Ref no:



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES Page: ELECTRICAL SAFETY PROCEDURES



Date: Rev no:



SOP 03-006 1 of 18 13/05/08 10



SOP 03-006



ELECTRICAL SAFETY PROCEDURES



Purpose of revision: - Organization change - Voltage Classification



10 9 Rev no



Date



13/05/08



16/05/08



21/05/08



13/05/08 04/08/06



M.Setiawan Amin R.Ginting



Sugihartono Sugihartono



M. Najib M. Najib



Date



Issued by



Checked by



J.M. Noiray P. Jahan



Approved by



Update Update Comments



This document is the property of TOTAL E&P INDONESIE. It must not be reproduced or transmitted to others without COMPANY’S authorization SOP-03-006



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



2 of 18



Date:



13/05/08



Rev no:



10



Table of Contents 1 2 3 4 5



Purpose ........................................................................................................................... 3 Scope............................................................................................................................... 3 References ...................................................................................................................... 3 Definitions ........................................................................................................................ 4 Operations of Electrical System....................................................................................... 6 5.1 Work on Live Parts ................................................................................................... 6 5.2 Intervention............................................................................................................... 7 5.2.1 Without Work Permit and Electrical Isolation Permit ......................................... 7 5.2.2 With Work Permit and Isolation Permit.............................................................. 7 5.3 Working in Hazardous Areas .................................................................................... 7 5.4 Entrance to Sub Station, Electrical Technical Room or Technical Switchgear......... 8 5.5 Operation of Switchgear ........................................................................................... 8 5.6 Re-Closing After Fault Operation ............................................................................. 8 5.7 Operation of Circuit Breaker in Substations & Electrical Rooms .............................. 8 5.8 Operation of Other Electrical Equipment in Plant Area ............................................ 8 5.9 Cutting and Jointing of Cables.................................................................................. 8 5.10 Mechanical Work on Electrical Driven Machine .................................................... 8 5.11 Work in a Substation or Close-to Any Electrical Live Installation.......................... 9 5.12 Excavations........................................................................................................... 9 5.13 Signal between Persons ....................................................................................... 9 5.14 Reports to Electrical Supervisor............................................................................ 9 5.15 Portable Electrical Apparatus................................................................................ 9 5.15.1 Requirements .................................................................................................... 9 5.15.2 inspection .......................................................................................................... 9 6 Electrical Isolation.......................................................................................................... 10 6.1 Lock Off .................................................................................................................. 10 6.1.1 Padlock & Key ................................................................................................. 10 6.1.2 Procedure........................................................................................................ 10 6.2 Electrical Isolation Permit ....................................................................................... 11 6.2.1 Generalities ..................................................................................................... 11 6.2.2 Request ........................................................................................................... 12 6.2.3 Execution......................................................................................................... 12 6.2.4 Checking ......................................................................................................... 13 6.2.5 Sign off ............................................................................................................ 13 6.2.6 Uncompleted Work.......................................................................................... 14 7 Electrical Ability Permit .................................................................................................. 14 7.1 General................................................................................................................... 14 7.2 Ability Permit Qualification...................................................................................... 15 7.2.1 Letters ............................................................................................................. 15 7.2.2 Numerical Indexes........................................................................................... 15 7.2.3 Letter after Numerical Indexes ........................................................................ 15 7.3 Ability Permit Level ................................................................................................. 16 Attachments: Electrical Isolation Permit Isolation Log Record



1 p. 1 p.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



1



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



3 of 18



Date:



13/05/08



Rev no:



10



PURPOSE



This Standard Operating Procedure (SOP) is issued and maintained by FO/MNT/ELC and reviewed by HSE as it belongs to the TOTAL E&P INDONESIE (TI) HSE Manual. The objectives of the Electrical Safety Procedures (ESP) are the following: - to provide directives for the application of safety electrical work rules, - to eliminate personnel injuries, reduction of damage to equipment/property and to prevent reoccurrence, - to establish responsibility and accountability, - to assure the safety of the company's employees and contractors who work on electrical equipment, - to ensure the continuity of the electrical supply in the best safe conditions. A hard copy of this procedure is issued to Electrical Section at each site. This SOP is also part of the TI CMS, Corporate Management System, available at Intranet.



2



SCOPE



This SOP is applicable in all TI premises and entities. Any works related to electricity including instrumentation and mechanical works, which require isolation and de-isolation of electric power supply shall refer to this SOP. Each employee belonging to TI or contracted by TI who may be concerned with the operation or work on electrical equipment / installation within the TI premises must strictly follow this SOP.



3



REFERENCES



International Standard: - I.E.C. 60038, IEC Standard Voltage - I.E.C. 60050-651, IEC Vocabulary : Live working, - I.E.C. 60050-605, IEC Vocabulary : Switchgear, Controlgear and Fuses - I.E.C. 60664-1, Insulation coordination for equipment within low-voltage systems. - I.E.C. 60742, Isolating Transformers and safety isolating transformer – Requirement - I.E.C. 61010-1, Safety Requirement for Electrical Equipment for Measurement, Control and Laboratory Used - I.E.C. 60079, General Requirement for Electrical Apparatus for Explosive Gas Atmosphere - I.E.C. 61892, Mobile and Fix Offshore Unit – Electrical Installation TOTAL Documents: - GS-ELE-179, Electrical Apparatus for Potentially Explosive Gas Atmospheres - GS-ELE-374, Construction Site Electrical Installations - GS-PJC-401, HSE on Construction and Installation Sites TI Documents: - SOP 03-001, Work Permits SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



-



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



4 of 18



Date:



13/05/08



Rev no:



10



SOP 03-002, Isolations SOP 03-315, Portable Power Tools SOP 03-403, Gas Testing SOP 03-509, Excavations



4



DEFINITIONS



AC/ DC: Alternating Current/ Direct Current Accessible Parts: Parts of electrical equipment or apparatus, which are liable to be touched by persons. Circuit of an Installation: Assembly of electrical equipment (conductors, appliances, etc.) having different phases supplied by the same power source and protected against overloads by the same protective device. Dead: at or about earth potential and disconnected from any live system. De-Isolate: to remove earthing and/or make live by switching on control and mains supplies to an equipment or system. Electrical Shock: Pathophysiological effect of the passage of an electric current through the human body. Electrical Ability Permit: is issued by the Sr. Electrical Authorized Person to a TI employee and the employee contracted by TI who meets the definition of an Electrical Authorized Person. It will state the type of work the person can undertake and any limitations that may apply, as described in this procedure. Electrical Authorized Person: is a person who has sufficient technical knowledge and experience to enable him to avoid danger when carrying out specific work on electrical equipment as certified by Sr. Electrical Authorized Person. Electrical Installation: Group of circuits for a given function and having coordinated characteristics. Electrical Isolation: to make a piece of equipment or electrical system "Dead" by switching off all sources of electrical power and connect it to the earthing network. Electrical Work: all operations on connection or insulation of equipment, installation of electrical devices, cabling work, etc on dead equipment of electrical installation. Hazardous Area: Area/location that classified has potential to create explosion due to presence of gas Insulation: All the insulators involved in the construction of equipment for the purpose of insulating the live parts, also designates the act of insulating. Basic Insulation: Insulation applied to live parts to provide basic protection against electrical shock. Supplementary Insulation: Independent insulation applied in addition to the Basic insulation, in order to provide protection against electrical shock in the event of a failure of the basic insulation. Double Insulation: Insulation comprising both Basic Insulation and Supplementary Insulation. Intervention: operation activities such as test, troubleshooting or measurement on an electrical installation SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



5 of 18



Date:



13/05/08



Rev no:



10



Isolation Responsible: Electrical authorized person who has responsibility to lock off/on equipment on specific location based on his/her ability permit. Isolation Log Record: is a book/record located in site electrical maintenance section which is used to record all information concerning the work carried out and the user of the padlock. Refer to the form attached to this SOP. Live Conductor/ Parts: Conductor or conductive part which is energized in normal operation, including a neutral conductor. Locking off: is performed to put and maintain the equipment in one status; stop, draw-out and test position in such condition that nobody is able to manipulate without authorization. Maneuver: Successive operations leading to an electrical installation status change (switching on, switching off, closing and opening loops...) with switches, breakers, isolators and other devices specially designed to this purpose. Except the maneuvers, whatever the voltage class, all other operations performed on the electrical installations or equipment are categorized as works. Neutral Conductor: Conductor (in an AC system) connected to the neutral point and liable to carry current. Operating Authority: is formally appointed by the RSES and he is directly responsible for acceptance of permits at the planning stage for operations of which he is in charge. Refer to SOP 03-001 Work Permits. Partial Electrical Isolation: this type of isolation is performed to avoid any possibility of putting back into service an electrical motor or device driving a machine, on which a non-electrical job has to be carried out. Locking off request is required on the electrical isolation permit and on the main work permit. Performing Authority: TI representative in charge of the work performance. He is present on the installation or in the immediate vicinity for the entire duration of the work. Refer to SOP 03-001 Work Permits. RSES: Responsible for Health, Safety and Environment on Site appointed by General Manager. Refer to SOP 03-309 RSES. Safety Padlock: padlock, which used for locking off purpose. Safety Extra-Low Voltage (SELV): denotes a voltage, which does not exceed 50 V a.c. r.m.s. or 120 V d.c. between conductors or between any conductor and earth in a circuit which is isolated from the supply mains by means such as a safety isolating transformer. Sr. Electrical Authorized Person: is the Senior Electrical Engineer who is appointed by Executive Vice President & East Kalimantan District Manager (EVP) in written, and must be a competent person on electrical subject and has the responsibility of issuing Electrical Ability Permit for TI. Substation: the part of power system, concentrated in given place, including mainly the terminations of transmission or distribution line switchgear and housing and which may also include transformers. It generally includes facilities necessary for system safety and control (e.g. the protective devices). Switchgear: A general term covering switching device and their combination with associated control, measuring, protective and regulation equipment, also assemblies of such devices and equipment with associated interconnections, accessories, enclosures and supporting structures, intended in principle for use in connection with generation, transmission, distribution and conversion of electric energy. SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



6 of 18



Date:



13/05/08



Rev no:



10



Total Isolation: this type of isolation is performed to allow work on electrical equipment. This equipment is out of service, current switched off without any possibility of it coming back and all other powers (pressured air, potential energy, etc) are disabled. Locking off/ isolation requisition is required on the electrical permit and the main work permit. Voltage Classification: Voltage Range Designation



5



Rated Voltage V (Volts) Symbol



AC



DC



Safety Extra Low Voltage



SELV



V≤ 50



V ≤ 120



Low Voltage A



LVA



50 < V ≤ 500



120 < V ≤ 750



Low Voltage B



LVB



500 < V ≤ 1,000



750 < V ≤ 1,500



High Voltage A



HVA



1,000 < V ≤ 50,000



1,500 < V ≤ 75,000



High Voltage B



HVB



V > 50,000



V > 75,000



OPERATIONS OF ELECTRICAL SYSTEM 5.1 WORK ON LIVE PARTS As a general rule, the interventions or the works of electrical field shall be performed on dead equipment or installation. Work on High Voltage is absolutely prohibited. Work on live-parts (only on Low Voltage) could only be performed under the following circumstances: - 1st case: the switching off of the installation or equipment may jeopardize the life or the health of person, - 2nd case: imperative necessities of exploitation prevent the switching off of the installation or equipment, - 3rd case: the nature of the work itself requires the presence of voltage (verification of circuits, relays, measuring devices, search and localization of faults, etc.). On above 1st and 2nd cases, the specific working procedures and safety measures have to be set up by Site Electrical Supervisor and approved by Head of Electrical Method Service and during work execution, Electrical Authorized Person shall supervise the work closely. For above 3rd case i.e. calibration, test, measurement and recording of electrical network are considered as intervention on live parts with the following condition: - only could be performed on LVA, - could only be done by competent person having ability permit to do so, - precaution should be taken to avoid electrical danger, - all working and used measurement devices are in safe and proper condition.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



7 of 18



Date:



13/05/08



Rev no:



10



5.2 INTERVENTION In case of any doubt (in implementation of the following rules), it is the responsibility of the RSES to appreciate if electrical works require the application of the work permit procedure or not. 5.2.1



WITHOUT WORK PERMIT AND ELECTRICAL ISOLATION PERMIT



Unless: - RSES does ask for issuing a Work Permit, - the works are located within an Explosive Area, the following works do not require the Work Permit and Isolation Permit: - replacement of LV fuses, - replacement of lamps and ballast including minor repair, - systematic maintenance of battery, - running test of emergency generators, - running test of turbine generators, - change-over turbine generator operation, - restarting of thermal electric generator/CCVT, - all works in workshop area, - routine systematic maintenance and performance test on engines, HVAC, domestic equipment and generators. However: - all above works should be recorded in a logbook available in control room, - those interventions should always be made in the absence of voltage (if applicable). - those intervention shall be covered by written instruction 5.2.2



WITH WORK PERMIT AND ISOLATION PERMIT



The work should not be started without following existing work permit procedure. If work location is not in Electrical Room, each working zone should be delimited by protection tape Passage for evacuation should be preserved every time. The work could be started only when any possible voltage sources are isolated. The electrical supervisor shall issue an electrical isolation permit to cover electrical locking off and total isolation.



5.3 WORKING IN HAZARDOUS AREAS When working in classified area, with risk of presence of ignition source, emission of nonaked flame work permit associated or not with risk assessment shall define precautions to be implemented to avoid explosion, such as but not limited to: - use of non sparking tools or intrinsically safe - ventilation of the atmosphere, - permanent monitoring of presence of explosive gas



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



8 of 18



Date:



13/05/08



Rev no:



10



5.4 ENTRANCE TO SUB STATION, ELECTRICAL TECHNICAL ROOM OR TECHNICAL SWITCHGEAR Entry to electrical room housing HV apparatus which is live is strictly limited to electrical authorized persons or someone accompanied by him/her. All Substations, Electrical Technical Rooms or Technical Switchgears shall be kept locked. The keys shall be available in Electrical Supervisor Room.



5.5 OPERATION OF SWITCHGEAR Circuit breaker or switch must not be operated without the presence of Electrical Supervisor or his/her delegation (who having suitable Electrical Ability Permit to do so) except in circumstances where any circuit breaker or switch has to be opened to prevent danger to life or in extreme emergency. When a circuit breaker or switch has been opened, it must not be closed again without consent of the Electrical Supervisor or his/her delegation who has suitable Electrical Ability Permit. No switching operations could be performed by persons other than those authorized to do so. All electrical distribution switching operation will be reported, detailed sequenced and suitably time/date recorded in Isolation Log Book.



5.6 RE-CLOSING AFTER FAULT OPERATION No incoming or outgoing circuit breaker in substation may be re-closed after fault trip until the cause of tripping has been definitely ascertained.



5.7 OPERATION OF CIRCUIT BREAKER IN SUBSTATIONS & ELECTRICAL ROOMS The operations of circuit breaker and means of isolated on the distribution network will be performed only by Isolation Responsible.



5.8 OPERATION OF OTHER ELECTRICAL EQUIPMENT IN PLANT AREA The start-stop operations of motors driving process equipment and the switching of other electrical equipment such as plant lighting, process heating, etc. will be carried out by operators or maintenance personnel having Ability Certificate to do so and also as required by the process operations.



5.9 CUTTING AND JOINTING OF CABLES Before any cable is cut, it must be identified and made dead and when practicably should be earthed. Cutting of cable in hazardous area requires a hot work permit procedure. Jointing of cables shall be performed using only the appropriate material.



5.10



MECHANICAL WORK ON ELECTRICAL DRIVEN MACHINE



Locking off (partial/electrical isolation) and locking off all other sources of power are necessary, and must appear on main work permit. For this type of work among aother requirements (refer also to SOP 03-002), an electrical isolation permit is required. After checking that the right machine has been locked off, no possibility of local or remote start-up, using padlocks, then work can be started on the machine. SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



5.11



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



9 of 18



Date:



13/05/08



Rev no:



10



WORK IN A SUBSTATION OR CLOSE-TO ANY ELECTRICAL LIVE INSTALLATION



The work does not require electrical isolation work as long as there is accessible livepart, however main work permit is necessary.



5.12



EXCAVATIONS



Refer to the SOP 03-508, Excavations. Before any excavation or other underground work is started, the necessary excavation permit must be signed by an Electrical Authorized Person. During work execution, a competent person should be at work location to ensure that cables or cables covers are not damaged, disturbed or removed without the specific consent from an Electrical Supervisor. A cable layout drawing shall be attached to the excavation permit.



5.13



SIGNAL BETWEEN PERSONS



Instruction to make apparatus alive or dead following a given signal or pre-arranged understanding after an agreed interval of time, verbally or by body language is strictly forbidden. All actions for isolation and/or de-isolation shall be based on this procedure.



5.14



REPORTS TO ELECTRICAL SUPERVISOR



Occurrence of any fault or abnormal condition or operating of protecting relays from whatever cause shall be reported as soon as possible to Electrical Supervisor. During failure of electrical supply, all electrical devices, equipment and conductors shall be considered as being alive until isolated.



5.15



PORTABLE ELECTRICAL APPARATUS



Refer also to SOP 03-315 Hand and Portable Power Tools. 5.15.1 REQUIREMENTS In order to minimize the effects of electrical shock, all portable electrical tools and lamps shall be: - Safety Extra Low Voltage (SELV) Class, or - Using Cordless Battery power, or - double insulation class II with the double square identification sign, or - supplied by a feeder equipped with a residual differential 30 mA device including ground conductor, In the very conductive area or enclosure, only SELV Class tools and lamps shall be used. If the space is very limited (such as small tank, etc), the LV-A/SELV isolation transformer shall be placed out of the working/ enclosure area. 5.15.2 INSPECTION All Electrical portable power operated apparatus shall be subjected to regular inspection by site authority.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



6



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



10 of 18



Date:



13/05/08



Rev no:



10



ELECTRICAL ISOLATION 6.1 LOCK OFF 6.1.1



PADLOCK & KEY



There are two series of padlocks, which have to be used: - A series: Electrical Isolation Padlock, used by electrical section only, - B series: Particular Safety at work for the work performers, used by all maintenance sections and other party (ies). Consequently: - a minimum of one padlock (A series) shall be installed when a permanent or temporary isolation concerns only maneuver, - a minimum of two padlocks (A+B series) shall be installed when the isolation is required for a work or intervention. All padlocks shall be key operated. All maintenance sections shall have their own padlocks and keys. Each padlock shall be engraved with the following information: - Site: BSP, TTN, HDL, NPU, BPN, SPU, etc., - Section: Mech (M), Elect (E), Inst (I), Other (C), for operator, contractor, etc., - A or B series and identification number as following examples: A series: Electrical (E) padlocks to have numbers from 01 to 99, B series: Electrical (E) padlocks to have numbers from 100 to 199, Mechanical (M) padlocks to have numbers from 200 to 299, Instrument (I) padlocks to have numbers from 300 to 399, Other (C) padlocks to have numbers from 400 to 499. 6.1.2



PROCEDURE



1. Padlock and keys are stored in keyboards installed in each section supervisor’s office. 2. If require, a master key or second keys for all safety padlocks are to be kept in keyboard installed in the Site Maintenance Superintendent office for emergency use only. 3. Keys for substation doors, electrical rooms and transformers fence doors, are stored in the Electrical Supervisor's office. 4. Padlocks and keys should be delivered to each employee who works on isolated equipment by his section Supervisor. 5. Padlocks and keys shall never be lent. 6. Padlock used for isolation shall be special type with unique key (not generic type). 7. A tag has to be attached to every padlock to identify the Work Responsible or Isolation Responsible. It is recommended also to indicate the reason for locking-off and the Work Order Number. 8. Each corresponding Supervisor shall draw up a list of the assigned and installed locks, with their discreet. SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



11 of 18



Date:



13/05/08



Rev no:



10



9. After the circuit breaker or switch has been opened, the worker or workers who will be involved in the job snap their lock or locks on the control lever/ locking off arrangement or on multiple lock adapters. 10. When the work is completed and checked by the Performing Authority, the isolation responsible is the last to remove his padlock. (A type). 11. Removing the electrical padlock should be under the supervision of the isolation responsible. 12. All padlocks and keys shall be returned back to the responsible Supervisor at the completion of the work.



6.2 ELECTRICAL ISOLATION PERMIT 6.2.1



GENERALITIES



1. For each work which requires an electrical isolation permit, a separate electrical isolation permit shall be issued, even if the same item is already isolated for other work. In this case all the works shall be completed before the electrical isolation could be cancelled. 2. The Electrical Isolation Permit is required for any intervention or work on equipment or an installation, which has to be electrically isolated. 3. It can only be issued as a complimentary permit to the main work permit and can never be used alone. It has to be signed off to indicate that the equipment has been de-isolated. 4. The electrical isolation shall use padlock and follow the lock off procedure (especially for HV equipment) available on each site for each equipment. 5. When the electrical section requires locking off/ electrical isolation of equipment for electrical work, the same procedure shall be adopted. 6. Separation of equipment or network from possible voltage sources should be clearly visible and secured (breaker or contactor draw-out, perfect operating indication). 7. The Electrical Isolation Permit can only be prepared by Electrical Authorized Person and the isolation work should only be done by Isolation Responsible. The isolation work has to be documented in special isolation logbook. Basically a record of each activity will be made as follows: - the work permits number, - the tag number of the equipment concerned, - the padlock number, - the name (and badge number) of the work responsible, - the date and time of this operation started, - the date of return of the padlock (and key) to the section Supervisor, 8. The isolation logbook should be kept in a good manner. 9. The five copies of the isolation permit should be signed together. 9.1. During performing work: - white copy shall be put in work place and available there permanently and to be presented at any request - yellow copy shall be kept by Operating Authority - blue copy shall be put in Control Room - pink copy shall be kept by Electrical Authority - green copy shall be kept by RSES SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



12 of 18



Date:



13/05/08



Rev no:



10



9.2. After signing off: - white copy is kept by Performing Authority, - yellow copy is kept by Operating Authority, - blue copy is kept in Control Room, - pink copy is kept by Electrical Authority, - green copy is kept by RSES 10. When signing, each responsible shall clearly indicate his name, the date and time of the signature. 6.2.2



REQUEST



The request for an electrical isolation permit shall be issued during the "daily work permit coordination meeting" by electrical authorized person. The requestor shall: - determine what type of isolation will be carried out, - describe the nature of work to be carried out, - indicate precisely the equipment to be locked off, the tag number and the location, - check all possible safety procedures. The RSES or his/her delegate shall: - verify the equipment to be locked off confirm to the main work permit, - acknowledge the electrical isolation permit to be undertaken by his signature. 6.2.3



EXECUTION



The Electrical Supervisor shall nominate the isolation responsible to perform the electrical isolation. The Isolation Responsible shall: 1. identify the equipment/ network to ensure the work, which will be carried out is on the isolated network, 2. read and follow the isolation procedure of the equipment isolated, 3. inform to control room to make sure the lock off is safe to be done, 4. verify the lack of voltage on the equipment or network, 5. put in place, if necessary, screen for prohibiting the access to the live parts if exist, 6. short circuit to earth the downstream conductors by closing the earthing switch if available and padlocking it in the closed position, 7. put the equipment in the desired condition and observe that the available indications show the desired condition; the indication should work properly, 8. put padlock for prohibiting any manipulation, 9. when total isolation of the equipment is completed, the working zone must be marked out with barricades or flags, if the work place is not in Electrical Room, 10. fill in the electrical slot on the permit with the reference number of each padlock applied and sign, 11. fill in the isolation logbook. Be careful: SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



-



-



6.2.4



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



13 of 18



Date:



13/05/08



Rev no:



10



When working on power transformers and putting them in parallel, the isolation shall be made on both primary and secondary side, since low voltage on secondary can produce high voltage in primary. Opening of the circuit which is supplied by the secondary of current transformer when the primary side is live or likely induced current is strictly forbidden. If opening is required, the secondary terminals of the current transformer shall first be sorted using an appropriate device. CHECKING



The five copies of electrical isolation permit form are filled up and signed all together and distributed accordingly. The Electrical Authorized Person shall check that the isolation is correct, perform the necessary tests and sign on the Electrical Authorized Person slot. Note: it is compulsory that tests of HV locking off/ isolation are performed by Isolation Responsible. The Operating Authority shall: - check the electrical isolation, - if required, fill up and sign the special instruction slot by himself / herself. The Performing Authority shall: - check the isolation conditions, - put his own padlock, - fill the padlock reference number in electrical isolation permit, - ensure that the workers have the ability permit level required to perform the work. The work will start only when the Performing Authority is in possession of both given main and electrical permits. 6.2.5



SIGN OFF



The five copies of electrical isolation permit form are collected, signed all together and archived accordingly. The Performing Authority shall: - remove his padlock, - sign in the Performing Authority slot. The Isolation Responsible shall: - read and follow the de-isolation procedure of the isolated equipment, - upon approval of the Operation Authority, put the involved equipment back in service, - perform de-isolation when any electrical isolation permits concerning this part are already returned to him, - return the equipment/ installation to service, sign in the signing-off slot. The Electrical Authorized Person shall: - check that the de-isolation is correct, - perform the necessary tests, - sign on the Electrical Authorized Person slot. The Operating Authority shall: SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



6.2.6



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



14 of 18



Date:



13/05/08



Rev no:



10



check that the deisolation is correct, accept the de-isolation by signing on the Operating Authority slot. UNCOMPLETED WORK



The Electrical Isolation Permit will never be closed without completion of the work. If the works are not completed and the validity of the main work permit has expired then: - the installation is kept isolated, - the Electrical Isolation Permit remains valid and open, - the reference number of valid Electrical Isolation Permit must be written on the new main work permit, - the work can be continued.



7



ELECTRICAL ABILITY PERMIT 7.1 GENERAL When a Contractor's employee works in TI plant as an electrician, the contractor must prove his/her electrical competence and electrical safety knowledge to the satisfaction of the Site Maintenance Superintendent and the Electrical Supervisor. All permanent employee and permanent contracted personnel working on electrical installation must obtain an Electrical Ability Permit from Sr. Electrical Authorized Person. Each employee (permanent or contracted) who works in electrical installation in Total Indonesie Sites has to know the content of this SOP 03-006. The person shall follow the electrical training before getting his / her ability permit and shall pass/ succeed the training test. The validity period of the ability permit is 3 (three) years and could be extended every other 3 (three) years. Extension of permit could only be issued if the person has followed the refreshment training and pass/ succeed the training test. The ability permit is only valid for specific site, type of work, etc., as indicated on the ability permit. Consequently, each person who moves to other site shall obtain the new ability permit upon request to the Electrical Supervisor. The ability permit is strictly personal and non-transferable to other persons. The holder must carry his/ her ability permit all the times during working hours or have it easily available. In the event of loss of his/ her ability permit document, the Electrical Supervisor should be informed immediately. The ability permit does not follow the order of hierarchy. It concerns only the safety consideration of electrical operations. The ability permit does not authorize the holder to perform an operation or works covered by it on his/ her own initiative. Each Supervisor could ask ability permit for his/ her subordinates to Sr. Electrical Authorized Person by mentioning the capability and competence of the proposed holders. Site Sr. Electrical Supervisor will keep the record of all the Electrical Authorized Persons at his/her site and inform Sr. Electrical Authorized Person for any change.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



15 of 18



Date:



13/05/08



Rev no:



10



7.2 ABILITY PERMIT QUALIFICATION Ability permit is identified by Letters and Numerical Indexes 7.2.1



LETTERS



-



First Letter: L (low voltage) and H (high voltage) L & H characterizing the voltage range of equipment and installations on which the entitled qualified person is authorized to work or perform an intervention



-



Second Letter: R: Intervention responsible, person who: - has to be aware of application of safety regulation, - is responsible of interventions or maintenance work on Low Voltage range only. C: Isolation responsible, person who is responsible to perform electrical isolation and takes the corresponding safety measures.



7.2.2



NUMERICAL INDEXES



Characterizing the functional level of person who is entitled to perform the job: 0: Non electrician: person who: is not in charge of the interventions or works in the scope of electricity, - is authorized only to enter into substations to do the works such as cleaning, maintenance of premises and reading of measurement apparatus. 1: Work Performer: person who: - is in charge of the interventions and the maintenance works in the scope of electricity, - can only take action after having received a written or verbal instruction from the work or intervention responsible. 2: Work Responsible: person who: - has to be aware of his own safety and the personnel under his responsibility, - shall continuously supervise his personnel (if necessary). 7.2.3



LETTER AFTER NUMERICAL INDEXES



This letter specifies a special assignment: V: indicates that the holder can work or perform an intervention on the proximity of live parts.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



STANDARD OPERATING PROCEDURES ELECTRICAL SAFETY PROCEDURES



Ref no:



SOP 03-006



Page:



16 of 18



Date:



13/05/08



Rev no:



10



7.3 ABILITY PERMIT LEVEL Operations Work On dead parts



Intervention



Close to live parts



Isolation Responsible Work Responsible



LC or HC L2 or H2



L2V or H2V



Interventions Responsible Work Performer



LR L1 or H1



L1V or H1V



Non Electrician Special Assignment



LV Range Only



L1V



L0 or H0 To be defined specifically for the job which will be assigned



Notes: - An ability of certain index may include the job of lower index as long as the equipment/ installation is still in the same voltage range. - Proximity limit clearance is defined according to the voltage range to give permissible nearest clearance to the live conducting parts.



SOP 03-006 Rev 10.doc



HSE Manual



17/06/08



TOTAL E&P INDONESIE



SEBAGAI IJIN TAMBAHAN COMPLEMENTARY PERMIT



PERMINTAAN ISOLASI SEBAHAGIAN LOCKING - OFF REQUISITION



LAMPIRAN IJIN UTAMA ATTACHED TO MAIN PERMIT No. l



l



l



l



l



l



l.



ATAU PERMINTAAN ISOLASI LISTRIK MENYELURUH OR TOTAL ELECTRICAL ISOLATION REQUISITION



Diminta oleh : Requested by : …………………….…………………… REQUEST PERMINTAAN



ELV LVA LVB HVA



IJIN ISOLASI LISTRIK ELECTRICAL ISOLATION PERMIT



Perusahaan / Seksi : company / Section …………………….………………



Peralatan yang dimatikan : Equipment to be locked off ………………………………………………………….…..



Tgl. : Date :……. …………………………..…



Nr. Tag. : Tag.Number: ……………………..…………….



Waktu : Time: …………….……..……………



Lokasi : Location: …………………………………………………………



Jelaskan disini pada bagian mana dari peralatan akan dilakukan pekerjaan, dengan Nr. Tag. : State here precisely on which part (s) of equipment work is to be carried out, with tag. Number :



Diketahui oleh RSES. : Acknowledged by RSES: Nama/Name



:



Tanda Tangan :



Jelaskan disini jenis pekerjaan yang akan dilakukan : State here precisely nature of work to be done :



Date/Tanggal



:



Isolasi dari peralatan listrik diatas telah selesai dengan : Isolation of the above mentioned electrical equipment has been completed by :



PENGISOLASIAN



ISOLATION



Pemutusan ditarik keluar . Racking out / down breaker Penutup terkunci Shutter locked Isolator utama dibuka . Switching main isolator off Isolator utama terkinci . Locking off main isolator Pembawa contactor dilepas Removal of contactor carriage Fuse utama dipasang Removal of main fuses Fuse utama dilepas Removal of control fuses Pemutus pemansa dimatikan Switch off CB space heater Hubungan utama dilepas Removal of control connection Pemutus control dimatikan . Switching off control breakers Tidak adanya tegangan diperiksa No voltage checking



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



Ditanahkan . Earthing at cubicle Tambahan pentanahan Additional earthing Tabir pengaman dipasang Protective screens installed Tenda peringatan dipasang Position and warning notices Kunci dilaksanakan Padlock (s) applied Nomor kunci Padlock number



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



2



YA/YES



TIDAK/NO



3



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



YA/YES



TIDAK/NO



1



Isolasi telah dilakukan Oleh Penanggung jawab isolasi The isolation is done by Isolation responsible Nama/Name



:



Tanda Tangan :



CHECKING



Date/Tanggal Peralatan tersebut diatas telah diisolasi untuk maksud ini dari system dan tidak diperbolehkan untuk disambung pada sembarang titik tanpa sanksi dari penanggung jawab listrik. Bekerja pada peralatan .yang telah diisolasi dapat dilakukan tanpa pemberitahuan kepada penanggung jawab listrik The equipment detailed above has been isolated for this purpose by the remainder of the system and must not be reconnected at any point without the sanction of the Authorized Person. Work on and operation of any part of the isolated equipment may be carried out without further reference to the Authorized Person



PEMERIKSAAN



Saya yang bertanda tangan dibawah ini menyatakan bahwa saya bertanggung jawab atas pekerjaan yang disebutkan dalam ijin ini dan tidak ada pekerjaan yang akan dilakukan pada bahagian lain dari peralatan oleh saya ataupun bawahan saya



I hereby give permission to carry out the work. Instruksi Kusus: Special Instruction :



Diperiksa Oleh Penanggung Jawab Listrik Checked by Electrical Authorized Person Nama/Name



:



Saya yang bertanda tangan dibawah ini memberikan ijin untuk melakukan pekerjaan.



I hereby declare that I accept responsibility for carrying out the work as detailed on this permit and that no other part of the equipment will be worked on by me or any other person under my control :



Disetujui Oleh Wewenang Operasi Approved by Operating Authority



:



Nama/Name



:



Tanda Tangan :



Tanda Tangan :



Date/Tanggal



Date/Tanggal



:



Diterima Oleh Wewenang Pelaksana Accepted by Performing Authority Nama/Name



:



Saya yang bertanda tangan dibawah ini menyatakan bahwa pekerjaan yang disebutkan dalam ijin ini telah selesai atau berhenti dan semua bawahan saya telah meninggalkan tempat pekerjaan. Peralatan telah siap untuk dioperasikan kembali dengan pengecualian



:



Tanda Tangan : Date/Tanggal



:



Saya menyatakan bahwa peralatan sudah di deisolasi dan dikembalikan seperti semula I hereby confirm that the equipment has been de-isolated and return to the initial condition



I hereby declare that the work detailed on this permit has been completed or stopped and every person under my control has been withdrawn. The equipment is in condition to be returned to service with the exception:



PELEPASAN ISOLASI



SIGN OFF



Nama/Name Wewenang Pelaksana Performing Authority



:



Penanggung Jawab Isolasi Isolation Responsible



Tanda Tangan : Date/Tanggal



:



Saya yang bertanda tangan dibawah ini menyatakan bahwa peralatan dapat dioperasikan kembali.



Nama/Name



:



Tanda Tangan : Date/Tanggal



:



Saya yang bertanda tangan dibawah ini menyatakan menerima pekerjaan deisolasi listrik I hereby confirm that I accept the electrical deisolation work.



I hereby confirm that the equipment may now be returned to service.



Distribusi : Distribution :



Wewenang Listrik Electrical Authorized Person PUTIH : Wewenang Pelaksana WHITE : Perf.Authority



SOP 03-006 Rev 10.doc



Nama/Name



:



Wewenang Operasi Operating Authority



Tanda Tangan : Date/Tanggal



: KUNING : Listrik YELLOW : Electrical



HSE Manual



BIRU : BLUE :



Nama/Name



:



Tanda Tangan : Date/Tanggal



:



Wewenang operasi Op. Authority



17/06/08



TOTAL E&P INDONESIE



ISOLATION LOG RECORD ISOLATION W.P.



TAG



Work



No.



No.



Responsible



SOP 03-006 Rev 10.doc



Date



Time



DE-SOLATION



Padlock No. Isolation



SITE: ……………………………….



Responsible



Date



Time



Responsible



Remarks



Performer



HSE Manual



17/06/08