LAPORAN PERHITUNGAN STRUKTUR RUMAH 2 LANTAI



DAFTAR ISI



Data Umum..................................................................................................................................... 1 Perhitungan Sloof dan Balok.......................................................................................................... 3 Perhitungan Kolom....................................................................................................................... 28 Perhitungan Pelat Lantai .............................................................................................................. 39 Perhitungan Pondasi .................................................................................................................... 43



Perhitungan Struktur Rumah 2 Lantai



PERHITUNGAN STRUKTUR RUMAH 2 LANTAI A. -



-



-



B. -



Data Permodelan Material properties F'c = Fy = Fys = Ec =



-



Mpa Mpa Mpa Mpa



Frame Section K1 K2 K3 KP Sloof Balok Ring Balok Balok Anak



= = = = = = = =



150 150 150 150 150 150 150 150



Wall/Slab Plat lantai Plat lantai atap



= =



120 mm 100 mm



x x x x x x x x



300 250 200 150 300 300 250 250



mm mm mm mm mm mm mm mm



(floor deck) (floor deck)



Pembebanan Beban Pada Pelat Lantai (Berdasarkan PPIUG) Beban Mati Keramik = 24 Kg/m² Spesi = 21 Kg/m² Plafond = 11 Kg/m² utilitas = 25 Kg/m² Total = 81 Kg/m² Beban Hidup



-



25 400 240 23500



=



200 Kg/m²



Beban Pada Balok lantai 1 (Berdasarkan PPIUG) Beban Mati Tinggi dinding = 3.25 m Dinding ⅟2 bata = 250 Kg/m² x 3.25 =



812.5 Kg/m



Beban Pada Balok lantai 2 (Berdasarkan PPIUG) Beban Mati Tinggi dinding = 3.25 m Dinding ⅟2 bata = 250 Kg/m² x 3.25 =



812.5 Kg/m



1



Perhitungan Struktur Rumah 2 Lantai -



Beban Pada Pelat Lantai atap (Berdasarkan PPIUG) Beban Mati Waterproofing = 5 Kg/m² Spesi (1 cm) = 21 Kg/m² Plafond = 11 Kg/m² M&E = 25 Kg/m² Total = 62 Kg/m² Beban Hidup



-



-



C.



=



125 Kg/m²



Beban Pada Balok lantai atap (Berdasarkan PPIUG) Beban Mati Tinggi dinding = 0.89 m Dinding ⅟2 bata = 250 Kg/m² x 0.89 =



222.5 Kg/m



Beban Pada Balok lantai atap tepi (Berdasarkan PPIUG) Beban Mati Tinggi dinding = 3.25 m Dinding ⅟2 bata = 250 Kg/m² x 3.25 =



812.5 Kg/m



Pemodelan struktur Pemodelan struktur pada perhitungan ini menggunakan software ETABS v9.7.2, perhitungan kolom menggunakan software PCA Col.



Pemodelan struktur menggunakan ETABS V 9.7.2



2



PERHITUNGAN SLOOF DAN BALOK



Data Perhitungan Balok B2 (150x300)



Data Perhitungan Balok B2 (150x300)



1,4DL 1,2DL + 1,6LL MAX



Tumpuan Lapangan V M V M Kg Kgm Kg Kgm 1618.644 5034.330 3371.151 1176.280 1622.255 5345.390 3450.952 1502.590 5345.39 3450.952 1502.59 1622.255



Mu (Tumpuan) Vu (Tumpuan)



= =



3450.952 Kgm 5345.39 Kg



= =



34.50952 KNm 53.4539 KN



Mu (Lapangan) Vu (Lapangan)



= =



1622.255 Kgm 1502.59 Kg



= =



16.22255 KNm 15.0259 KN



PEMBEBANAN H B t Pelat Pjg Balok Longitudinal Pjg Balok Transversal Tinggi Bangunan Luas Tributari Area



= = = = = = =



0.3 m 0.15 m 0.12 m 4m 3m 3.25 m (pjg.long + 0.5) / (2 x pjg.transversal)



=



6.75 m²



Berat Beton Berat Pelat Lantai Berat Balok



= = =



2400 Kg/m³ (berat beton x t.pelat x L.tributari)/pjg (berat beton x L.kolom x Pjg.Long)/Pjg



= =



486 Kg/m 108 Kg/m



Keramik Spesi Plafond Utilitas Berat Total



= = = = = =



24 Kg/m² 21 Kg/m² 11 Kg/m² 25 Kg/m² 81 Kg/m² (Total x L.tributari) / Pjg.longitudinal



=



136.69 Kg/m



= =



250 Kg/m² (berat dinding x tinggi x pjg)/Pjg



=



812.5 Kg/m



DL Total



=



b.pelat+b.balok+b.total+b.dinding



=



1543.2 Kg/m



Beban Hidup (Sekolah) LL Total



= =



250 Kg/m² (Beban hidup x L.tributari)/Pjg



=



421.88 Kg/m



Kombinasi



Berat Dinding



3



Perhitungan Balok B2 (150 x 300)



Perhitungan Balok B2 (150x300) 1. Desain Balok Tulangan Rangkap (Pada Tumpuan) Panjang Balok = 4000 mm H = 300 mm B = 150 mm fy tul. Longitudinal = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy tul. Geser = 240 Mpa Mu total = -



= = =



34.50952 KN.m 12 mm 3 buah π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 3 buah π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2) 12 mm 0 buah π x 1/4 x D.tul3² x Jml H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2 D.Tul Tarik Lapis 3 Jumlah As3 d3



= = = = = = = = = = = =



As total d total



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



- D.Tul Tekan Lapis 1 fy Jumlah As' d' D.Tul Tekan Lapis 2 Jumlah As' d' As' total d' total



= = = = = = = = =



4m 0.3 m 0.15 m



12 mm 400 Mpa 3 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul) 12 mm 0 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul)



= As'1 + As'2 = (As'1 x d'1+As'2 x d'2)/As'tot



= =



339.292 mm² 261 mm



= =



339.292 mm² 224 mm



= =



0 mm² 237 mm



= =



678.584 mm² 242.5 mm



= =



339.292007 mm² 39 mm



= =



0 mm² 76 mm



= =



339.292007 mm² 39 mm



=



50.2654825 mm²



- d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



- Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



= =



8 mm OK



4



Perhitungan Balok B2 (150 x 300) - Rasio Tulangan ρ ρ' ρmin 1 ρmin 2 ρb -



-



-



= = = = =



As / (B x d) As' / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/(600+fy)]



= = = = =



0.018655 0.009328 0.003125 0.005833 0.053757



Tegangan Tul. Tekan ρ - ρ' 0.009327615 = k = (β' x 0.85 x f'c x d')/[fy x d x [600/(600+fy)] = ρ - ρ' > k



= 0.021787 = Belum leleh



Tegangan Tul. Tekan fs' = 600 x {1 - [(β' x 0.85 x f'c x d')/(ρ - ρ' x fy x d)]} Menggunakan = fs' < fy



= 132.8554 = fs'



Momen Nominal a Mn



= (As x fy - As' x fy)/(0.85 x f'c x B) = [(As x fy - As' x fs') x (d - a/2)] + [As' x fy x (d-d')]



фMn



= 0.8 x Mn



= = = =



71.01391 56027413 56.02741 44.82193



mm N.mm KN.m KN.m



Syarat Mu < Mn Mu < Mn 34.50952 < 44.82193062 Kuat -



Jenis Keruntuhan ρmax ρmin < ρ ρ < ρmax



= 0.75 x ρb + ρ' x (fs' / fy) = Under Reinforce = Under Reinforce



2. Desain Balok Tulangan Tunggal (Pada Lapangan) Panjang Balok = 4000 mm H = 300 mm B = 150 mm fy = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy = 240 Mpa Mu total = -



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2



= = = = = = = =



=



= = =



0.04341614



4m 0.3 m 0.15 m



16.22255 KN.m 12 mm 3 π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 3 π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2)



= =



339.292 mm² 261 mm



= =



339.292 mm² 224 mm



5



Perhitungan Balok B2 (150 x 300)



-



-



-



-



-



D.Tul Tarik Lapis 3 Jumlah As3 d3



= 12 mm = 0 = π x 1/4 x D.tul3² x Jml = H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



= =



0 mm² 237 mm



As d



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



= =



678.584 mm² 242.5 mm



d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



Rasio Tulangan ρ ρmin 1 ρmin 2 ρb ρmaks



= = = = =



Jenis Keruntuhan ρmin < ρ ρ < ρmax



= Under Reinforce = Under Reinforce



Momen Nominal a Mn



= (As x fy) / (0.85 x f'c x B) = (As x fy) x (d - a / 2)



фMn



= 0.8 x Mn



=



50.2654825 mm²



As / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/( 600+fy)] 0,75 x ρb



= = = =



85.1556409 54265598 54.265598 43.4124784



= =



OK



8 mm



= = = = =



0.018655 0.003125 0.005833 0.053757 0.040318



mm N.mm KN.m KN.m



Syarat Mu < Mn Mu < Mn 16.22255 < 43.41247838 Kuat 3. Desain Balok Tulangan Geser - Data: Panjang Balok = Ln = Penampang Balok: b = h = Penampang Kolom: b = h =



4000 mm 3850 mm



= =



4m 3.85 m



150 mm 300 mm



= =



0.15 m 0.3 m



150 mm 300 mm



= =



0.15 m 0.3 m



6



Perhitungan Balok B2 (150 x 300) -



-



Properti Material: f'c dekking Tul. memanjang Fy Dia. Tul. Tarik Dia. Tul. Tekan Tul. geser Fy Dia. Sengkang As



25 = 25 = = Ulir 400 = 12 = 12 = = polos 240 = 8 = 50.26548246 =



Pembebanan qDL qLL



= =



-



-



lapangan



Tulangan terpasang As1 = As2 = As3 = As4 = As Lapangan = Tinggi efektif d1 d2 d3 d4 d lapangan



Cek Penampang Rasio b terhadap h b/h 0.5 Panjang balok (Ln) Ln 3850 P 53.4539 Cek Rasio Tul. ρmin1 ρmin2 ρmax



Mpa mm mm²



Mpr4



Mpr3



-



Mpa mm mm



1543.1875 Kg/m 421.875 Kg/m



Mpr1



-



Mpa mm



Mpr2



678.5840132 339.2920066 339.2920066 678.5840132 678.5840132



= = = = =



242.5 461 461 242.5 242.5



> >



0.3 0.3



mm² mm² mm² mm² mm²



mm mm mm mm mm



> 4d 1844 mm > < Ag x f'c / 10 112.5 KN
1/4 M terbesar Mpr1 > 1/4 M terbesar 64.22041893 > 16.05510473 Mpr2 > 1/4 M terbesar 73.69233435 > 16.05510473 Mpr3 1/4 M terbesar > 73.69233435 > 16.05510473 Mpr4 1/4 M terbesar > 64.22041893 > 16.05510473



-



mm² mm²



mm mm mm mm



64.2204189 73.6923344 73.6923344 64.2204189



KNm KNm KNm KNm



OK



KNm



OK



KNm



OK



KNm



OK



KNm



Jarak Sengkang Maksimum Syarat s1 = d/4 s2 = 8 x d.utama s3 = 24 x d.sengkang s4 = 300 S pakai mm = 60 Wu



= = = =



= = = =



60.625 96 192 300



mm mm mm mm



= 1,2 DL + 1.6 LL 2526.825 = Kg/m 25.26825 = KN/m



8



Perhitungan Balok B2 (150 x 300) -



Reaksi Tumpuan V Ve1



= Wu x Ln / 2 = (Mpr1 + Mpr2) + Ln 84.46287561 = = (Mpr3 + Mpr4) + Ln 84.46287561 =



Ve2



=



48.6413813 KN



=



117.309549 mm²



(Wu x Ln) 2 KN (Wu x Ln) 2 KN



Vu



=



84.46287561 KN



Vn



= Vu / φ 112.6171675 KN = 112617.1675 N =



Av



= Vu / φ x s fy x d



Jumlah kaki



= Av / As sengkang 2.333799334 = 3 Kaki =



Jadi pada daerah tumpuan : Sengkang terpasang 3 D



8 -



60



Sengkang di Daerah Lapangan Vn Tumpuan 112.6171675 KN =



 294,35



X



2 x d = 881



1844  2725



X 485



=



112.6171675 1925



X



=



28.37



KN



Vn Lapangan Digunakan s



= =



28.37 150



KN mm



Av



= Vn x s fy x d



Jumlah kaki



= Av / As sengkang 0.872901569 = 1 Kaki =



Maka



=



43.8768185 mm²



9



Perhitungan Balok B2 (150 x 300) Jadi pada daerah lapangan : Sengkang terpasang 1 D



8 -



150



4. Cek Lendutan



δ Ijin δ Ijin (m) 0.0167



= L/240 > δ Balok (m) > 0.002



=



16.67



mm



OK



10



Data Perhitungan Balok B3 (150 x 250)



Data Perhitungan Balok B3 (150 x 250)



1,4DL 1,2DL + 1,6LL MAX



Tumpuan V M Kg Kgm 2578.790 1850.512 2281.400 1673.043 2578.79 1850.512



Mu (Tumpuan) Vu (Tumpuan)



= =



1850.512 Kgm 2578.79 Kg



= =



18.50512 KNm 25.7879 KN



Mu (Lapangan) Vu (Lapangan)



= =



443.665 Kgm 168.3 Kg



= =



4.43665 KNm 1.683 KN



PEMBEBANAN H B t Pelat Pjg Balok Longitudinal Pjg Balok Transversal Tinggi Bangunan Luas Tributari Area



= = = = = = =



0.25 m 0.15 m 0.12 m 5.925 m 3.5 m 3.25 m (pjg.long + 0.5) / (2 x pjg.transversal)



=



11.244 m²



Berat Beton Berat Pelat Lantai Berat Balok



= = =



2400 Kg/m³ (berat beton x t.pelat x L.tributari)/pjg (berat beton x L.kolom x Pjg.Long)/Pjg



= =



546.53 Kg/m 90 Kg/m



Keramik Spesi Plafond Utilitas Berat Total



= = = = = =



24 Kg/m² 21 Kg/m² 11 Kg/m² 25 Kg/m² 81 Kg/m² (Total x L.tributari) / Pjg.longitudinal



=



153.71 Kg/m



= =



250 Kg/m² (berat dinding x tinggi x pjg)/Pjg



=



812.5 Kg/m



DL Total



=



b.pelat+b.balok+b.total+b.dinding



=



1602.7 Kg/m



Beban Hidup (Sekolah) LL Total



= =



250 Kg/m² (Beban hidup x L.tributari)/Pjg



=



474.42 Kg/m



Kombinasi



Berat Dinding



Lapangan V M Kg Kgm 44.300 423.678 168.300 443.665 168.30 443.665



11



Perhitungan Balok B3 (150 x 250)



Perhitungan Balok B3 (150 x 250) 1. Desain Balok Tulangan Rangkap (Pada Tumpuan) Panjang Balok = 5925 mm H = 250 mm B = 150 mm fy tul. Longitudinal = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy tul. Geser = 240 Mpa Mu total = -



= = =



18.50512 KN.m 12 mm 3 buah π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 2 buah π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2) 12 mm 0 buah π x 1/4 x D.tul3² x Jml H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2 D.Tul Tarik Lapis 3 Jumlah As3 d3



= = = = = = = = = = = =



As total d total



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



- D.Tul Tekan Lapis 1 fy Jumlah As' d' D.Tul Tekan Lapis 2 Jumlah As' d' As' total d' total



= = = = = = = = =



5.925 m 0.25 m 0.15 m



12 mm 400 Mpa 3 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul) 12 mm 0 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul)



= As'1 + As'2 = (As'1 x d'1+As'2 x d'2)/As'tot



= =



339.292 mm² 211 mm



= 226.1947 mm² = 174 mm



= =



0 mm² 187 mm



= 565.4867 mm² = 196.2 mm



= =



339.292007 mm² 39 mm



= =



0 mm² 76 mm



= =



339.292007 mm² 39 mm



=



50.2654825 mm²



- d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



- Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



= =



8 mm OK



12



Perhitungan Balok B3 (150 x 250) - Rasio Tulangan ρ ρ' ρmin 1 ρmin 2 ρb -



-



-



= = = = =



As / (B x d) As' / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/(600+fy)]



= = = = =



0.019215 0.011529 0.003125 0.005833 0.053757



Tegangan Tul. Tekan ρ - ρ' 0.007685854 = k = (β' x 0.85 x f'c x d')/[fy x d x [600/(600+fy)] = ρ - ρ' > k



= 0.026928 = Belum leleh



Tegangan Tul. Tekan fs' = 600 x {1 - [(β' x 0.85 x f'c x d')/(ρ - ρ' x fy x d)]} Menggunakan = fs' < fy



= -100.717 = fs'



Momen Nominal a Mn



= (As x fy - As' x fy)/(0.85 x f'c x B) = [(As x fy - As' x fs') x (d - a/2)] + [As' x fy x (d-d')]



фMn



= 0.8 x Mn



= 81.6838 mm = 35078232 N.mm = 35.07823 KN.m = 28.06259 KN.m



Syarat Mu < Mn Mu < Mn 18.50512 < 28.06258531 Kuat -



Jenis Keruntuhan ρmax ρmin < ρ ρ < ρmax



= 0.75 x ρb + ρ' x (fs' / fy) = Under Reinforce = Under Reinforce



2. Desain Balok Tulangan Tunggal (Pada Lapangan) Panjang Balok = 5925 mm H = 250 mm B = 150 mm fy = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy = 240 Mpa Mu total = -



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2



= = = = = = = =



=



= = =



0.03741522



5.925 m 0.25 m 0.15 m



4.43665 KN.m 12 mm 3 π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 2 π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2)



= =



339.292 mm² 211 mm



= 226.1947 mm² = 174 mm



13



Perhitungan Balok B3 (150 x 250)



-



-



-



-



-



D.Tul Tarik Lapis 3 Jumlah As3 d3



= 12 mm = 0 = π x 1/4 x D.tul3² x Jml = H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



= =



As d



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



= 565.4867 mm² = 196.2 mm



d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



Rasio Tulangan ρ ρmin 1 ρmin 2 ρb ρmaks



= = = = =



Jenis Keruntuhan ρmin < ρ ρ < ρmax



= Under Reinforce = Under Reinforce



Momen Nominal a Mn



= (As x fy) / (0.85 x f'c x B) = (As x fy) x (d - a / 2)



фMn



= 0.8 x Mn



=



50.2654825 mm²



As / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/( 600+fy)] 0,75 x ρb



= = = =



0 mm² 187 mm



70.9630341 36353664.4 36.3536644 29.0829315



= =



8 mm OK



= = = = =



0.019215 0.003125 0.005833 0.053757 0.040318



mm N.mm KN.m KN.m



Syarat Mu < Mn Mu < Mn 4.43665 < 29.08293151 Kuat 3. Desain Balok Tulangan Geser - Data: Panjang Balok = Ln = Penampang Balok: b = h = Penampang Kolom: b = h =



5925 mm 5775 mm



= =



5.925 m 5.775 m



150 mm 250 mm



= =



0.15 m 0.25 m



150 mm 300 mm



= =



0.15 m 0.3 m



14



Perhitungan Balok B3 (150 x 250) -



-



Properti Material: f'c dekking Tul. memanjang Fy Dia. Tul. Tarik Dia. Tul. Tekan Tul. geser Fy Dia. Sengkang As



25 = 25 = = Ulir 400 = 12 = 12 = = polos 240 = 8 = 50.26548246 =



Pembebanan qDL qLL



= =



-



-



lapangan



Mpr2



Tulangan terpasang As1 As2 As3 As4 As Lapangan



= = = = =



565.4866776 339.2920066 339.2920066 565.4866776 565.4866776



Tinggi efektif d1 d2 d3 d4 d lapangan



= = = = =



196.2 461 461 196.2 196.2



> >



0.3 0.3



Cek Penampang Rasio b terhadap h b/h 0.6 Panjang balok (Ln) Ln 5775 P 53.4539 Cek Rasio Tul. ρmin1 ρmin2 ρmax



Mpa mm mm²



Mpr4



Mpr3



-



Mpa mm mm



1543.1875 Kg/m 421.875 Kg/m



Mpr1



-



Mpa mm



mm² mm² mm² mm² mm²



mm mm mm mm mm



> 4d 1844 mm > < Ag x f'c / 10 93.75 KN
1/4 M terbesar Mpr1 > 1/4 M terbesar 42.93403984 > 10.73350996 Mpr2 1/4 M terbesar > 73.69233435 > 10.73350996 Mpr3 > 1/4 M terbesar 73.69233435 > 10.73350996 Mpr4 > 1/4 M terbesar 42.93403984 > 10.73350996



-



mm² mm²



mm mm mm mm



42.9340398 73.6923344 73.6923344 42.9340398



KNm KNm KNm KNm



OK



KNm



OK



KNm



OK



KNm



OK



KNm



Jarak Sengkang Maksimum Syarat s1 = d/4 s2 = 8 x d.utama s3 = 24 x d.sengkang s4 300 = S pakai 50 mm = Wu



= = = =



= = = =



49.05 96 192 300



mm mm mm mm



= 1,2 DL + 1,6 LL 2526.825 = Kg/m 25.26825 = KN/m



16



Perhitungan Balok B3 (150 x 250) -



Reaksi Tumpuan V Ve1



= Wu x Ln / 2 = (Mpr1 + Mpr2) + Ln 93.15711502 = = (Mpr3 + Mpr4) + Ln 93.15711502 =



Ve2



=



72.9620719 KN



=



129.384882 mm²



(Wu x Ln) 2 KN (Wu x Ln) 2 KN



Vu



=



93.15711502 KN



Vn



= Vu / φ 124.2094867 KN = 124209.4867 N =



Av



= Vu / φ x s fy x d



Jumlah kaki



= Av / As sengkang 2.574030441 = 3 Kaki =



Jadi pada daerah tumpuan : Sengkang terpasang 3 D



8 -



50



Sengkang di Daerah Lapangan Vn Tumpuan 124.2094867 KN =



 294,35



X



2 x d = 881



1844  2725



X 392.4



=



124.2094867 2887.5



X



=



16.88



KN



Vn Lapangan Digunakan s



= =



16.88 150



KN mm



Av



= Vn x s fy x d



Jumlah kaki



= Av / As sengkang 0.641836162 = 1 Kaki =



Maka



=



32.2622043 mm²



17



Perhitungan Balok B3 (150 x 250)



Jadi pada daerah lapangan : Sengkang terpasang 1 D



8 -



150



4. Cek Lendutan



δ Ijin δ Ijin (m) 0.0247



= L/240 > δ Balok (m) > 0.002



=



24.69



mm



OK



18



Data Perhitungan Balok Sloof (150 x 300)



Data Perhitungan Balok Sloof (150 x 300)



1,4DL 1,2DL + 1,6LL MAX



Tumpuan V M Kg Kgm 2700.550 1880.937 2313.850 1611.023 2700.55 1880.937



Mu (Tumpuan) Vu (Tumpuan)



= =



1880.937 Kgm 2700.55 Kg



= =



18.80937 KNm 27.0055 KN



Mu (Lapangan) Vu (Lapangan)



= =



942.456 Kgm 122.84 Kg



= =



9.42456 KNm 1.2284 KN



PEMBEBANAN H B t Pelat Pjg Balok Longitudinal Pjg Balok Transversal Tinggi Bangunan Luas Tributari Area



= = = = = = =



0.3 m 0.15 m 0.12 m 4m 3m 3.25 m (pjg.long + 0.5) / (2 x pjg.transversal)



=



6.75 m²



Berat Beton Berat Pelat Lantai Berat Balok



= = =



2400 Kg/m³ (berat beton x t.pelat x L.tributari)/pjg (berat beton x L.kolom x Pjg.Long)/Pjg



= =



486 Kg/m 108 Kg/m



Keramik Spesi Plafond Utilitas Berat Total



= = = = = =



24 Kg/m² 21 Kg/m² 11 Kg/m² 25 Kg/m² 81 Kg/m² (Total x L.tributari) / Pjg.longitudinal



=



136.69 Kg/m



= =



250 Kg/m² (berat dinding x tinggi x pjg)/Pjg



=



812.5 Kg/m



DL Total



=



b.pelat+b.balok+b.total+b.dinding



=



1543.2 Kg/m



Beban Hidup (Sekolah) LL Total



= =



250 Kg/m² (Beban hidup x L.tributari)/Pjg



=



421.88 Kg/m



Kombinasi



Berat Dinding



Lapangan V M Kg Kgm 122.840 942.456 104.380 807.220 122.84 942.456



19



Perhitungan Balok Sloof (150 x 300)



Perhitungan Balok Sloof (150 x 300) 1. Desain Balok Tulangan Rangkap (Pada Tumpuan) Panjang Balok = 4000 mm H = 300 mm B = 150 mm fy tul. Longitudinal = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy tul. Geser = 240 Mpa Mu total = -



= = =



18.80937 KN.m 12 mm 2 buah π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 2 buah π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2) 12 mm 0 buah π x 1/4 x D.tul3² x Jml H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2 D.Tul Tarik Lapis 3 Jumlah As3 d3



= = = = = = = = = = = =



As total d total



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



- D.Tul Tekan Lapis 1 fy Jumlah As' d' D.Tul Tekan Lapis 2 Jumlah As' d' As' total d' total



= = = = = = = = =



4m 0.3 m 0.15 m



12 mm 400 Mpa 2 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul) 12 mm 0 buah π x 1/4 x D.tul² x Jml P + d.skg + (1/2 x D.tul)



= As'1 + As'2 = (As'1 x d'1+As'2 x d'2)/As'tot



= 226.1947 mm² = 261 mm



= 226.1947 mm² = 224 mm



= =



0 mm² 237 mm



= 452.3893 mm² = 242.5 mm



= =



226.194671 mm² 39 mm



= =



0 mm² 76 mm



= =



226.194671 mm² 39 mm



=



50.2654825 mm²



- d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



- Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



= =



40 mm OK



20



Perhitungan Balok Sloof (150 x 300) - Rasio Tulangan ρ ρ' ρmin 1 ρmin 2 ρb -



-



-



= = = = =



As / (B x d) As' / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/(600+fy)]



= = = = =



0.012437 0.006218 0.003125 0.005833 0.053757



Tegangan Tul. Tekan ρ - ρ' 0.00621841 = k = (β' x 0.85 x f'c x d')/[fy x d x [600/(600+fy)] = ρ - ρ' > k



= 0.021787 = Belum leleh



Tegangan Tul. Tekan fs' = 600 x {1 - [(β' x 0.85 x f'c x d')/(ρ - ρ' x fy x d)]} Menggunakan = fs' < fy



= -100.717 = fs'



Momen Nominal a Mn



= (As x fy - As' x fy)/(0.85 x f'c x B) = [(As x fy - As' x fs') x (d - a/2)] + [As' x fy x (d-d')]



фMn



= 0.8 x Mn



= = = =



63.91761 38259047 38.25905 30.60724



mm N.mm KN.m KN.m



Syarat Mu < Mn Mu < Mn 18.80937 < 30.60723787 Kuat -



Jenis Keruntuhan ρmax ρmin < ρ ρ < ρmax



= 0.75 x ρb + ρ' x (fs' / fy) = Under Reinforce = Under Reinforce



2. Desain Balok Tulangan Tunggal (Pada Lapangan) Panjang Balok = 4000 mm H = 300 mm B = 150 mm fy = 400 Mpa f'c = 25 Mpa β' = 0.85 Mpa fy = 240 Mpa Mu total = -



D.Tul Tarik Lapis 1 Jumlah As1 d1 D.Tul Tarik Lapis 2 Jumlah As2 d2



= = = = = = = =



=



= = =



0.03875233



4m 0.3 m 0.15 m



9.42456 KN.m 12 mm 2 π x 1/4 x D.tul1² x Jml H - P - d.skg - (1/2 x D.Tul1) 12 mm 2 π x 1/4 x D.tul2² x Jml H - P - d.skg - D.tul1 - (1/2 x D.Tul2)



= 226.1947 mm² = 261 mm



= 226.1947 mm² = 224 mm



21



Perhitungan Balok Sloof (150 x 300)



-



-



-



-



-



D.Tul Tarik Lapis 3 Jumlah As3 d3



= 12 mm = 0 = π x 1/4 x D.tul3² x Jml = H - P - d.skg - D.tul1 - D.tul2 - (1/2 x D.Tul3)



= =



As d



= As1 + AS2 + As3 = (As1 x d1 + As2 x d2 x As3 x d3) / Astot



= 452.3893 mm² = 242.5 mm



d.sengkang fy Av P



= 8 mm = 240 Mpa = π x 1/4 x d.skg² = 25 mm



Cek Tulangan Sisa Space



= B - (D.tul1 x Jml) - 20 x (Jml-1) - 2 x P - 2 x d.skg



Rasio Tulangan ρ ρmin 1 ρmin 2 ρb ρmaks



= = = = =



Jenis Keruntuhan ρmin < ρ ρ < ρmax



= Under Reinforce = Under Reinforce



Momen Nominal a Mn



= (As x fy) / (0.85 x f'c x B) = (As x fy) x (d - a / 2)



фMn



= 0.8 x Mn



=



50.2654825 mm²



As / (B x d) √(f'c) / (4fy) 1.4 / fy (β' x 0.85 x f'c/fy) x [600/( 600+fy)] 0,75 x ρb



= = = =



0 mm² 237 mm



56.7704272 38745298.9 38.7452989 30.9962392



= =



40 mm OK



= = = = =



0.012437 0.003125 0.005833 0.053757 0.040318



mm N.mm KN.m KN.m



Syarat Mu < Mn Mu < Mn 9.42456 < 30.99623915 Kuat 3. Desain Balok Tulangan Geser - Data: Panjang Balok = Ln = Penampang Balok: b = h = Penampang Pondasi: b = h =



4000 mm 3850 mm



= =



4m 3.85 m



150 mm 300 mm



= =



0.15 m 0.3 m



150 mm 300 mm



= =



0.15 m 0.3 m



22



Perhitungan Balok Sloof (150 x 300) -



-



Properti Material: f'c dekking Tul. memanjang Fy Dia. Tul. Tarik Dia. Tul. Tekan Tul. geser Fy Dia. Sengkang As



25 = 25 = = Ulir 400 = 12 = 12 = = polos 240 = 8 = 50.26548246 =



Pembebanan qDL qLL



= =



-



-



Mpr2



lapangan



Tulangan terpasang As1 As2 As3 As4 As Lapangan



= = = = =



452.3893421 226.1946711 226.1946711 452.3893421 452.3893421



Tinggi efektif d1 d2 d3 d4 d lapangan



= = = = =



242.5 461 461 242.5 242.5



> >



0.3 0.3



Cek Penampang Rasio b terhadap h b/h 0.5 Panjang balok (Ln) Ln 3850 P 53.4539 Cek Rasio Tul. ρmin1 ρmin2 ρmax



Mpa mm mm²



Mpr4



Mpr3



-



Mpa mm mm



1543.1875 Kg/m 421.875 Kg/m



Mpr1



-



Mpa mm



mm² mm² mm² mm² mm²



mm mm mm mm mm



> 4d 1844 mm > < Ag x f'c / 10 112.5 KN
1/4 M terbesar Mpr1 > 1/4 M terbesar 46.82647766 > 11.70661941 Mpr2 1/4 M terbesar > 50.13143916 > 11.70661941 Mpr3 > 1/4 M terbesar 50.13143916 > 11.70661941 Mpr4 > 1/4 M terbesar 46.82647766 > 11.70661941



-



mm² mm²



mm mm mm mm



46.8264777 50.1314392 50.1314392 46.8264777



KNm KNm KNm KNm



OK



KNm



OK



KNm



OK



KNm



OK



KNm



Jarak Sengkang Maksimum Syarat s1 = d/4 s2 = 8 x d.utama s3 = 24 x d.sengkang s4 300 = S pakai 60 mm = Wu



= = = =



= = = =



60.625 96 192 300



mm mm mm mm



= 1,2 DL + 1 LL 2273.7 = Kg/m 22.737 = KN/m



24



Perhitungan Balok Sloof (150 x 300) -



Reaksi Tumpuan V Ve1



= Wu x Ln / 2 = (Mpr1 + Mpr2) + Ln 68.9525995 = = (Mpr3 + Mpr4) + Ln 68.9525995 =



Ve2



=



43.768725 KN



=



95.7674993 mm²



(Wu x Ln) 2 KN (Wu x Ln) 2 KN



Vu



=



68.9525995 KN



Vn



= Vu / φ 91.93679933 KN = 91936.79933 N =



Av



= Vu / φ x s fy x d



Jumlah kaki



= Av / As sengkang 1.905233863 = 2 Kaki =



Jadi pada daerah tumpuan : Sengkang terpasang 2 D



8 -



60



Sengkang di Daerah Lapangan Vn Tumpuan 91.93679933 KN =  294,35



X 2 x d = 881



1844  2725



X 485



=



91.93679933 1925



X



=



23.16



KN



Vn Lapangan Digunakan s



= =



23.16 150



KN mm



Av



= Vn x s fy x d



Jumlah kaki



= Av / As sengkang 0.712606951 = 1 Kaki =



Maka



=



35.8195322 mm²



25



Perhitungan Balok Sloof (150 x 300) Jadi pada daerah lapangan : Sengkang terpasang 1 D



8 -



150



4. Cek Lendutan



δ Ijin δ Ijin (m) 0.0167



= L/240 > δ Balok (m) > 0.002



=



16.67



mm



OK



26



Tabel Hasil Perhitungan Balok Tabel Hasil Perhitungan Balok B2



B3



4000



5925



Tipe Balok Panjang Balok (mm) Dimensi Balok (mm)



150



Lokasi



Tumpuan



x



300



150



Lapangan



x



250



Tumpuan



Lapangan



Tulangan Atas



6



D 12



3



D 12



5



D 12



3



D 12



Tulangan Bawah



3



D 12



6



D 12



3



D 12



5



D 12



D



8



D



8



D



8



D



8



Tulangan Geser



3



-



60



1



-



3



-



50



1



-



150



SLOOF



Tipe Balok



4000



Panjang Balok (mm) 150



Dimensi Balok (mm)



x



300



Tumpuan



Lokasi



Lapangan



Tulangan Atas



4



D 12



2



D 12



Tulangan Bawah



2



D 12



4



D 12



D



8



D



8



Tulangan Geser



150



2



-



60



1



-



150



27



PERHITUNGAN KOLOM



Data Gaya-Gaya Dalam Kolom Data Gaya-Gaya Dalam Kolom 1. KOLOM 150X300 Hasil Perhitungan Dari Program ETABS : P Kombinasi Kgf 1,4DL 15569.49 1,2DL + 1,6LL 16423.04 MAX 16423.04 Mu Pu



= = = =



V Kgf 170.33 186.43 186.43 119.754 1.19754 16423.04 164.2304



M P Kgm KN 119.754 155.6949 95.741 164.2304 119.754 164.2304



V KN 1.7033 1.8643 1.8643



M KNm 1.19754 0.95741 1.19754



V KN 0.0623 0.0638 0.0638



M KNm 1.91578 1.7666 1.91578



V KN 0.2706 0.2364 0.2706



M KNm 0.93253 0.8492 0.93253



Kgm KNm Kg KN



2. KOLOM 150 X 250 Hasil Perhitungan Dari Program ETABS : P Kombinasi Kgf 1,4DL 12593.34 1,2DL + 1,6LL 12398.57 MAX 12593.34 Mu Pu



= = = =



V Kgf 6.23 6.38 6.38 191.578 1.91578 12593.34 125.9334



M P Kgm KN 191.578 125.9334 176.66 123.9857 191.578 125.9334 Kgm KNm Kg KN



3. KOLOM 150 X 200 Hasil Perhitungan Dari Program ETABS : P Kombinasi Kgf 1,4DL 11239.83 1,2DL + 1,6LL 10844.73 MAX 11239.83 Mu Pu



= = = =



V Kgf 27.06 23.64 27.06 93.253 0.93253 11239.83 112.3983



M P Kgm KN 93.253 112.3983 84.92 108.4473 93.253 112.3983 Kgm KNm Kg KN



28



Perhitungan Kolom Struktur 150 X 300 Perhitungan Kolom Struktur 150 X 300 - Dimensi balok B2 b h Ln -



= = =



Tul. Tumpuan Atas (-) a(mm) Mn Bawah (+) a(mm) Mn



- Data Kolom C24 : b h Ln Dekking Tul. Terpasang f'c fy Sengkang fy



150 mm 300 mm 2.85 m B2 D 71.0139 44.8219 D 85.1556 43.4125



6



3



= = = = = = = = =



- Dimensi baloK B3 b = h = Ln =



150 300 3.25 30 12 25 400



mm mm m mm D Mpa Mpa D 240 Mpa



12 mm KNm 12 mm KNm



5



3



12



mm



8



mm



150 mm 250 mm 5.775 m



B3 D 81.684 28.063 D 70.963 29.083



12 mm KNm 12 mm KNm



- Hasil Perhitungan Dari Program ETABS Gaya Maksimum



Nilai



Mu (KNm) Pu (KN)



1.1975 164.23



- Dari diagram interaksi didapatkan Mn = 51.85 KNm (dari PCA COL) d balok = h balok - t.selimut - dia skg - dia tul balok hc = h balok - 2 x t.selimut - 2 x dia skg Ag = b kolom x h kolom b' kolom = b kolom - 2 x t.selimut - 2 x dia skg h' kolom = h kolom - 2 x t.selimut - 2 x dia skg Ac = b' kolom x h' kolom - Cek Gaya Aksial (Pu) Pu > 0,1.Ag.f'c 164.2304 > 112.5 kN - Cek Dimensi Penampang b/h = - Cek Rasio Tulangan ρ ρmin ρmax ρmin < ρ < ρmax



= = =



= = = = = =



256 224 45000 74 224 16576



mm mm mm²



mm²



OK



0.5 >



0.4



OK



0.0344 (dari PCA COL) 0.01 0.06 OK



29



Perhitungan Kolom Struktur 150 X 300 - Cek Kekuatan Kolom thd. Balok ΣMe > 6/5 ΣMg ΣMe = 2 x Mn ΣMg1 = Mn1 + Mn4 ΣMg2 = Mn2 + Mn3 ΣMg = Mg max 6/5ΣMg ΣMe > 6/5ΣMg 103.7 > 88.686 KNm - Perhitungan Tul. Geser Mpr kolom ΣMpr kolom Ve Ve/φ Vn



= = = = =



51.85 KNm 2 x Mpr kolom ΣMpr kolom / Ln Ve / 0,75 Ve/φ



- Jarak Sengkang Maksimal s = h/2 s = 6D s = 100 s dipakai = s min



= = = = =



103.7 73.9049 71.4751 73.9049 88.6858



KNm KNm KNm KNm KNm



(dari PCA COL) = 103.7 = 31.9077 42.5436 = 42.5436 =



KNm KN KN KN



= = = =



mm mm mm mm



OK



75 72 100 70



Av



= Vn.s/(fy.d) = 48.471 mm²



Ash1 Ash2 Ash yang digunakan



= 0,3 x s x hc x (f'c / fy) x (Ag / Ac -1) = 0,09 x [s x Ac (f'c / fy)] = Ash max



= = =



504.142 mm² 88.2 mm² 504.142 mm²



= = =



50.2655 mm² 10.0296 kaki 12 kaki



- Cek Av thd. Ash untuk Penentuan Hoops Av < Ash 48.47 < 504.14 mm² Digunakan Ash = 504.14 mm² Luas sengkang 1 kaki Jumlah Kaki - Penentuan lo lo lo lo Digunakan lo



= 1 /4 x pi x D² = Ash / Luas sengkang 1 kaki



= Ln / 6 = = h = = 500 mm = lo max = =



541.67 mm 300 mm 541.67 mm 600 mm



30



Perhitungan Kolom Struktur 150 X 300 Gambar interaksi kolom menggunakan program pca Column (fy = 400)



31



Perhitungan Kolom Struktur 150 X 250 Perhitungan Kolom Struktur 150 X 250 - Dimensi balok B2 b h Ln -



= = =



Tul. Tumpuan Atas (-) a(mm) Mn Bawah (+) a(mm) Mn



- Data Kolom C24 : b h Ln Dekking Tul. Terpasang f'c fy Sengkang fy



150 mm 300 mm 1.85 m B2 D 71.0139 44.8219 D 85.1556 43.4125



6



3



= = = = = = = = =



- Dimensi baloK B2 b = h = Ln =



150 250 3.25 30 10 25 400



mm mm m mm D Mpa Mpa D 240 Mpa



12 mm KNm 12 mm KNm



6



3



12



mm



8



mm



150 mm 300 mm 1.6 m



B2 D 71.014 44.822 D 85.156 43.412



12 mm KNm 12 mm KNm



- Hasil Perhitungan Dari Program ETABS Gaya Maksimum Mu (KNm) Pu (KN)



Nilai 1.9158 125.93



- Dari diagram interaksi didapatkan Mn = 34.03 KNm (dari PCA COL) d balok = h balok - t.selimut - dia skg - dia tul balok hc = h balok - 2 x t.selimut - 2 x dia skg Ag = b kolom x h kolom b' kolom = b kolom - 2 x t.selimut - 2 x dia skg h' kolom = h kolom - 2 x t.selimut - 2 x dia skg Ac = b' kolom x h' kolom - Cek Gaya Aksial (Pu) Pu > 0,1.Ag.f'c 125.9334 > 93.75 kN - Cek Dimensi Penampang b/h =



0.6 >



= = = = = =



256 174 37500 74 174 12876



mm mm mm²



mm²



OK



0.4



OK



32



Perhitungan Kolom Struktur 150 X 250 - Cek Rasio Tulangan ρ ρmin ρmax ρmin < ρ < ρmax



- Perhitungan Tul. Geser Mpr kolom ΣMpr kolom Ve Ve/φ Vn



= = =



0.0344 (dari PCA COL) 0.01 0.06 OK



= = = = =



34.03 KNm 2 x Mpr kolom ΣMpr kolom / Ln Ve / 0,75 Ve/φ



- Jarak Sengkang Maksimal s = h/2 s = 6D s = 100 s dipakai = s min



(dari PCA COL) = 68.06 = 20.9415 27.9221 = 27.9221 =



KNm KN KN KN



= = = =



mm mm mm mm



75 72 100 70



Av



= Vn.s/(fy.d) = 31.812 mm²



Ash1 Ash2 Ash yang digunakan



= 0,3 x s x hc x (f'c / fy) x (Ag / Ac -1) = 0,09 x [s x Ac (f'c / fy)] = Ash max



= = =



436.743 mm² 68.5125 mm² 436.743 mm²



= = =



50.2655 mm² 8.68873 kaki 10 kaki



- Cek Av thd. Ash untuk Penentuan Hoops Av < Ash 31.81 < 436.74 mm² Digunakan Ash = 436.74 mm² Luas sengkang 1 kaki Jumlah Kaki - Penentuan lo lo lo lo Digunakan lo



= 1 /4 x pi x D² = Ash / Luas sengkang 1 kaki



= Ln / 6 = = h = = 500 mm = lo max = =



541.67 mm 250 mm 541.67 mm 600 mm



33



Perhitungan Kolom Struktur 150 X 250 Gambar interaksi kolom menggunakan program pca Column (fy = 400)



34



Perhitungan Kolom Struktur 150 X 200 Perhitungan Kolom Struktur 150 X 200 - Dimensi balok B2 b h Ln -



= = =



Tul. Tumpuan Atas (-) a(mm) Mn Bawah (+) a(mm) Mn



- Data Kolom C24 : b h Ln Dekking Tul. Terpasang f'c fy Sengkang fy



150 mm 300 mm 2.125 m



5



3



= = = = = = = = =



- Dimensi baloK B3 b = h = Ln =



B3 D 81.6838 28.0626 D 70.963 29.0829



150 200 3.25 30 8 25 400



mm mm m mm D Mpa Mpa D 240 Mpa



12 mm KNm 12 mm KNm



5



2



12



mm



8



mm



150 mm 250 mm 0.35 m



B3 D 81.684 28.063 D 70.963 29.083



12 mm KNm 16 mm KNm



- Hasil Perhitungan Dari Program ETABS Gaya Maksimum Mu (KNm) Pu (KN)



Nilai 0.9325 112.4



- Dari diagram interaksi didapatkan Mn = 16.98 KNm (dari PCA COL) d balok = h balok - t.selimut - dia skg - dia tul balok hc = h balok - 2 x t.selimut - 2 x dia skg Ag = b kolom x h kolom b' kolom = b kolom - 2 x t.selimut - 2 x dia skg h' kolom = h kolom - 2 x t.selimut - 2 x dia skg Ac = b' kolom x h' kolom - Cek Gaya Aksial (Pu) Pu > 0,1.Ag.f'c 112.3983 > 75 kN - Cek Dimensi Penampang b/h =



0.75 >



= = = = = =



256 124 30000 74 124 9176



mm mm mm²



mm²



OK



0.4



OK



35



Perhitungan Kolom Struktur 150 X 200 - Cek Rasio Tulangan ρ ρmin ρmax ρmin < ρ < ρmax



- Perhitungan Tul. Geser Mpr kolom ΣMpr kolom Ve Ve/φ Vn



= = =



0.0344 (dari PCA COL) 0.01 0.06 OK



= = = = =



16.98 KNm 2 x Mpr kolom ΣMpr kolom / Ln Ve / 0,75 Ve/φ



- Jarak Sengkang Maksimal s = h/2 s = 6D s = 100 s dipakai = s min



(dari PCA COL) = 33.96 = 10.4492 13.9323 = 13.9323 =



KNm KN KN KN



= = = =



mm mm mm mm



75 72 100 70



Av



= Vn.s/(fy.d) = 15.873 mm²



Ash1 Ash2 Ash yang digunakan



= 0,3 x s x hc x (f'c / fy) x (Ag / Ac -1) = 0,09 x [s x Ac (f'c / fy)] = Ash max



= = =



369.345 mm² 48.825 mm² 369.345 mm²



= = =



50.2655 mm² 7.34788 kaki 8 kaki



- Cek Av thd. Ash untuk Penentuan Hoops Av < Ash 15.87 < 369.34 mm² Digunakan Ash = 369.34 mm² Luas sengkang 1 kaki Jumlah Kaki - Penentuan lo lo lo lo Digunakan lo



= 1 /4 x pi x D² = Ash / Luas sengkang 1 kaki



= Ln / 6 = = h = = 500 mm = lo max = =



541.67 mm 200 mm 541.67 mm 600 mm



36



Perhitungan Kolom Struktur 150 X 200 Gambar interaksi kolom menggunakan program pca Column (fy = 400)



37



Tabel Hasil Perhitungan Kolom Tabel Hasil Perhitungan Kolom Tipe Kolom Tinggi Kolom (mm) Dimensi Kolom (mm) ρ Lokasi Tulangan Utama Tulangan Geser



Kolom 150 x 300 3250 150 x 300 0.0344 Sepanjang lo Lapangan 12 D 12 12 D 12 φ 8 - 70 0 D 8 - 70



Tipe Kolom Tinggi Kolom (mm) Dimensi Kolom (mm) ρ Lokasi Tulangan Utama Tulangan Geser



Kolom 150 x 300 3250 150 x 200 0.0344 Sepanjang lo Lapangan 8 D 12 8 D 12 φ 8 - 70 φ 8 - 70



Kolom 150 x 250 3250 150 x 250 0.0344 Sepanjang lo Lapangan 10 D 12 10 D 12 φ 8 - 70 D 8 - 70



38



PERHITUNGAN PLAT LANTAI



PERHITUNGAN PELAT LANTAI t:120 mm (FLOOR DECK) PERHITUNGAN PELAT LANTAI t:120 mm (FLOOR DECK) 1 Data Perencanaan Tebal Pelat



Berat Beton Berat Floor Deck Keramik Spesi Plafond utilitas



= = = = = = =



2 Analisa pembebanan - Beban Mati (qDL) Keramik Spesi Plafond utilitas Total



= = = = =



Beban Hidup (qLL)



=



-



Kombinasi Pembebanan 1DL 1.2 DL + 1.6 LL



120 mm 3 2400 kg/m 10.15 Kg/m² 24 Kg/m² 21 Kg/m² 11 Kg/m² 25 Kg/m²



24 21 11 25 81



Kg/m² Kg/m² Kg/m² Kg/m² Kg/m²



200 Kg/m² Load 81 417.2



3 Beban maksimum yang digunakan -



417.2 Kg/m² = Bentang menerus tulangan negative Load yang dipakai



=



2 4.99 cm /m



=



499 mm2/m



39



PERHITUNGAN PELAT LANTAI t:120 mm (FLOOR DECK) 4 Perhitungan tulangan negatif Perhitungan tulangan positif diabaikan karena floordeck dapat menggantikan tulangan positif pada plat lantai. -



Bentang menerus tulangan negative Tulangan rencana ф



As



= = =



-



Banyaknya tulangan tiap 1 meter



= = = =



-



Jarak tulangan tarik



= =



4.99 8



cm2/m mm



=



499 mm2/m



πd² 50.2655 A As 499 50.2655 9.92729 1000 10 100



~



10 Buah



mm



-



Jarak Tulangan negatif yang dipakai



=



φ 8 - 100 mm



-



Tebal floordeck yang dipakai



=



0.75 mm



40



PERHITUNGAN DAK BETON t:100 mm (FLOOR DECK) PERHITUNGAN DAK BETON t:100 mm (FLOOR DECK) 1 Data Perencanaan Tebal Pelat



Berat Beton Berat Floor Deck Waterproofing Spesi (1 cm) Plafond utilitas



= = = = = = =



2 Analisa pembebanan - Beban Mati (qDL) Waterproofing Spesi (1 cm) Plafond utilitas Total



= = = = =



Beban Hidup (qLL)



=



-



Kombinasi Pembebanan 1DL 1.2 DL + 1.6 LL



100 mm 3 2400 kg/m 10.15 Kg/m² 5 Kg/m² 21 Kg/m² 11 Kg/m² 25 Kg/m²



5 21 11 25 62



Kg/m² Kg/m² Kg/m² Kg/m² Kg/m²



100 Kg/m² Load 62 234.4



3 Beban maksimum yang digunakan = 234.4 Kg/m² - Load yang dipakai - Bentang menerus tulangan negative =



2 2.7 cm /m



=



270 mm2/m



41



PERHITUNGAN DAK BETON t:100 mm (FLOOR DECK) 4 Perhitungan tulangan negatif Perhitungan tulangan positif diabaikan karena floordeck dapat menggantikan tulangan positif pada plat lantai. - Bentang menerus tulangan negative - Tulangan rencana ф - As



= = =



- Banyaknya tulangan tiap 1 meter



= = = =



- Jarak tulangan tarik



= =



2.7 8



cm2/m mm



=



270 mm2/m



πd² 50.2655 A As 270 50.2655 5.37148



~



6 Buah



1000 6 166.667 mm



- Jarak Tulangan negatif yang dipakai



=



φ 8 - 150 mm



- Tebal floordeck yang dipakai



=



0.75 mm



42



PERHITUNGAN PONDASI



43



44



45



46



47