PT . KARTIKA ASRI PRIMA
ANALISA HARGA SATUAN PEKERJAAN 1 M3 SLOOF PAGAR PT.KARTIKA ASRI PRIMA Project / Area - City : ARTHAMAS MINAHASA MANADO Site ID / Site Name : Site Enginer : Sub Contractor : No.
1
URAIAN
SATUAN VOLUME
HARGA SATUAN
1 M3
COR SLOOF PAGAR 25/25
Bahan
Paku 5
Kg
0.40
16,500.00
Papan 2/25 - 3 M
Lbr
11.00
35,000.00
Besi D.13 Ulir
Btg
6.00
128,000.00
Besi Ǿ8 Polos
Btg
6.00
102,000.00
Kawat Bendrat
0.46
18,000.00
Pasir
Kg M3
0.65
48,500.00
Split
M3
0.724
275,000.00
Semen
5.00
59,000.00
Pengecoran Site Mix
Zak M3
1.00
100,000.00
Pembesian
Kg
92.44
900.00
Upah
Jumlah 2
1 M3
COR SLOOF PAGAR 20/30 (AREA BEKASI)
Bahan
Paku 5
Kg
0.75
17,000.00
Multiplek 8mm
Lbr
3.47
105,000.00
Besi D.13 Ulir
Btg
5.56
122,500.00
Besi Ǿ8 Polos
Btg
6.30
38,000.00
Kawat Bendrat
0.79
18,000.00
Pasir
Kg M3
0.65
48,500.00
Split
3
M
0.800
275,000.00
Semen
7.00
59,000.00
Pengecoran Site Mix
Zak M3
1.00
125,000.00
Pembesian
Kg
99.24
1,063.00
Upah
Jumlah
PreparedbyHermawan
AHS/Area South Borneo/Page 1
JUMLAH (RP)
TOTAL (RP)
2,488,740.60 6,600.00 385,000.00 768,000.00 612,000.00 8,319.60 31,525.00 199,100.00 295,000.00 100,000.00 83,196.00 2,488,740.60 12,750.00 364,560.00 680,555.56 239,400.00 14,290.56 31,525.00 220,000.00 413,000.00 125,000.00 105,492.12 2,206,573.24
PreparedbyHermawan
AHS/Area South Borneo/Page 2