RENCANA ANGGARAN PEMBUATAN CABANG PRODUKSI PT. MEGA TIRTA ALAMI REGIONAL I
No.
POST ANGGARAN
A
PEMBANGUNAN PABRIK CABANG PRODUKSI
I
Volume
sat
Harga
Jumlah
Sub
Satuan
Harga
Total
PEKERJAAN PERSIAPAN 1 Pembersihan Lapangan 2 Pemasangan bouwplank + uitzet 3 Barak Kerja
5.000
m2
9.338
46.692.272
265
m1
87.548
23.204.600
12
m2
291.827
3.501.920 73.398.793
II
PEKERJAAN TANAH DAN PASIR 1 Galian tanah pondasi
563
m3
58.365
32.884.784
46
m3
58.365
2.687.724
3 Urug tanah + pemdtan tiap 300 mm tebal lapisan
275
m3
93.385
25.680.750
4 Urug tanah penyesuaian pel lantai
620
m3
93.385
57.898.418
53
m3
175.096
9.227.560
124
m3
175.096
21.711.907
2 Galian tanah pondasi footplate
5 Urug pasir pasang bawah paving block 6 Urug pasir pasang bawah pondasi
150.091.142 III
PEKERJAAN PONDASI 1 Pondasi Staal 1:3:10
653
m3
70.038
45.735.081
2 Footplate 100x100
20
m3
5.765.822
115.316.442
3 Sloof 20/25
45
m3
4.715.258
211.950.831 373.002.353
IV
PEKERJAAN BETON
1
Kolom praktis 15/15
2
kolom 20/20
3
Kolom footplate 30/30
4
Ring balk 15/20
5
Balok latiu 20/40
6
Dag beton
V
PEKERJAAN KONSTRUKSI BAJA
7
m3
3.812.995
25.127.636
46
m3
4.711.756
216.740.763
8
m3
4.715.258
37.722.061
45
m3
4.715.258
212.186.594
6
m3
4.715.258
28.291.546
6
m3
4.715.258
29.234.597 549.303.197
1 Pekerjaan Rangka Baja, termasuk:
3.250
m2
1.750.960
5.690.620.685
- Kolom IWF 250x125x6x9 - Rangka kuda-kuda IWF 250x125x6x9 - Plat plendes t=16 mm - Plat buhul t=12 mm - Gording UNP 125x65x6 - Trackstang besi beton D.10 mm - Wind brace besi beton D.16 mm - Atap galvalum t=0,35 - Insulation atap - Ikat tiang cremona 5.690.620.685 VI
PEKERJAAN PASANGAN & PLESTERAN 1 Pas. Beton Ringan ex.
2.170
m2
180.933
392.623.645
2 Plesteran 3 Acian 3 Pasangan dinding partisi batu bata
4.340 4.340 32
m2 m2 m
52.529 35.019 230.478
227.975.019 151.983.346 7.375.287
377
m2
17.510
6.594.992
4 Sponengan
786.552.289 VII PEKERJAAN INSTALASI LISTRIK 1 Instalasi stop kontak panasonic
35
ttk
105.058
3.677.016
2 Instalasi sakelar tunggal panasonic
20
ttk
87.548
1.750.960
12
ttk
93.385
1.120.615
3 Instalasi sakelar dobel panasonic
Rencana Anggaran Pembuatan Cabang Produksi Air Minum AXOGY
Hal : 1 dari : 5
No.
POST ANGGARAN
Volume
4 Instalasi sakelar tripel
sat
Harga
Jumlah
Sub
Satuan
Harga
Total
5
ttk
99.221
496.105
5 Instalasi AC 2PK
15
bh
7.704.225
115.563.374
6 Instalasi titik lampu
70
ttk
291.827
20.427.869
7 Instalasi lampu jalan
8
ttk
2.334.614
18.676.909
8 Panel Listrik + Pasang Listrik
1
ttk
18.093.256
18.093.256
9 Koneksi internet
1
ls
2.334.614
2.334.614
2
unit
875.480
1.750.960
10 Modem
183.891.678 VIII PEKERJAAN KERAMIK 1 Pasang keramik lantai 40/40
1.163
m2
256.807
2 Pasang keramik lantai 30/30
109
m2
245.134
298.538.716 26.597.086
3 Pasang keramik lantai km/wc 20x20
481
m2
245.134
117.787.093
4 Keramik dinding dalam ruang pabrik
53
m2
233.461
12.485.514
5 keramik dinding km/wc 20x25
23
m2
245.134
5.699.375 461.107.784
IX
PEKERJAAN PINTU & JENDELA 1 Pasang pintu double 2 Pasang pintu P1 (2100 x 900mm) 3 Pasang pintu P2 km/wc (2100 x 800mm)
2
bh
2.334.614
4.669.227
20
bh
1.400.768
28.015.363
3
bh
1.284.037
3.852.112
4 Pasang pintu Folding Gate 0,8 mm
39
m2
4.085.574
158.315.986
5 Pasang pintu gerbang besi (7x3)
43
m2
3.501.920
150.582.578
6 Pasang jendela J1
15
bh
1.167.307
17.509.602
7 Pasang jendela J2 (akses berkas)
2
bh
1.167.307
2.334.614
8 Pasang jendela konveyor
7
bh
1.050.576
7.354.033
60
m2
233.461
14.007.682
120
m
105.058
12.606.914
3
bh
992.211
2.976.632
8 Partisi kaca 8 Partisi alumunium 9 Pasang Bouvenlight
402.224.743 X
PEKERJAAN ATAP (BANGUNAN TAMBAHAN) 1 Kuda-kuda beton 2 Gording 8/12 3 Penutup atap asbes
1
m3
4.715.258
6.224.140
1
m3
4.715.258
3.300.680
113
m2
46.692
5.283.231 14.808.051
XI
PEKERJAAN PLAFOND 1 Plafond gypsum board rangka hollow
763
m2
105.058
80.116.935
2 List Profil Gypsum
488
m1
29.183
14.248.439 94.365.374
XII PEKERJAAN SANITASI 1 Pipa 4 " pvc Wavin type o 4" aw
115
m1
87.548
10.041.757
2 Pipa 3 " pvc Wavin type o 3" aw
16
m1
75.875
1.176.062
128
m1
58.365
7.463.760
15
bh
58.365
875.480
5 Bak mandi beton
3
bh
1.517.499
4.552.497
6 Septictank
2
bh
4.085.574
8.171.148
7 Sumur resapan
2
bh
2.918.267
5.836.534
8 Bak kontrol
8
bh
175.096
1.400.768
9 Washtafel Toto
6
bh
875.480
5.252.881
10 Closet duduk TOTO
4
bh
1.459.134
5.836.534
11 Kitchen sink Royal
2
bh
408.557
817.115
10
bh
87.548
875.480
3 Pipa 3/4 " pvc Wavin type o 3/4" aw 4 Kran air ronda
12 Floor drain Royal
52.300.014 XIII PEKERJAAN CAT 1 Cat tembok ex Catylac
4.340
m2
46.692
202.644.462
2 Cat plafond ex Catylac
763
m2
46.692
35.607.527
3 Cat daun pintu ex Emco
149
m2
58.365
8.684.763
4 Cat kusen dan daun jendela ex emco
149
m2
46.692
6.947.810 253.884.561
XIV PEKERJAAN LAIN-LAIN Rencana Anggaran Pembuatan Cabang Produksi Air Minum AXOGY
Hal : 2 dari : 5
No.
POST ANGGARAN
Volume
1 Dinding partisi Gypsum 2 Pasang Paving conblock K300 tbl 6 cm
sat
Harga
Jumlah
Sub
Satuan
Harga
Total
171
m2
145.913
24.878.226
1.511
m2
64.202
97.025.083 19.133.618
3 Pasang awning/kanopi polycarbonate 4 Lisplang 5 Pasang Cyclone Turbine Ventilator, D = 45cm
70
m1
274.317
135
bh
64.202
8.657.623
6
m3
2.334.614
14.007.682 163.702.231
XV PEKERJAAN PAGAR 1 Kolom 15/15
40
m1
59.959
2.383.958
2 Dinding 3 M
492
m2
52.943
26.034.289
3 Dinding 1 M
195
m2
52.943
10.324.453
37
m2
145.913
5.427.977
6
m2
1.400.768
8.684.763
4 Ipal 5 pos satpam
52.855.441 XVI PENGADAAN BARANG 1 Tandon 5.000 liter bahan baku
16
set
7.354.033
117.664.526
2 Tandon 5.000 liter bahan jadi 3 Almari
8
set
7.354.033
58.832.263
3
bh
525.288
1.575.864
4 Jam Dinding 5 Meja kerja + Kursi
1
bh
58.365
58.365
10
bh
875.480
8.754.801
6 Sofa Tamu 7 Infocus
1
bh
1.750.960
1.750.960
1
bh
5.252.881
5.252.881
8 Pesawat Telephone 9 Meja presentasi
5
bh
145.913
729.567
2
bh
875.480
1.750.960
10 Kursi Presentasi 11 White Board
50
bh
408.557
20.427.869
2
bh
1.167.307
2.334.614
12 PABX + Pasang Telp 13 Kalkulator
1
bh
7.003.841
7.003.841
3
bh
70.038
210.115
14 Almari besi (filling cabinet)
4
bh
1.750.960
7.003.841 233.350.467 JUMLAH TOTAL RAB
XVI JASA 10% DARI TOTAL RAB BANGUNAN
1
Ls
953.545.880
953.545.880
JUMLAH TOTAL RAB + JASA II
9.535.458.804 953.545.880 10.489.004.684
SARANA PABRIK 1. Pengadaan Sarana Pabrik a. Mesin Air AXOGY Kap. 30.000 liter/hari
6
unit
291.826.702
1.750.960.211
b. Mesin Filling Galon + Cuci + Kode
1
unit
1.284.037.488
1.284.037.488
c. Mesin Filling Botol 500 ml + Cuci + Kode
2
unit
875.480.105
1.750.960.211
27
unit
7.003.841
189.103.703
1
lot
46.692.272
46.692.272
i. Conveyor
1
set
81.711.477
81.711.477
j. Compresor set
1
set
110.894.147
110.894.147
d. Mesin Filling gelas
1
unit
642.018.744
642.018.744
e. Generator Ozon
4
unit
40.855.738
163.422.953
c. Tandon kapasitas 5.000 lt food grade h. Pipa PVC dan perlengkapan lain
6.019.801.205 2. Pengadaan Sarana Produksi a. PH Digital Meter
10 bh
700.384
7.003.841
b.TDS meter
10 bh
233.461
2.334.614
c. Finger spot
2 bh
1.750.960
3.501.920
10 bh
1.459.134
14.591.335
e. CCTV ( 4 kamera )
5 set
17.509.602
87.548.011
f. Seragam Karyawan
48 ptg
175.096
8.404.609
g. Seragam Produksi + Topi
20 ptg
175.096
3.501.920
h. Sarung Tangan
40 ptg
11.673
466.923
d. HT
Rencana Anggaran Pembuatan Cabang Produksi Air Minum AXOGY
Hal : 3 dari : 5
No.
POST ANGGARAN
Volume
sat
i. Masker
40 bh
j. Sepatu Boot Karet
20 psg
Harga
Jumlah
Sub
Satuan
Harga
Total
5.837
233.461
116.731
2.334.614
k. Sarana Produksi Lain
2 bh
116.731
233.461
l. Peralatan laboratorium
1 set
128.403.749
128.403.749
m. Pallet
40 pcs
455.250
18.209.986
n. Toolset
1 set
5.836.534
5.836.534 282.604.978
3. Stock Awal Bahan Produksi a. Gallon Embos 19 lt
30.000
pcs
44.941
1.348.239.362
b. Tutup Galon
500.000
pcs
467
233.461.361
c. Seal tutup galon
500.000
pcs
117
58.365.340
d. Tissue
500.000
pcs
146
72.956.675
60.000
pcs
875
52.528.806
1.200.000
pcs
1.401
1.680.921.802
e. Stiker Galon f. Botol g. Karton Botol
10.000
pcs
2.918
29.182.670
h. Tutup botol
1.200.000
pcs
76
91.049.931
i. Stiker botol
1.200.000
pcs
175
210.115.225
j. Gelas
2.400.000
pcs
140
336.184.360
10.000
pcs
2.918
29.182.670
l. Lid gelas
2.400.000
pcs
41
98.053.772
m. Sedotan
2.400.000
pcs
23
56.030.727
o. Nota numerator
600
pcs
5.837
3.501.920
p. Formulir pendaftaran
600
pcs
21.012
12.606.914
q. Brosur system
24.000
pcs
490
11.766.453
r. Brosur produk
24.000
pcs
490
11.766.453
s. Paket outlet baru
600
pcs
68.754
41.252.623
t. Paket agen
120
pcs
175.096
21.011.523
1.200.000
pcs
58
70.038.408
v. Tds
100
pcs
110.894
11.089.415
w. Rak galon
500
pcs
583.653
291.826.702
n. Lakban
500
pcs
5.837
2.918.267
k. Karton gelas
u. Seal botol
4.774.051.380 4. Pengadaan Armada a. Sepeda Motor
2
unit
14.007.682
28.015.363
b. Mobil pick up (L300)
4
unit
166.341.220
665.364.880
c. Mobil nissan livina
3
unit
215.951.759
647.855.278
d. Mobil nissan serena
1
unit
566.143.801
566.143.801
d. Mobil truck
4
unit
280.153.634
1.120.614.535
e. Forklift
1
unit
175.096.021
175.096.021
f. Handpallet
2
unit
17.509.602
35.019.204 3.238.109.083
6. Pengadaan Peralatan Kantor a. Komputer
10
unit
5.252.881
52.528.806
b. Printer
6
unit
1.750.960
10.505.761
c. Almari besi
10 bh
2.626.440
26.264.403
d. Jam Dinding
10 bh
58.365
583.653
e. Meja kerja + Kursi
10 bh
875.480
8.754.801
f. Sofa Tamu
1 bh
1.750.960
1.750.960
g. Infocus
2 bh
5.252.881
10.505.761
h. Pesawat Telephone
5 bh
145.913
729.567
i. Meja presentasi
2 bh
875.480
1.750.960
j. Kursi Presentasi
100 bh
408.557
40.855.738
k. White Board
5 bh
1.167.307
5.836.534
l. PABX + Pasang Telp
1 bh
7.003.841
7.003.841
10 bh
70.038
700.384
4 bh
35.019
140.077
o. Filling cabinet
10 bh
1.750.960
17.509.602
p. ATK
1
2.334.614
2.334.614
m. Kalkulator n. Stempel
lot
Rencana Anggaran Pembuatan Cabang Produksi Air Minum AXOGY
Hal : 4 dari : 5
No.
POST ANGGARAN
Volume
sat
Harga
Jumlah
Sub
Satuan
Harga
Total
q. Digital Kamera
2
bh
1.750.960
3.501.920
r. Peralatan Kebersihan
1
set
3.501.920
3.501.920
10
bh
1.750.960
17.509.602
8
bh
1.750.960
14.007.682
s. Alat pemadam Kebakaran t. Dispenser
226.276.588 TOTAL BIAYA PRASANA PABRIK :
14.540.843.234
817.115
4.085.573.825
4.085.573.825
RENCANA KEBUTUHAN INVESTASI 1. Pembelian Tanah
5.000
m2
2. Pekerjaan Bangunan
1
ls
9.535.458.804
9.535.458.804
9.535.458.804
3. Sarana Pabrik
1
ls
14.540.843.234
14.540.843.234
14.540.843.234
4. Pasang Listrik 180 KVA
1
paket
583.653.404
583.653.404
583.653.404
5. Genset 150 KVA
1
paket
204.278.691
204.278.691
204.278.691
6. Perijinan & Pengawasan Proyek
1
paket
350.192.042
350.192.042
350.192.042
TOTAL :
29.300.000.000
Sukoharjo, 1 September 2014 Hormat saya,
Hormat saya,
AGUS SRI HARTONO
ADITYO SUPRAYOGO
DIREKTUR UTAMA
DIREKTUR UTAMA
PT MEGA TIRTA ALAMI
PT MEGA PROFIT INDONESIA
Rencana Anggaran Pembuatan Cabang Produksi Air Minum AXOGY
Hal : 5 dari : 5