugan Pasir Bawah Lantai
m3 m3 m3 m3 m3 m3 m3
14.88 3.72 1.40 4.19 23.56 9.22 27.66
19,360.00 10,924.80 266,730.00 286,395.00 637,943.80 116,225.00 266,730.00
288,077 40,640 372,088 1,198,563 15,029,956 1,071,595 7,377,752
II 1 2 3 4 5 6
PEKERJAAN BETON Pek. Cor Lantai 1 : 3 : 5 Pek. Cor Sloof 02 15 / 20 1 : 2 : 3 Pek. Kolom K01 (25 x 25 cm) 1 : 2 : 3 Pek. Kolom K03 (15 x 15 cm) Kolom Praktis 1 : 2 : 3 Pek. Cor RingBalok RB 15 x 20 1 : 2 : 3 Pek. Cor Canopy Keliling t = 8 cm 1 : 2 : 3
m3 m3 m3 m3 m3 m3
4.61 0.93 1.88 0.20 1.25 0.22
737,491.00 3,519,837.41 3,654,744.24 4,390,471.68 3,519,837.41 4,254,012.03
III 1 2 3 3 5 7
PEKERJAAN DINDING , PLESTERAN DAN LANTAI Pek. Pas. Dinding 1/2 Batu Batako 1 : 5 Pek. Plesteran halus t = 1,5 cm 1 : 5 Pek. Plesteran Pondasi 1 : 5 Pek. Acian Pek. Pas . Lt.Keramik uk. 40 x 40 cm ( Permukaan Kasar ) Pek. Pas. Keramik Plint Uk. 10 x 40 cm
m2 m2 m2 m2 m2 m1
79.95 159.90 11.83 159.90 92.20 23.00
164,716.52 32,300.88 32,300.88 9,271.30 110,814.64 65,072.24
IV 1
PEKERJAAN KAYU, ALAT PENGGANTUNG DAN ACCESORIES TANGGA Pintu Garasi ( 15 Buah ) Pek. Kusen Kayu Kls II Pek. Pas . Daun Pintu Panil Pas.Lockset Pas. Engsel 4 " Pas. Grendel Pintu V04 Rooster (28 Buah) Pek. Kusen Kayu Kls II
25,378,671 3,399,834 3,273,449 6,852,645 889,071 4,382,198 951,197
19,748,393 13,169,086 5,164,911 381,958 1,482,481 10,217,110 1,496,662
31,912,207 2 -
m3 m2 unit Bh Bh
0.16 18.00 3.00 45.00 30.00
3,641,700.00 290,950.00 282,920.00 34,864.25 49,819.00
573,568 5,237,100 848,760 1,568,891 1,494,570 76,476 9,799,365
m3
0.02
3,641,700.00
V 1 2 3
PEKERJAAN PLAFOND Pek. Rangka Plafond 60x120 Pek. Plafond Pek. Lis Plafond
m2 m2 m'
133.88 133.88 79.60
75,320.00 37,166.50 68,594.50
10,083,842 4,975,851 5,460,122 20,519,815
VIII 1 2 3 4 5 6 7
PEKERJAAN PENGECETAN Pek. Cat Kusen Pek. Cat Daun Pintu Pek. Cat ventilasi Pek. Cat Dinding Pek. Cat pondasi Pek. Cat Plafon + Profil Pek. Cat Beton Canopy
m2 m2 m2 m2 m2 m2 m2
5.25 18.00 0.33 159.90 11.83 133.88 87.56
42,916.50 42,916.50 42,916.50 11,417.30 11,417.30 11,417.30 11,417.30
225,312 772,497 13,948 1,825,626 135,010 1,528,548 999,699
IX 1 2 3 4 5 6 7
PEKERJAAN KUDA-KUDA Kuda-kuda Rangka Atap Gording Pek. Ventilasi jalusi pek. Atap Multiroof Pas. Bumbungan pek. Lisplank 2x25X3 cm
m3 m2 m3 m3 m2 m1 m1
1.09 142.52 0.69 0.04 142.52 12.35
3,166,600.00 32,550.00 3,166,600.00 3,166,600.00 148,229.00 76,652.50 41,372.00
X 1 2 3 4 5
PEKERJAAN M/E Pek. Titik Lampu Pek. Stop Kontak Pek. Saklar Ganda Pek. Pas. Lampu Downlight Pek. Pas. MCB
titik titik bh bh bh
5.00 1.00 1.00 5.00 1.00
150,000.00 13,813.00 13,813.00 131,250.00 45,000.00
XI 1
PEKERJAAN AKHIR Pek. Pembersihan Akhir
ls
1.00
231,000.00
5,500,639
REAL COST PPN / PPH JUMLAH DIBULATKAN
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
3,465,527 4,638,993 2,190,021 120,381 21,125,449 946,658 32,487,030 750,000 13,813 13,813 656,250 45,000 1,478,876 231,000 231,000
154,546,180 15,454,618 170,000,797 170,000,000.00
REKAPITULASI PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO
URAIAN PEKERJAAN
1
A 1
I II III IV V VIII IX X 2
2
3
PEKERJAAN PENDAHULUAN GARASI
7,490,184.80
PEK. TANAH & BATU PEK. BETON PEK. DINDING , PLESTERAN DAN LANTAI PEK. KAYU, ALAT PENGGANTUNG & ACC. TANGGA PEK. PLAFOND PEK. PENGECETAN PEKERJAAN KUDA-KUDA PEK. M/E
25,378,670.71 19,748,392.92 31,912,206.59 9,799,364.70 20,519,814.82 5,500,639.24 32,487,029.74 1,478,876.00 231,000.00
PEK. AKHIR
1. REAL COST LT I ( I + II + III +IV + V + VI + VII + VIII + IX ) 2. PEKERJAAN PENDAHULUAN + PEKERJAAN AKHIR JUMLAH ( 1 + 2 ) PPN / PPH TOTAL DIBULATKAN
146,824,994.73 7,721,184.80 154,546,179.53 15,454,617.95 170,000,797.48 170,000,000.00
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
Salakan ,..................2012 Disetujui KUASA PENGGUNA ANGGARAN
Mengetahui Pejabat Pelaksana Teknis Kegiatan
( PPTK )
HARTO NURSIN, S. SOS NIP. 19650603 198603 1 022
MUSTARIM S. NURSIN, S.Sos NIP. 19730605 200012 1 003
DAFTAR HARGA PELAKSANAAN BARANG DAN JASA
TAHUN ANGGARAN 2013 No
Uraian
Spesifikasi
Satuan
1
2
3
4
Harga Satuan 5
Harga Pelaksanaan
UPAH KERJA 1
Buruh / Pekerja
Orang/Hari
41,500.00
2
Tukang
Orang/Hari
63,000.00
3
Mandor
Orang/Hari
69,000.00
4
Kepala Tukang
Orang/Hari
66,000.00
1
Batu Kali / Batu Gunung
M3
129,000.00
2
Kerikil Sungai Pilihan
M3
138,000.00
3
Kerikil Sungai Tersaring
M3
138,000.00
4
Kerikil Sungai tak Tersaring
M3
138,000.00
5
Pasir Pasang/pasir beton
M3
209,200.00
6
Pasir Urug
M3
209,200.00
7
Material Timbunan
M3
85,000.00
8
Sirtu
M3
150,000.00
BAHAN / MATERIAL
9
Batu Pecah 5-7 cm
M3
229,600.00
10
Batu Pecah 3-5 cm
M3
229,600.00
11
Batu Pecah 2-3 cm
M3
229,600.00
12
Batu Pecah 1-2 cm
M3
229,600.00
13
Batu Pecah 0,5-1 cm
M3
229,600.00
14
Balok 5/7 x 4 ( Klas II)
M3
1,800,000.00
15
Balok 6/16 x 4 ( Klas I)
M3
2,500,000.00
16
Balok 6/16 x 4 ( Klas II )
M3
1,800,000.00
17
Balok 8/12 x 4 ( Klas II)
M3
1,800,000.00
18
Papan kates
M3
4,062,500.00
19
Papan Palapi
M3
2,437,500.00
20
Kayu Kls I
M3
2,500,000.00
21
Kayu Kls II
M3
1,800,000.00
22
Papan Mal Kayu Kls III
M3
1,400,000.00
23
Balok/ Kayu Kls III
M3
1,400,000.00
24
Kayu Bekisting
M3
1,929,688.00
25
Batu Bata 12 cm
Bh
731.00
26
Batu Bata 9 cm
Bh
650.00
27
Batu Bata 7 cm
Bh
650.00
28
Bataco Pres 12 cm
Bh
1,650.00
29
Bataco Pres 9 cm
Bh
1,500.00
30
Semen PC
Zak
95,700.00
1,914
31
Semen warna/Putih
Zak
120,000.00
2,400
32
Seng Gelombang BJLS 0,20
Lbr
65,000.00
33
Seng Gelombang BJLS 0,18
Lbr
60,000.00
34
Seng Plat BJLS 0,20
Lbr
75,000.00
35
Seng Plastik Gelombang Besar
Lbr
105,625.00
36
Teakwood 122 x 244 cm
Lbr
146,250.00
37
Teakwood 90 x 210 cm
Lbr
138,125.00
38
Tripleks uk. 122 x 244 cm
Lbr
70,000.00
39
Kapur
m3
195,313.00
40
Besi beton Polos / Baja Tulangan Beton
Kg
13,000.00
41
Besi beton Ø 24 mm
Kg
12,250.00
42
Besi beton Ø 32 mm ( Ulir )
Kg
14,250.00
43
Besi beton Ø 6 mm
btg
35,000.00
44
Besi beton Ø 8 mm
btg
65,000.00
45
Besi beton Ø 10 mm
btg
95,000.00
46
Besi beton Ø 12 mm
btg
125,000.00
47
Besi beton Ø 16 mm
btg
220,000.00
48
Marmerkalk
Kg
5,175.00
49
Kawat Beton / Bendrat
Kg
26,000.00
No
Uraian
Spesifikasi
2
3
1
Harga Satuan
Satuan 4
5
50
Kawat Bronjong
Kg
20,313.00
51
Kawat Las
dos
150,000.00
52
Kawat Las Listrik
Kg
40,000.00
53
Kawat Duri
Roll
156,250.00
54
Paku 2-5 cm
Kg
27,000.00
55
Paku 4-10 cm
Kg
24,375.00
56
Paku Seng Kepala Kecil
Kg
28,500.00
57
Paku Seng Kepala Besar
Kg
25,000.00
58
Paku Tripleks
Kg
28,000.00
59
Paku Jembatan
Kg
19,000.00
60
Tegel Keramik uk. 40x40 cm
Dos
69,063.00
11,050.08
61
Tegel Keramik uk. 30x30 cm
Dos
56,875.00
5,118.75
62
Tegel Keramik uk. 20x20 cm
Dos
65,000.00
2,600.00
63
Tegel Keramik uk. 20x25 cm
dos
65,000.00
3,250.00
64
Tegel Keramik uk. 10x20 cm
dos
73,125.00
1,462.50
65
Tegel Keramik Uk. 60x60 cm
Bh
125,000.00
66
Tegel Keramik Uk. 60x60 cm Biasa
Bh
67,500.00
67
Tegel Keramik Uk. 60x60 cm Permukaan Kasar
Bh
81,000.00
68
Tegel Keramik Uk. 30x30 cm Permukaan Kasar
Bh
5,750.00
69
Tegel Keramik uk. 20x25 cm
Bh
2,990.00
70
Tegel Keramik uk. 10x20 cm Ex Roman
Bh
1,196.00
71
Tegel Keramik List uk. 7.5x20 cm Ex Roman
Bh
1,196.00
72
Tegel Keramik uk. 10x30 cm Ex Roman
Bh
4,290.00
73
List keramik uk. 20x25 cm
Bh
5,000.00
74
Kuku Keramik Uk. 2x10 cm
Bh
1,500.00
75
Kaca Rayben 5mm
M2
357,500.00
76
Kaca Es 5 mm
M2
200,000.00
77
Kaca One Way 5 mm
M2
281,250.00
78
Kaca One Way 8 mm
M2
406,250.00
79
Glass Block
M2
27,812.50
80
Kunci Pintu 2 Slag
Merk Dekson
Set
187,500.00
81
Engsel Pintu 4 "
Khusus
Psg
47,500.00
23,750.00
82
Engsel Jendela 3 "
Khusus
Psg
35,000.00
17,500.00
83
Engsel Pivot
Psg
75,000.00
84
Grendel Jendela
Khusus
Bh
35,000.00
85
Hag Angin
Khusus
Psg
35,000.00
86
Kait Angin
Khusus
Psg
35,000.00
87
Full Handle Pintu
Bh
250,000.00
88
Lockset + handle
Bh
250,000.00
89
Besi Stainless Still
M1
162,500.00
90
Besi Relling Firkan
M1
406,250.00
91
Aluminium Kusen 4 " x 1.3/4 ( YKK )
M1
165,262.50
92
Paku Sekrup 3 - 5"
Dos
9,375.00
93
Gypsum Board Polos 9 mm
Lbr
75,000.00
94
List Profil Gypsum
M1
25,000.00
95
Profil Archicraf
M1
65,000.00
96
Profil Beading
M1
34,375.00
97
Closet duduk monoblock
Bh
3,687,500.00
98
Bathup Sudut
Bh
61,250,000.00
99
Bathup Panjang
Bh
17,875,000.00
100
Bidet
Bh
3,125,000.00
101
Bak Air Viber
Bh
500,000.00
102
Wastafel Under Counter
Bh
6,500,000.00
103
Zink
Bh
350,000.00
104
urinoir
Bh
500,000.00
105
Floor Drain
Bh
21,840.00
106
Floor Drain Stainless
Bh
105,000.00
107
Kran panas Dingin Shower
Unit
250,000.00
108
Kran Wudhu
Unit
275,000.00
109
Jet Shower ( Closet )
Unit
318,750.00
EX China
merk Totto
Harga Pelaksanaan
No
Uraian
Spesifikasi
2
3
1
Harga Satuan
Satuan 4
5
Harga Pelaksanaan
110
Hanger Curtain + Ring 2m
Unit
893,750.00
111
Exhaust Ø 20 cm
Unit
350,000.00
112
Soap Tray
Unit
85,000.00
113
Towel Hanger
Unit
350,000.00
114
Avour
Unit
371,250.00
115
Pintu Saft
Unit
250,000.00
116
Bath Up panjang
Unit
16,625,000.00
117
Kitchen Zink ( Twin )
Unit
275,000.00
118
Kran Leher angsa
Unit
325,000.00
Bh
187,500.00 437,500.00
119
Kran Shower
120
Kran Shower Panas Dingin
Bh
121
The Dos
Bh
3,250.00
122
Saklar tunggal
merk Brocco
Bh
43,750.00
123
Saklar ganda
merk Brocco
Bh
62,500.00
124
Saklar + Stop Kontak
merk Brocco
Bh
68,750.00
125
Stop Kontak
merk Brocco
Bh
43,750.00
126
Stop Kontak Lantai
Bh
281,250.00
127
Saklar hotel
Bh
65,625.00
128
Stop Kontak TV + Telpon
Bh
65,625.00
129
Lampu TL biasa 20 watt
Bh
37,500.00
130
Lampu TL biasa 40 watt
Bh
100,000.00
131
lampu Pijar 60 - 100 watt
Bh
6,500.00
132
Lampu TL type 52 20 watt + Frame
Bh
156,875.00
133
Lampu Philps 18 watt
Hemat Energi
Bh
43,750.00
134
Lampu Philps 8 watt
Hemat Energi
Bh
240,000.00
135
Lampu Downlight 18 watt
Bh
75,000.00
136
Lampu Downlight 14 watt
Bh
45,000.00
137
Lampu Downlight TL 2 x 20 watt RMI + frame
Bh
250,000.00
138
Lampu baret lengkap
Bh
131,250.00
139
Lampu Spot light lengkap
Bh
7,800,000.00
140
Lampu Gantung industrialight lengkap
Bh
225,000.00
141
Panel Distribusi
Bh
6,500,000.00
142
Kabel NYY 3 x 2.5 mm
Roll
1,250,000.00
143
Kabel NYY 2 x 1.5 mm
Roll
718,750.00
144
Pipa Paralon 5/8
Ljr
4,500.00
145
T DOOS PVC
Bh
3,250.00
146
Las doof
Bh
1,000.00
147
Penangkal Petir
Bh
93,750.00
148
Door Closer
Bh
450,000.00
149
Door Stoper
Bh
62,500.00
150
Batu Alam Palimanan
M2
247,500.00
151
Batu alam Paras Alur
M2
253,000.00
152
Pearl Stone Tille Ukuran 40 x 60
Bh
109,200.00
153
Accesoris Plafond
Bh
75,000.00
154
Rooster
M2
165,000.00
155
Cat Tembok
kg
45,000.00
156
Cat Ducco
kg
87,000.00
157
Cat Coating clear
kg
56,000.00
158
Bambu
Btg
10,400.00
159
Isolator
Bh
10,000.00
160
Pipa C 5/8
161
Galvalum Hollow 40 x 40
162
Atap genteng Zincalumb Type USR
163
Rumput Lamur
M2
20,000.00
164
Lantai Granit China Ukuran 60 x60 cm
Bh
357,500.00
165
Kaca Polos 3 mm
M2
121,875.00
166
Kaca Polos 5 mm
M2
146,250.00
167
Kaca Polos 3 mm ( Rayben )
M2
138,125.00
168
Kaca Polos 5 mm ( rayben )
M2
162,500.00
169
Kaca Nako Bening
Set
284,375.00
170
Kaca Nako Rayben
Set
211,250.00
merk Catylac merk Glotex
Unico single Rib
Lonjor
4,500.00
Btg
45,000.00
M2
125,000.00
7,187.50
No
Uraian 2
1
Spesifikasi
Harga Satuan
Satuan
3
4
5
171
Kunci Pintu 2 slag
Merk Kuda terbang
Bh
90,625.00
Harga Pelaksanaan
172
Kunci Pintu 2 slag
Merk Royal
Bh
73,125.00
173
Kunci Pintu Tanam
Merk yale
Bh
148,438.00
174
Engsel Pintu Nilon
psg
14,625.00
175
Engsel Jendela Nilon
psg
13,000.00
176
Grendel Jendela
Bh
9,750.00
177
Hag Angin
psg
9,750.00
178
Kait Angin
psg
4,875.00
179
gagang jendela
Bh
10,313.00
180
Cat Tembok
catylac
Kg
45,000.00
181
Cat Tembok
Belmas
Kg
13,000.00
182
Cat Tembok
Paragon 20 kg
Kaleng
357,000.00
183
cat Politur
Liter
65,000.00
184
Cat marka ( Non Thermoplas )
Kg
54,688.00
185
Cat Besi
Kg
33,000.00
186
Meni kayu
Kg
23,425.00
187
Meni Besi / seng
Kg
27,325.00
188
Minyak Cat / afdunner
Ltr
31,250.00
189
Minyak Bekisting
Ltr
26,400.00
190
Plamur Tembok
Kg
13,500.00
191
Plamur Kayu
Kg
32,500.00
192
Cat Atap dan genteng
Kg
24,375.00
193
Dempul jadi
Kg
23,425.00
194
Pisau dempul
Set
24,375.00
195
Kertas pasir
Lbr
4,875.00
196
Kuas 5 "
Bh
21,125.00
197
Kuas 4 "
Bh
15,000.00
198
Kuas 3 "
Bh
8,000.00
199
Kuas 2 "
Bh
5,650.00
200
Tinner A
kg
39,000.00
201
Kuas Roll
Bh
24,375.00
202
Closet Jongkok Biasa
Merk INA
Bh
203,125.00
203
Closet Jongkok Standar
Merk INA
Bh
186,875.00
204
Closet duduk Standar
Merk INA
Bh
650,000.00
205
Kawat harmonika
M2
60,938.00
206
Krain Air 1/2"
Bh
40,625.00
207
wastafel
Bh
487,500.00
208
PIPA PVC 1/2" - 4M
Btg
34,125.00
8,531.25
209
PIPA PVC 3/4" - 4M
Btg
48,750.00
12,187.50
210
PIPA PVC 3" - 6M
Btg
570,000.00
95,000.00
211
PIPA PVC 4" - 6M
Btg
850,313.00
141,718.83
212
Pipa Besi 3/4"
Btg
75,000.00
213
Pipa Besi 4"
Btg
450,000.00
214
Besi Beugel / baut
Bh
3,906.00
215
Besi Siku Ukuran 30 x 3 mm - 6M'
Btg
121,875.00
216
Besi Siku Ukuran 40 x 3 mm - 6M'
Btg
159,250.00
217
Besi Siku Ukuran 40 x 4 mm - 6M'
Btg
227,500.00
218
Besi Siku Ukuran 50 x 4 mm - 6M'
Btg
260,000.00
219
Besi Siku Ukuran 50 x 5 mm - 6M'
Btg
316,875.00
220
Listplank ornamen
Lbr
121,875.00
221
Papan lembarseri 8 cm
btg
28,425.00
222
List profil 10 cm
Btg
56,875.00
223
List profil 6 cm
Btg
35,750.00
224
Saklar double
Bh
13,813.00
225
saklar tunggal
Bh
10,157.00
226
saklar + stop Kontak
Bh
28,425.00
227
Stop Kontak
Bh
13,813.00
228
Fitting Plafond
Bh
15,000.00
229
lampu pijar 25 watt
Bh
12,500.00
230
Lampu Neon TL 20 watt
Bh
43,125.00
231
Lampu Neon TL 40 watt ( Bambu )
Bh
115,000.00
No
Uraian
Spesifikasi
2
3
1
Harga Satuan
Satuan 4
5
Bh
43,750.00
lampu mercury 400 watt + stavolt
Set
481,250.00
Kabel NYY 2 x 1.5 mm
Roll
826,500.00
235
Kabel Listrik 50 mm 2 x4 Cok
Set
300,000.00
236
MCB 360 A Dan Accesoris
Bh
4,000,000.00
237
Box Sekring 1 fase
Bh
24,375.00
238
Box Sekring 2 fase
Bh
32,500.00
239
Lem kayu
kg
24,375.00
240
Besi Strip
Btg
56,875.00
241
Besi Strip
kg
10,000.00
242
Paku Sekrup 3 - 5"
Dos
11,700.00
243
Kayu Biulat Ø 8-10cm - 4m'
Btg
8,125.00
244
Kunci Tanam kamar mandi
Bh
148,425.00
245
Kunci Slot
Bh
37,500.00
246
cat residu/ter
kg
19,531.00
247
Besi Plat 3 mm
Lbr
1,625,000.00
248
Besi Plat 2 mm
Lbr
1,300,000.00
249
Besi Plat 1.2 mm
Lbr
690,625.00
250
Besi Plat 1.4 mm
Lbr
804,375.00
251
Tripleks Lapis Alumunium
Lbr
142,175.00
252
engsel Per
Bh
97,500.00
253
Kunci tanam Antik
Bh
390,625.00
254
papan Flooring
Lbr
121,875.00
255
Foons
M2
20,313.00
256
Lem Profil
Kg
97,500.00
257
Sakura Roof 2 susun
Lbr
56,875.00
258
Nok Sakura Roof
Bh
48,750.00
259
batu Alam
M2
398,125.00
260
Filler
Kg
1,300.00
261
Rooster
M2
171,875.00
262
Gypsum Polos
Lbr
89,375.00
263
Profil Gypsum
M1
20,313.00
264
Atap Aspal shet/ ondoluline
Lbr
86,125.00
265
Nok Aspal Shet
Bh
37,375.00
266
Paku Aspal shet
Bh
325.00
267
baja Profil IWF
Kg
20,313.00
268
baut baja
BH
35,750.00
269
Aspal Cement ( Grade 60/70 )
Kg
10,300.00
270
Kayu bakar
M3
150,000.00
271
Minyak diesel solar
Ltr
9,667.00
272
Minyak bensin ( Premium )
Ltr
7,721.00
273
Pelumas
Ltr
28,750.00
274
Minyak Tanah
Ltr
8,950.00
275
Air
M3
500.00
276
Formit ( Penjaga Jarak bekisting )
Bh
5,000.00
277
Paving Blok
Bh
1,200.00
278
Kawat Las LB
Kg
640,000.00
279
Kawat las RB
Kg
460,000.00
280
klem 3 x50 mm
Kg
15,000.00
281
EAL Waterproofing Epoxy
Kg
160,000.00
282
Thinner WTP
Kg
69,000.00
283
Polymide
Kg
218,500.00
284
cat residu/ter
Ltr
12,000.00
285
Baja Gelombang ( Corugated steel pipe )
286
Type Nesatble flange E-100 Ø 600 mm tebal 2 mm
M1
1,782,500.00
287
Type Nesatble flange E-100 Ø 800 mm tebal 2 mm
M1
241,250.00
288
Type Nesatble flange E-100 Ø 1000 mm tebal 2 mm
M1
2,357,500.00
232
Lampu Philps
233 234
Harga Pelaksanaan
Salakan ,..................2012 Dihitung Oleh -
......................................................... Direktur
ENGINEER'S ESTIMATE ( EE ) PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO.
URAIAN PEKERJAAN
SAT
VOLUME
HARGA SATUAN
JUMLAH
1
2
4
5
6
7
A 1 2 3 4 5 6 7
PEKERJAAN PENDAHULUAN Pembersihan Lokasi Pek. Pengukuran & Bowplank Pek. Kantor Direksi Pek. Bangsal Kerja Papan Nama Proyek Pek. Stelingan Mobilisasi
ls Ls m2 m2 ls ls ls
1.00 1.00 4.00 4.00 1.00 1.00 1.00
150,000.00 500,000.00 916,710.70 630,835.50 250,000.00 150,000.00 250,000.00
150,000 500,000 3,666,843 2,523,342 250,000 150,000 250,000 7,490,185
B I 1 2 3 4 5 6 7
PEKERJAAN GARASI RUJAB PEKERJAAN TANAH & BATU Pek. Galian Tanah Pondasi Garis Pek. Urugan Tanah Kembali Pek. Urugan Pasir Pondasi Garis Pek. Pas. Batu kosong Pek. Pasangan Batu Gunung 1 : 5 Pek. Urugan Tanah Bawah Lantai Pek. Urugan Pasir Bawah Lantai
m3 m3 m3 m3 m3 m3 m3
14.88 3.72 1.40 4.19 23.56 9.22 27.66
19,360.00 10,924.80 266,730.00 286,395.00 637,943.80 116,225.00 266,730.00
288,077 40,640 372,088 1,198,563 15,029,956 1,071,595 7,377,752
II 1 2 3 4 5 6
PEKERJAAN BETON Pek. Cor Lantai 1 : 3 : 5 Pek. Cor Sloof 02 15 / 20 1 : 2 : 3 Pek. Kolom K01 (25 x 25 cm) 1 : 2 : 3 Pek. Kolom K03 (15 x 15 cm) Kolom Praktis 1 : 2 : 3 Pek. Cor RingBalok RB 15 x 20 1 : 2 : 3 Pek. Cor Canopy Keliling t = 8 cm 1 : 2 : 3
III 1 2 3 3 5 7
PEKERJAAN DINDING , PLESTERAN DAN LANTAI Pek. Pas. Dinding 1/2 Batu Batako 1 : 5 Pek. Plesteran halus t = 1,5 cm 1 : 5 Pek. Plesteran Pondasi 1 : 5 Pek. Acian Pek. Pas . Lt.Keramik uk. 40 x 40 cm ( Permukaan Kasar ) Pek. Pas. Keramik Plint Uk. 10 x 40 cm
IV 1
PEKERJAAN KAYU, ALAT PENGGANTUNG DAN ACCESORIES TANGGA Pintu Garasi ( 15 Buah ) Pek. Kusen Kayu Kls II Pek. Pas . Daun Pintu Panil Pas.Lockset Pas. Engsel 4 " Pas. Grendel Pintu V04 Rooster (28 Buah) Pek. Kusen Kayu Kls II
25,378,671 m3 m3 m3 m3 m3 m3
4.61 0.93 1.88 0.20 1.25 0.22
737,491.00 3,519,837.41 3,654,744.24 4,390,471.68 3,519,837.41 4,254,012.03
3,399,834 3,273,449 6,852,645 889,071 4,382,198 951,197
19,748,393 m2 m2 m2 m2 m2 m1
79.95 159.90 11.83 159.90 92.20 23.00
164,716.52 32,300.88 32,300.88 9,271.30 110,814.64 65,072.24
13,169,086 5,164,911 381,958 1,482,481 10,217,110 1,496,662
31,912,207 2 -
m3 m2 unit Bh Bh
0.16 18.00 3.00 45.00 30.00
3,641,700.00 290,950.00 282,920.00 34,864.25 49,819.00
573,568 5,237,100 848,760 1,568,891 1,494,570
m3
0.02
3,641,700.00
76,476 9,799,365
V 1 2 3
PEKERJAAN PLAFOND Pek. Rangka Plafond 60x120 Pek. Plafond Pek. Lis Plafond
m2 m2 m'
133.88 133.88 79.60
75,320.00 37,166.50 68,594.50
10,083,842 4,975,851 5,460,122 20,519,815
VIII 1 2 3 4 5 6 7
PEKERJAAN PENGECETAN Pek. Cat Kusen Pek. Cat Daun Pintu Pek. Cat ventilasi Pek. Cat Dinding Pek. Cat pondasi Pek. Cat Plafon + Profil Pek. Cat Beton Canopy
m2 m2 m2 m2 m2 m2 m2
5.25 18.00 0.33 159.90 11.83 133.88 87.56
42,916.50 42,916.50 42,916.50 11,417.30 11,417.30 11,417.30 11,417.30
225,312 772,497 13,948 1,825,626 135,010 1,528,548 999,699
IX 1 2 3 4 5 6 7
PEKERJAAN KUDA-KUDA Kuda-kuda Rangka Atap Gording Pek. Ventilasi jalusi pek. Atap Multiroof Pas. Bumbungan pek. Lisplank 2x25X3 cm
m3 m2 m3 m3 m2 m1 m1
1.09 142.52 0.69 0.04 142.52 12.35
3,166,600.00 32,550.00 3,166,600.00 3,166,600.00 148,229.00 76,652.50 41,372.00
X 1 2 3 4 5
PEKERJAAN M/E Pek. Titik Lampu Pek. Stop Kontak Pek. Saklar Ganda Pek. Pas. Lampu Downlight Pek. Pas. MCB
titik titik bh bh bh
5.00 1.00 1.00 5.00 1.00
150,000.00 13,813.00 13,813.00 131,250.00 45,000.00
750,000 13,813 13,813 656,250 45,000 1,478,876
XI 1
PEKERJAAN AKHIR Pek. Pembersihan Akhir
ls
1.00
231,000.00
231,000 231,000
5,500,639
REAL COST PPN / PPH JUMLAH DIBULATKAN
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
3,465,527 4,638,993 2,190,021 120,381 21,125,449 946,658 32,487,030
154,546,180 15,454,618 170,000,797 170,000,000.00
REKAPITULASI PROGRAM KEGIATAN PEKERJAAN LOKASI TAHUN ANGGARAN
: : : : :
PENINGKATAN SARANA DAN PRASARANA APARATUR PEMBANGUNAN GEDUNG KANTOR PEMBUATAN GARASI MOBIL RUJAB SALAKAN KEC. TINANGKUNG 2013
NO
URAIAN PEKERJAAN
1
A 1
I II III IV V VIII IX X 2
2
3
PEKERJAAN PENDAHULUAN GARASI
7,490,184.80
PEK. TANAH & BATU PEK. BETON PEK. DINDING , PLESTERAN DAN LANTAI PEK. KAYU, ALAT PENGGANTUNG & ACC. TANGGA PEK. PLAFOND PEK. PENGECETAN PEKERJAAN KUDA-KUDA PEK. M/E
25,378,670.71 19,748,392.92 31,912,206.59 9,799,364.70 20,519,814.82 5,500,639.24 32,487,029.74 1,478,876.00 231,000.00
PEK. AKHIR
146,824,994.73 7,721,184.80 154,546,179.53 15,454,617.95 170,000,797.48 170,000,000.00
1. REAL COST LT I ( I + II + III +IV + V + VI + VII + VIII + IX ) 2. PEKERJAAN PENDAHULUAN + PEKERJAAN AKHIR JUMLAH ( 1 + 2 ) PPN / PPH TOTAL DIBULATKAN
TERBILANG : SERATUS TUJUH PULUH JUTA RUPIAH
Salakan ,..................2012 Mengetahui Pejabat Pelaksana Teknis Kegiatan
Dihitung Oleh
( PPTK )
MUSTARIM S. NURSIN, S.Sos NIP. 19730605 200012 1 003
Mengetahui KUASA PENGGUNA ANGGARAN
HARTO NURSIN, S. SOS NIP. 19650603 198603 1 022
.........................................................
DAFTAR ANALISA HARGA SATUAN UNIT PRICE
HARGA SATUAN
JUMLAH HARGA
PEKERJAAN PENDAHULUAN 2
3
1 M2 Pembuatan Kantor Sementara dengan Lantai Plesteran 2.000 Org Pekerja 0.050 Org Mandor 2.000 Org Tukang Kayu 1.000 Org Tukang Batu 0.300 Org Kepala Tukang 1.250 Btg Dolken Kayu f 8-10/400 cm 0.180 M3 Kayu 0.850 Kg Paku Biasa 2-5 cm 0.850 Kg Paku Biasa 4-10 cm 1.100 Kg Besi Strip 35.000 Kg Semen Portland 0.150 M3 Pasir Pasang 0.100 M3 Pasir Beton 0.150 M3 Kerikil Beton 30.000 Bh Bata Merah 0.250 Lbr Seng Plat 1.500 Lbr Seng Gelombang 2.000 Bh Jendela Nako 0.080 M2 Kaca Polos 0.150 Bh Kunci Tanam 0.060 Lbr Plywood 4 mm
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 63,000.00 66,000.00 8,125.00 1,400,000.00 27,000.00 24,375.00 10,000.00 1,914.00 209,200.00 209,200.00 138,000.00 731.00 75,000.00 65,000.00
1 M2 Pembuatan Gudang Semen dan Alat-alat 1.000 Org Pekerja 0.050 Org Mandor 2.000 Org Tukang Kayu 0.200 Org Kepala Tukang 1.700 Btg Dolken Kayu f 8-10/400 cm 0.210 M3 Kayu 0.300 Kg Paku Biasa 10.500 Kg Semen Portland 0.030 M3 Pasir Beton 0.050 M3 Kerikil Beton 1.500 Lbr Seng Gelombang
148,438.00 70,000.00
= = = = = = = = = = = = = = = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
83,000.00 3,450.00 126,000.00 63,000.00 19,800.00 10,156.25 252,000.00 22,950.00 20,718.75 11,000.00 66,990.00 31,380.00 20,920.00 20,700.00 21,930.00 18,750.00 97,500.00 0.00 0.00 22,265.70 4,200.00 916,710.70
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 8,125.00 1,400,000.00 27,000.00 1,914.00 209,200.00 138,000.00 65,000.00
= = = = = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 3,450.00 126,000.00 13,200.00 13,812.50 294,000.00 8,100.00 20,097.00 6,276.00 6,900.00 97,500.00 630,835.50
Rp. Rp.
41,500.00 69,000.00
= Rp. = Rp. Rp.
16,600.00 2,760.00 19,360.00
1 m3 Galian Tanah Biasa sedalam 2 meter 0.526 Org/ Hr Pekerja 0.052 Org/ Hr Mandor
Rp. Rp.
50,000.00 69,000.00
= Rp. = Rp. Rp.
26,300.00 3,588.00 29,888.00
1 m3 Urugan kembali 0.192 Org/ Hr 0.019 Org/ Hr
Pekerja Mandor
Rp. Rp.
50,000.00 69,000.00
= Rp. = Rp. Rp.
9,600.00 1,324.80 10,924.80
1 m3 Urugan pasir 0.300 Org/ Hr 0.010 Org/ Hr 1.200 m3
Pekerja Mandor Pasir Urug
Rp. Rp. Rp.
50,000.00 69,000.00 209,200.00
= Rp. = Rp. = Rp. Rp.
15,000.00 690.00 251,040.00 266,730.00
Pekerja Mandor Tanah Urug
Rp. Rp. Rp.
50,000.00 69,000.00 85,000.00
= Rp. = Rp. = Rp. Rp.
12,500.00 1,725.00 102,000.00 116,225.00
Pekerja Mandor Tukang Kepala Tukang Batu Kali / Belah Pasir Urug
Rp. Rp. Rp. Rp. Rp. Rp.
50,000.00 69,000.00 63,000.00 66,000.00 129,000.00 209,200.00
= = = = = =
39,000.00 2,691.00 24,570.00 2,574.00 154,800.00 62,760.00 286,395.00
PEKERJAAN TANAH 4 1 m3 Galian Tanah Biasa sedalam 1 meter 0.400 Org/ Hr Pekerja 0.040 Org/ Hr Mandor 5
6
7
8
1m3 Urugan Tanah 0.250 0.025 1.200
Org Org M3
PEKERJAAN PONDASI 9
1 M3 Pasangan Batu Kosong 0.780 Org 0.039 Org 0.390 Org 0.039 Org 1.200 M3 0.300 M3
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
10
1 M3 Pasangan Batu Kali / Belah Camp. 1 : 5 1.500 Org Pekerja 0.075 Org Mandor 0.600 Org Tukang 0.060 Org Kepala Tukang 1.100 M3 Batu Kali / Belah 2.720 Zak Semen Portland 0.544 M3 Pasir Pasang
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
50,000.00 69,000.00 63,000.00 66,000.00 129,000.00 95,700.00 209,200.00
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
75,000.00 5,175.00 37,800.00 3,960.00 141,900.00 260,304.00 113,804.80 637,943.80
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,650.00 95,700.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
13,280.00 1,035.00 6,300.00 660.00 115,500.00 18,527.52
Rp.
209,200.00
PEKERJAAN DINDING dan PENUTUP LANTAI 12
1 M2 Pasangan Batu Bata Tebal 1/2 Batu Camp. 1 : 5 0.320 Org Pekerja 0.015 Org Mandor 0.100 Org Tukang 0.010 Org Kepala Tukang 70.000 Bh Batu Bata / Batako 0.194 Zak Semen Portland 0.045
16
18
M3
Pasir Pasang
= Rp.
9,414.00
Rp.
164,716.52
1 M2 Pasang Lantai Ubin Warna uk 40 x 40 cm ( Permukaan Kasar ) 0.2500 Org Pekerja 0.0125 Org Mandor 0.120 Org Tukang Batu 0.0120 Org Kepala Tukang 11.8700 Bh Ubin Warna 40 x 40 cm 0.1672 Zak Semen Portland 0.0230 M3 Pasir Pasang 0.9000 Kg Semen Warna
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 5,750.00 95,700.00 209,200.00 2,400.00
= = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
10,375.00 862.50 7,560.00 792.00 68,252.50 16,001.04 4,811.60 2,160.00 110,814.64
1 M' Pasang Plint Ubin Teralux Kerang uk 10 x 40 cm 0.900 Org Pekerja 0.045 Org Mandor 0.090 Org Tukang Batu 0.009 Org Kepala Tukang 3.330 Bh Plint Ubin Uk. 10 x 40 cm
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 4,290.00
= = = = =
Rp. Rp. Rp. Rp. Rp.
37,350.00 3,105.00 5,670.00 594.00 14,285.70
0.033 0.0032 0.100
Zak M3 Kg
Semen Portland Pasir Pasang Semen Warna
Rp. Rp. Rp.
95,700.00 209,200.00 2,400.00
= Rp. = Rp. = Rp. Rp.
3,158.10 669.44 240.00 65,072.24
1 m2 Plesteran Tebal 15 mm, Camp. 1 : 5 0.200 Org Pekerja 0.010 Org Mandor 0.150 Org Tukang Batu 0.015 Org Kepala Tukang 0.086 Zak Semen Portland 0.022 m3 Pasir Pasang
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 95,700.00 209,200.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
8,300.00 690.00 9,450.00 990.00 8,268.48 4,602.40 32,300.88
Rp. Rp. Rp. Rp. Rp.
95,700.00
= = = = =
Rp. Rp. 66,000.00 Rp. 41,500.00 Rp. 69,000.00 Rp. Jumlah Rp.
3,253.80 5,040.00 528.00 415.00 34.50
PEKERJAAN PLESTERAN 19
20
1 m2 Pekerjaan Acian 1 : 7 0.0340 Zak Org 0.0800 Org 0.0080 Org 0.0100 Org 0.0005
Semen PC Tukang Batu Kep.Tukang Batu Pekerja Mandor
63,000.00
9,271.30
PEKERJAAN KAYU 21
22
24
25
27
1 m3 Pasang Kusen Pintu dan Jendela Kayu Jati / Kls II 6.000 Org Pekerja 0.300 Org Mandor 20.000 Org Tukang Kayu 2.000 Org Kepala Tukang 1.100 m3 Kayu Jati (Balok) 1 m2 Pasang Pintu Panel Kayu Jati / Kls II 1.000 Org Pekerja 0.050 Org Mandor 2.500 Org Tukang Kayu 0.250 Org Kepala Tukang 0.040 m3 Kayu Jati (papan) 1 m3 Pasang Konstruksi Kuda-Kuda Kayu Jati / Kls II 4.000 Org Pekerja 0.200 Org Mandor 12.000 Org Tukang Kayu 1.200 Org Kepala Tukang 1.1000 m3 Kayu Jati, Balok 15.000 Kg Besi Strip 0.800 Kg Paku Biasa 2" - 5" 1 m2 Pasang Rangka 0.200 0.010 0.300 0.030 0.0230 0.150
Langit-Langit Org Org Org Org m3 Kg
60 x 60) m, Kayu Jati Pekerja Mandor Tukang Kayu Kepala Tukang Kayu Kls II Paku Biasa 2" - 5"
1 m' Pasang Listplank 0.110 0.005 0.220 0.022 0.0110 0.050
Ukuran (3 x 30) cm, Kayu Jati Org Pekerja Org Mandor Org Tukang Kayu Org Kepala Tukang m3 Kayu Jati, Papan Kg Paku Biasa 2" - 5"
Kls II
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,800,000.00
= = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
249,000.00 20,700.00 1,260,000.00 132,000.00 1,980,000.00 3,641,700.00
Kls II
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,800,000.00
= = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 3,450.00 157,500.00 16,500.00 72,000.00 290,950.00
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,800,000.00 10,000.00 27,000.00
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
166,000.00 13,800.00 756,000.00 79,200.00 1,980,000.00 150,000.00 21,600.00 3,166,600.00
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,800,000.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
8,300.00 690.00 18,900.00 1,980.00 41,400.00 4,050.00 75,320.00
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,800,000.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
4,565.00 345.00 13,860.00 1,452.00 19,800.00 1,350.00 41,372.00
Rp. Rp.
41,500.00 69,000.00
= Rp. = Rp.
68,475.00 5,520.00
Kls II
PEKERJAAN BETON 28
1 m3 Membuat Beton Tumbuk, 1 Pc : 3 Psr : 5 Krkl 1.650 Org Pekerja 0.080 Org Mandor
0.250 0.025 4.360 0.520 0.8700 29
30
31
32
33
34
35
Org Org Zak m3 m3
Tukang Batu Kepala Tukang Semen Portland Pasir Beton Kerikil Beton
Rp. Rp. Rp. Rp. Rp.
63,000.00 66,000.00 95,700.00 209,200.00 138,000.00
= = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
15,750.00 1,650.00 417,252.00 108,784.00 120,060.00 737,491.00
1 m3 Membuat Beton Bertulang 1 Pc : 2 Psr : 3 Krkl 1.650 Org Pekerja 0.080 Org Mandor 0.250 Org Tukang Batu 0.025 Org Kepala Tukang 4.640 Zak Semen Portland 0.520 m3 Pasir Beton 0.780 m3 Kerikil Beton
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 95,700.00 209,200.00 138,000.00
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
68,475.00 5,520.00 15,750.00 1,650.00 444,048.00 108,784.00 107,640.00 751,867.00
1 Kg Pembesian dengan Besi Polos atau Besi Ulir 0.007 Org Pekerja 0.0003 Org Mandor 0.007 Org Tukang Batu 0.0007 Org Kepala Tukang 1.050 Kg Besi Beton (Polos/Ulir) 0.015 Kg Kawat Beton
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 13,000.00 26,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
290.50 20.70 441.00 46.20 13,650.00 390.00 14,838.40
1 m2 Pasang Bekisting untuk Pondasi 0.300 Org Pekerja 0.005 Org Mandor 0.260 Org Tukang Batu 0.026 Org Kepala Tukang 0.040 M3 Kayu Terentang 0.300 Kg Paku Biasa 2" - 5" 0.100 Ltr Minyak Bekisting
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 950,000.00 26,000.00 14,843.75
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
12,450.00 345.00 16,380.00 1,716.00 38,000.00 7,800.00 1,484.38 78,175.38
1 m2 Pasang Bekisting untuk Sloof 0.300 Org Pekerja 0.005 Org Mandor 0.260 Org Tukang Batu 0.026 Org Kepala Tukang 0.045 M3 Kayu Terentang 0.300 Kg Paku Biasa 2" - 5" 0.100 Ltr Minyak Bekisting
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,400,000.00 27,000.00
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
12,450.00 345.00 16,380.00 1,716.00 63,000.00 8,100.00 0.00 101,991.00
1 m2 Pasang Bekisting untuk Kolom 0.300 Org Pekerja 0.006 Org Mandor 0.330 Org Tukang Batu 0.033 Org Kepala Tukang 0.040 M3 Kayu Terentang 0.400 Kg Paku Biasa 2" - 5" 0.200 Ltr Minyak Bekisting 0.015 M3 Balok Kayu Kls III 0.350 Lbr Plywood tebal 9 mm 2.000 Btg Dolken Kayu f 8 - 10/4
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,400,000.00 27,000.00 0.00 1,400,000.00 146,250.00 8,125.00
= = = = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
12,450.00 414.00 20,790.00 2,178.00 56,000.00 10,800.00 0.00 21,000.00 51,187.50 16,250.00 191,069.50
1 m2 Pasang Bekisting untuk Balok 0.320 Org Pekerja 0.006 Org Mandor 0.330 Org Tukang Batu 0.033 Org Kepala Tukang 0.040 M3 Kayu Terentang 0.400 Kg Paku Biasa 2" - 5" 0.200 Ltr Minyak Bekisting 0.018 M3 Balok Kayu Kls II 0.350 Lbr Plywood tebal 9 mm 2.000 Btg Dolken Kayu f 8 - 10/4
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,400,000.00 27,000.00 0.00 1,400,000.00 146,250.00 8,125.00
= = = = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
13,280.00 414.00 20,790.00 2,178.00 56,000.00 10,800.00 0.00 25,200.00 51,187.50 16,250.00 196,099.50
1 m2 Pasang Bekisting untuk Lantai 0.320 Org Pekerja 0.006 Org Mandor 0.330 Org Tukang Batu 0.033 Org Kepala Tukang 0.040 M3 Kayu Terentang 0.400 Kg Paku Biasa 2" - 5" 0.200 Ltr Minyak Bekisting 0.015 M3 Balok Kayu Kls III 0.350 Lbr Plywood tebal 9 mm 6.000 Btg Dolken Kayu f 8 - 10/4
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 1,400,000.00 27,000.00 0.00 1,400,000.00 146,250.00 8,125.00
= = = = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
13,280.00 414.00 20,790.00 2,178.00 56,000.00 10,800.00 0.00 21,000.00 51,187.50 48,750.00 224,399.50
38
1 m3 Membuat Sloof Beton Bertulang 15/20 ( 156 Kg Besi + Bekisting) 1.00 156.00 4.44
43
Rp. Rp. Rp.
751,867.00 14,838.40 101,991.00
= Rp. = Rp. = Rp. Rp. Rp.
751,867.00 2,314,790.40 453,180.01 3,519,837.41 4,622,447.36
M3 Kg M2
Beton 1 : 2 : 3 Besi Beton Polos Bekisting
Rp. Rp. Rp.
751,867.00 14,838.40 191,069.50
= Rp. = Rp. = Rp. Rp.
751,867.00 2,789,619.20 848,985.48 4,390,471.68
Rp. Rp. Rp.
751,867.00 14,838.40 191,069.50
= Rp. = Rp. = Rp. Rp.
751,867.00 1,884,476.80 1,018,400.44 3,654,744.24
Rp. Rp. Rp.
751,867.00 14,838.40 196,099.50
= Rp. = Rp. = Rp. Rp.
751,867.00 2,344,467.20 958,926.56 4,055,260.76
1 m3 Membuat Kolom 25/25( 127 Kg Besi + Bekisting) 1.000 127.000 5.330
46
Beton 1 : 2 : 3 Besi Beton Polos Bekisting
1 m3 Membuat Kolom Beton Bertulang 15/15 (188 Kg Besi + Bekisting) 1.0000 188.00 4.44
44
M3 Kg M2
M3 Kg M2
Beton 1 : 2 : 3 Besi Beton Polos Bekisting
1 m3 Membuat Ringbalk Beton Bertulang 15/20 ( 158 Kg Besi + Bekisting) 1.000 158.000 4.890
M3 Kg M2
Beton 1 : 2 : 3 Besi Beton Polos Bekisting
PEKERJAAN PENUTUP ATAP 50
51
1 m2 Pasang Atap Genteng Metal 0.200 Org 0.001 Org 0.100 Org 0.010 Org 1.020 Bh 0.200 Kg
Pekerja Mandor Tukang Kayu Kepala Tukang Genteng Metal Paku Biasa 2" - 5"
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 125,000.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
8,300.00 69.00 6,300.00 660.00 127,500.00 5,400.00 148,229.00
1 m' Pasang Nok Genteng Metal 0.250 Org 0.013 Org 0.150 Org 0.015 Org 1.100 Bh 0.050 Kg
Pekerja Mandor Tukang Kayu Kepala Tukang Genteng Decra Bond Paku Biasa 1/2" - 1"
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 48,750.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
10,375.00 862.50 9,450.00 990.00 53,625.00 1,350.00 76,652.50
1 m2 Langit-Langit Teakwood (60 x 120) cm, tebal 4 mm 0.070 Org Pekerja 0.0035 Org Mandor 0.100 Org Tukang Kayu 0.010 Org Kepala Tukang 0.375 Lbr Teakwood 4' x 8' x 4 mm 0.030 Kg Paku
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 70,000.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
2,905.00 241.50 6,300.00 660.00 26,250.00 810.00 37,166.50
1 m2 List Langit-Langit Kayu Profil 10 Cm 0.050 Org Pekerja 0.003 Org Mandor 0.050 Org Tukang Kayu 0.005 Org Kepala Tukang 1.100 M List Kayu Profil 0.010 Kg Paku
Rp. Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 56,875.00 27,000.00
= = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp.
2,075.00 207.00 3,150.00 330.00 62,562.50 270.00 68,594.50
PEKERJAAN LANGIT-LANGIT 52
53
Rp.
48,771.25
PEKERJAAN KUNCI DAN KACA 61
63
64
65
67
1 Buah Pasang Grendel Tanam 0.020 Org 0.00100 Org 0.200 Org 0.020 Org 1.000 Bh
Pekerja Mandor Tukang kayu Kepala Tukang Grendel tanam
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 35,000.00
= = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
830.00 69.00 12,600.00 1,320.00 35,000.00 49,819.00
1 M2 Pasang Kaca Tebal 5 mm Polos 0.015 Org Pekerja 0.00075 Org Mandor 0.150 Org Tukang Las 0.015 Org Kepala Tukang 1.100 M2 Kaca
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 146,250.00
= = = = =
Rp. Rp. Rp. Rp. Rp. Rp.
622.50 51.75 9,450.00 990.00 160,875.00 171,989.25
= = = =
Rp. Rp. Rp. Rp.
415.00 345.00 31,500.00 660.00
= Rp. Rp.
250,000.00 282,920.00
1 Buah Pasang Lockset + Handle 0.0100 0.0050 0.5000 0.0100
Org Org Org Org
Pekerja Mandor Tukang Las Kepala Tukang
Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00
1.0000
Bh
Lock Set + Handle
Rp.
250,000.00
1 Buah Pasang Engsel Pintu 4" 0.0150 0.0008 0.1500 0.0150
Org Org Org Org
Pekerja Mandor Tukang Las Kepala Tukang
Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00
= = = =
Rp. Rp. Rp. Rp.
622.50 51.75 9,450.00 990.00
1.0000
Bh
Engsel Pintu
Rp.
23,750.00
= Rp. Rp.
23,750.00 34,864.25
Pekerja Mandor Tukang Kepala Tukang Kait Angin
Rp. Rp. Rp. Rp. Rp.
41,500.00 69,000.00 63,000.00 66,000.00 35,000.00
= = = = =
622.50 51.75 9,450.00 990.00 35,000.00 46,114.25
1 Buah Pasang hag Angin 0.015 Org 0.00075 Org 0.150 Org 0.015 Org 1.000 Bh
Rp. Rp. Rp. Rp. Rp. Rp.
PEKERJAAN PENGECATAN 70
71
1 M2 Pengecatan Bidang Kayu Baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup 0.070 Org Pekerja Rp. 0.0025 Org Mandor Rp. 0.105 Org Tukang Cat Rp. 0.0040 Org Kepala Tukang Rp. 0.2000 Kg Cat Meni Rp. 0.1500 Kg Plamir Rp. 0.1700 Kg Cat Dasar Rp. 0.3500 Kg Cat Penutup 3 Kali Rp.
41,500.00 69,000.00 63,000.00 66,000.00 23,425.00 32,500.00 45,000.00 45,000.00
= = = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
2,905.00 172.50 6,615.00 264.00 4,685.00 4,875.00 7,650.00 15,750.00 42,916.50
1 M2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) 0.020 Org Pekerja Rp. 0.0025 Org Mandor Rp. 0.063 Org Tukang Cat Rp. 0.0063 Org Kepala Tukang Rp. 0.1000 Kg Plamir Rp. 0.1000 Kg Cat Dasar Rp. 0.2600 Kg Cat Penutup 2 x Rp.
41,500.00 69,000.00 63,000.00 66,000.00 13,500.00 13,000.00 13,000.00
= = = = = = =
Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.
830.00 172.50 3,969.00 415.80 1,350.00 1,300.00 3,380.00 11,417.30
1 4 3 3 5 29 25 105 94 36 19 19 18 32 102 53 65 112 1 4 3 5 29 25 105 36 19 18 101
1 4 1 4 1 4 1 4 20 1 4 22
1 4 3 5 14 20
22
#REF!
1 4 3 5 14 36 19
1 4 3 5 34 36 19
72 72
871.609 871.609 871.609 871.609 871.609 871.609
278.9149 13.07414 87.1609 8.71609 61012.63 168.7435
72
871.609 39.22241
#REF!
kebutuhan bahan #REF! 13.939 3.240
sak
1 4 3 5 36 19
19,430.00
1 4 3 5 24 1 4 3 5 24 1 4 3 5 24 94 104 1 4 3 5 24 106
1 4
0.9 0.1725
3 5 36 19 18
0.1575 116,155
1 4 3 5 36 19 18 1 4 3 5 77 85 1 4 3 5 28 104 187 1 4 3 5 28 104 187 1 4 3 5 28 104 187 25 233 29 1 4 3 5 28 104 187 25 233 29 1 4 3 5 28 104 187 25 233 29
552.89 24.88005 552.89 165.867 552.89 55.289
#REF! #REF!
552.89 22.1156 552.89 221.156 552.89 110.578 552.89 8.29335 552.89 193.5115 552.89 1105.78
62.5 sloof 62.5 kolom
#REF! #REF!
5.76 5.76 5.76 0.03 33.33333333
#REF! 133.3333333
#REF!
22
#REF! #REF!
#REF! #REF!
#REF!
#REF! #REF!
1 4 3 5 98 104 1 4 3 5 100 104
1 4 3 5 119 104
1 4 3 5 65 1 4 3 5 56
1 4 3 5 190 188 182
4d12 Pek. Cor Sloof 01 15 / 20 1 : 2 : 3 Pek. Cor Sloof 02 30 / 40 1 : 2 : 3 Pek. Kolom K01 (40 x 50 cm) 1 : 2 : 3 Pek. Kolom K02 (25 x 25 cm) 1 : 2 : 3 Pek. Kolom K03 (20 x 50 cm) 1 : 2 : 3 Pek. Kolom K04 (15 x 30 cm) 1 : 2 : 3 Pek. Kolom K05 (15 x 15 cm) Kolom Praktis 1 : 2 : 3 Pek. Sunscreen ( 10 x 20 cm ) Pek. Cor RingBalok RB 01 15 x 20 1 : 2 : 3 Pek. Cor RingBalk RB 02 30 x 40
1:2:3
Pek. Cor Balok RB03 15 x 30
1:2:3
Pek. Cor Balok RB04 15 x 55
1:2:3
kolom praktis 15x15 44.44444444 177.7777778
beugel 158.2222222
33.33333333
133.3333333
118.6666667
3.472
48
0.4
66.6624
15/20 33.33333333
133.3333333
118.2912
0.8
223.2222
178.5778
177.7777778
157.7216
0.7
297.2963
208.1074
66.66666667
59.1456
1.5
56.55556
84.83333
5
60
53.23104
1.9
34.33333
65.23333
16
96
85.169664
1.1
107.6667
118.4333
10
100
88.7184
1.5
67.66667
101.5
22.22222222
133.3333333
118.2912
1
149.1481
149.1481
50
200
123.22
0.7
334.3333
234.0333
12.12121212
96.96969697
86.0299636
1.5
81.80808
122.7121
15/15 44.44444444
30/40 8.333333333
40/50 25/25 20/50 15/30 10x20 15/55
pondasi poer plat 80x80
tinggi 30 cm 6.4
1.5
33.811568
28 28
9.6
42
50.717352
1
187.6667
m1 jmlh btg 33.33333333 4 8.333333333 10 5 10 16 8 10 8 22.22222222 6 44.44444444 4 50 4 33.33333333 4 8.333333333 10 33.33333333 6 12.12121212 8
133.3333333 83.33333333 50 128 80 133.3333333 177.7777778 200 133.3333333 83.33333333 200 96.96969697
berat besi/kg 0.89 118.6666667 0.89 74.16666667 0.89 44.5 0.89 113.92 0.89 71.2 0.89 118.6666667 0.89 158.2222222 0.89 178 0.89 118.6666667 0.89 74.16666667 0.89 178 0.89 86.3030303
beugel kg kg kg kg kg kg kg kg kg kg kg kg
Ø8-20 2.222222222
24
53.33333333
211.5555556 kg
1.666666667
24
40
158.6666667 kg
beugel 70.4139321
188.7051321
82.0575832
239.7791832
33.4501227
92.59572267
25.7217643
78.95280427
46.6987371
131.8684011
40.021856
128.740256
58.8097114
177.1009114
51.9076572
175.1276572
48.3858802
134.4158439
d8-16
0.000156
7 0.001094
Total berat Besi/kg
0.006165
144
44.44444444
39.456
0.006165
144
33.33333333
29.592