QA/QC Handover Note 1. Documentation A. Kobeissi ITPs, Method Statements and Materials Submittals shall be addressed by Paul Ogbaji and Hassan Daoud in response to CRS received from MPN. Remember to forward the revised documents to our discipline engineers as the case may be.  Mechanical documents – Vitalis, Martins & Hassan Abdallah  Electrical – Amed  Civil/Architectural – Thaddeus/Maher Awaited documents from MPN Method Statements: Method Statement for LV Cable Installation Method Statement for Hot & Cold Water Pipes & Fittings Installation Method Statement CPVC Pipes Installation Method Statement for Fan Coil Unit (FCU) & CU Installation Method Statement for Water Meter Installation Materials: EL7 Bedroom Lighting IPEX BLAZEMASTER CPVC to VIKING BLAZEMASTER CPVC Hot Water and Chilled Water Pump Panels MV Armored Cables Lighting Fixtures (EL5, EL14 & EL15) Medium Voltage Transformers Material Submittals to be followed up with Kobeissi Sanitary Wares- Remind Vitalis to request for this submission. As soon as this is submitted, get Vitalis to review it alongside Hassan. If all is in agreement, a copy should be forwarded to both Paul (GAMSTEC) & Wale (MPN) for offline review. Vitalis can help you out with this. UPS Equipment – When this is B. NGS ITPs, Method Statements and Materials Submittals shall be addressed by Opeoluwa Adebayo in response to CRS received from MPN. The distribution for review should follow as stated above. NGS is to revise and resubmit all their MS & ITPs after their shop drawings have been submitted and approved Awaited documents from MPN Materials:



Fibre Optic Cables Category 6a U/Utp Cable These documents were already Code B. NGS revised the submittals with the addition of a letter from Commscope. So the documents should come back with Code A. C. M & G Materials Submittals shall be addressed by Fadi Geagea in response to CRS received from MPN. Awaited documents from MPN Covered Walkways Cast-in Threaded Rods & Nuts Inspection Roof Steel structure members – Issue an IR sometime next week after M & G must have procured the new elcometer. Liaise with Fadi Geagea. D. MERCURY Documents to be revised by Amed (Electrical Inspector) ITP for MV Underground Installation ITP for LV Underground Installation MS for MV Underground Installation Awaited submittals from MPN MS for PE Pipes Installation Light Poles



Reminders Inspection Requests (IRs) must be raised and issued well ahead of time Work extension notifications must be sent daily and timely. MEETINGS Tuesdays @ 9am – Technical meeting comprising MPN/GAMSTEC/MERCURY/KOBEISSI/NGS Thursdays @ 1:30pm – Internal Construction Meeting comprising MERCURY/KOBEISSI/NGS/M & G Fridays @ 9am – Weekly Construction Meeting with MPN/GAMSTEC/MERCURY/KOBEISSI/NGS