FLOW CHART OF SOD FACING Start
Trimming/ Slope Excavation
1. Before execute sod facing work, Contractor shall be trimming location with 2:1, as shown on construction drawing which approved by Engineer.
Install Sod Facing
2. After Trimming have been executed, sod facing install with chess board method which size 20cm x 20cm per segment, this method will be shown on attached picture .
Water Spraying
Finish
3. After install sod facing, it will be maintenance by spraying water on location.
1. Trimming Location by Excavator
2. Install Sod Facing by Manually
3. Method of Sod Facing Area of Install sod facing
4. Water Spraying