PEKERJAAN WATER PROOFING 1 Screeding tebal 3 cm M2 semen 0.288 zak pasir beton 0.039 m3 tukang batu 0.1 org/hr kepala tukang batu 0.01 org/hr pekerja 0.2 org/hr mandor 0.01 org/hr 2 Screeding tebal 2 cm M2 semen 0.2 zak pasir beton 0.026 m3 tukang batu 0.1 org/hr kepala tukang batu 0.01 org/hr pekerja 0.2 org/hr mandor 0.01 org/hr 3 Pekerjaan water proofing (coating) M2 pre treatment/ cleaning 1 m2 curbing sudut 0.4 m' bahan waterproofting coating 2.5 kg sewa mixer 0.02 bh kuas 0.2 unit tukang batu 0.2 org/hr kepala tukang batu 0.02 org/hr pekerja 0.1 org/hr mandor 0.01 org/hr 4 Pekerjaan water proofing (membrance) M2 material primer 0.3 kg water proofing membrnce 1.05 m2 tukang batu 0.5 org/hr kepala tukang batu 0.05 org/hr pekerja 0.25 org/hr mandor 0.0125 org/hr 5 Pekerjaan Floor Hardener M2 Material natural non metalic 6 kg Curing compound 0.125 ltr tukang batu 0.15 org/hr kepala tukang batu 0.015 org/hr pekerja 0.075 org/hr mandor 0.0075 org/hr