DAFTAR PERHITUNGAN BAHAN DAN UPAH Jenis Kegiatan : Jalan Rabat Beton
Desa : UPAH
No
Sket Gambar
Perhitungan Volume
BAHAN
Pekerja
Tukang
Bt Pch 2/3
Bt Pch 5/7
Semen
Ps-B
HOK
HOK
m3
m3
zak
m3
Analisa Bangkim Kab. Garut Th 2014 (K-225) 1. Rabat Beton
LEBAR PERKERASAN
1
=
1.50
x
=
0.23
m3
V Pas. Tot =
0.23
=
14
1,50 m
Urugan Tanah 0.5 x 0.12 6-8 % 4-5 %
CL
Rabat Beton ( L = 1.5 m T = 12 cm ) Camp. (1Pc : 3Ps: 5Kr) Urugan Tanah (Biaya Swadaya)
4-5 %
1.00
x
63.00
m
23.39
5.53
3.17
-
-
-
0.15
6-8 %
Lantai Kerja Urugan Pasir ( t = 5 cm )
x m3
Konstruksi Existing (Tanah) Bahu Jalan yang ada telah padat
URAIAN
KOEF
SAT
BAHAN 1.50
Bt Pecah 2/3
0.7760
m3
Semen (50kg)
7.4200
zak
Pasir
0.4990
m3
Bt Pecah 5/7
m3
UPAH 1.00
Pekerja
1.6500
Tukang
0.3900
OH
Molen
0.1000
hari
vibro
OH
-
hari
2. Hamparan Pasir untuk Lantai Kerja ( t = 5 cm ) = 2
1.50
V Tot = URAIAN
x
0.05
x
63
4.73 KOEF
SAT
1.34
m3
0.5000
HOK
BAHAN Pasir Urug UPAH Pekerja
3
3. Hamparan Sirtu U/ Bahu ( Kiri dan Kanan ) =
-
V Tot = URAIAN BAHAN
x
0.50
KOEF
SAT
x
0.12
11.00
-
105.18
7.07
Saluran
Bahu
0.50
0.50
Sirtu
1.34
m3
0.5000
HOK
UPAH Pekerja
4. Galian Saluran/ Bahu =
-
x
0.50
,+ 2
0.50
= URAIAN
0.30
-
0.30
x
0.50
M3
KOEF
SAT
Upah Pekerja
0.50
HOK
JUMLAH
26.55
5.53
11.00
-
105.18
7.07
DAFTAR PERHITUNGAN BAHAN DAN UPAH Jenis Kegiatan : Jalan Rabat Beton
Desa : ....................... UPAH
No
Sket Gambar
Perhitungan Volume
4
5. Bekisting 1.50
1. Memanjang 2. Melintang =
Tukang
Besi o 10
Paku
Kawat
Papan
HOK
HOK
Btg
Kg
Kg
M3
x
32
x
0.15
m3
63
:
2.00
x
1.50
x
0.15
x
1.50
x
0.15
x
1.50
x
0.15
+
0.15
33
=
0.15
3.40
0.34
63 m'
0.189
= Total =
2
= 2.00
=
5
Pekerja
3.26
Asumsi yang dipakai
BAHAN
=
x
0.020
x
0.020
32
m3
0.34 m3
Pekerja =
63
=
14.18
=
32
6. Paku = URAIAN
0.71
7.09 KOEF
SAT
0.1
Kg
Pekerja
0.2300
HOK
Tukang
0.2400
HOK
BAHAN Paku UPAH
7. Plastik = = URAIAN
63
x(
1.50
+
0.15 )
113.40 KOEF
SAT
1.05
m2
BAHAN Plastik ( PPK III 2005 dan BINA MARGA )
JUMLAH
3.26
3.40
-
0.71
-
0.34
.......................
Ps- U
Sirtu
Molen
m3
m3
LS 1.42
6.33
-
6.33
-
1.42
Sirtu
Plastik
M3
M2
119
-
119
RENCANA ANGGARAN BIAYA DESA SUKAWENING KECAMATAN SUKAWENING TAHUN 2017
Kegiatan
: Pembangunan Jalan Lingkungan Rabat Beton
Volume
: 100 M x 1,5M x 0,15M
Waktu Pelaksanaan
:
No
U R A I A N
V o l u m e
Harga Satuan (Rp)
Total Biaya (Rp)
1
2
3
4
5
A.
B A H A N
1 Semen @ 50 Kg
105.0 Zak
60,000
6,300,000
2 Pasir Beton
7.0 M3
300,000
2,100,000
3 Pasir Urug
6.0 M3
300,000
1,800,000
4 Batu Pecah 2/3
11.0 M3
300,000
3,300,000
850,000
-
20,000
40,000
Sub Total 1)
13,540,000
5 Papan Bekisting
-
6 Paku
B.
M3
2.0 Kg
A L A T
1 Papan Proyek
1.0 Ls
100,000
100,000
2 Prasasti
1.0 Ls
150,000
150,000
4 Roda Sorang
1.0 Buah
500,000
500,000
5 Meteran 5 m'
1.0 Buah
25,000
25,000
6 Sekop
2.0 Buah
75,000
150,000
7 Ember
30.0 Buah
10,000
300,000
8 Benang
3.0 Rol
5,000
15,000
9 Cangkul
1.0 Buah
70,000
70,000
Sub Total 2)
1,310,000
C.
U P A H
1 Pekerja
30.0 HOK
100,000
3,000,000
2 Tukang
9.0 HOK
120,000
1,080,000
Sub Total 3)
4,080,000
1,050,000
500,000
Sub Total 4)
500,000
D.
Honor TPK 1 Honor TPK
1.0 Paket TOTAL BIAYA
19,430,000 PPN 10 % Jumlah
1,943,000 21,373,000
323,833
FIX
Kegiatan
:
Pembangunan Jalan Lingkungan Rabat Beton
Volume
:
100 M x 1,5M x 0,15M
Waktu Pelaksanaan
:
URAIAN 2
Volume 3
Harga Satuan (Rp)
Total Biaya (Rp)
4
5
105 Zak
60,000
6,300,000
Pasir Beton
9 M3
300,000
2,700,000
Pasir Urug
7 M3
300,000
2,100,000
Batu Pecah 2/3
10 M3
300,000
3,000,000
Papan Bekisting
0 M3
850,000
-
Paku
2 Kg
20,000
40,000
BAHAN Semen @ 50 Kg
14,140,000 ALAT Papan Proyek
1 Ls
100,000
100,000
Prasasti
1 Ls
150,000
150,000
Roda Sorang
1 Buah
500,000
500,000
Meteran 5 m'
1 Buah
25,000
25,000
Sekop
2 Buah
75,000
150,000
Ember
27 Buah
10,000
270,000
Benang
3 Rol
5,000
15,000
Cangkul
1 Buah
70,000
70,000 1,280,000
UPAH Pekerja
30 HOK
100,000
3,000,000
Tukang
9 HOK
120,000
1,080,000
4,080,000 Honor TPK Honor TPK
1 Paket
500,000
500,000 500,000 20,000,000
PPN 10 % Jumlah
1,943,000 21,373,000