5 0 76 KB
TIME SCHEDULE PROJECT Mechanical & Electrical Work (ME) Kawasan Industri Suryacipta - Karawang Timur Owner
: PT. Kadi International - PT.Suryacipta Swadaya (City Of Industry)
Contractor
: CV. Dunia Induksi
Project Manager
: Ahmad Darajat
Site Enngineer
: Ahmad Jaelani
Site Enngineer
: Solihin Suppriyadi
Pelaksana
: Suhaidi Waktu Pelaksanaan Pekerjaan (2 Bulan)
No.
I.
Jumlah Harga (Rp.)
Uraian Pekerjaan
Pekerjaan Persiapan
Rp
5,000,000
1-Aug s/d 7-Aug M1
Bobot
1.01
A
Water Supply
-
1
HDPE PIPE
-
- Pipa HDPE (Unilon SDR 17 PN 10), dia.150mm
Rp
50,000,000
- Galian
Rp
- Pemasangan/Instal/Penyambungan
Rp
- Urugan
Rp
Sep-19 5-Sep 12-Sep s/d s/d 11-Sep 18-Sep M6 M7
19-Sep s/d 25-Sep M8
Okt-19 10-Oct s/d 16-Oct M11
17-Oct s/d 23-Oct M12
KET.
60 hari kalender (2 bulan)
15,752,752
3.18
0.64
0.64
0.64
0.64
0.64
75,000,000
15.15
2.16
2.16
2.16
2.16
2.16
2.16
2.16
37,000,000
7.48
2.49
2.49
2.49
2.41
2.41
1.01
1.01
1.01
1.01
1.30
1.30
1.30
0.29
0.29
0.29
0.29
0.65
0.65
-
Rp
71,656,000
14.48
7.24
7.24
3.62
3.62
-
- Pengadaan
Rp
35,828,000
- Install
Rp
35,828,000
7.24 Rp
143,312,000
Hydrant Pillar lengkap
7.24
2.41
-
- Pengadaan, set komplit
Rp
16,496,346
- Install
Rp
25,000,000
3.33 Rp
41,496,346
Street Lighting
1.67
5.05
1.67 1.01
-
Street Lighting Pole (h=11 m') – Galvanis,
-
- Produksi PJU type Octagonal
Rp
45,000,000
9.09
1.30
1.30
1.30
- Pengdaan Lampu LED 120 Watt
Rp
20,000,000
4.04
1.35
1.35
1.35
- Pengdaan Baterry Lampu
Rp
26,000,000
5.25
1.75
1.75
1.75
- Pengdaan Armature Solar Cell
Rp
15,000,000
3.03
1.01
1.01
1.01
- Pemasangan/Instalasai
Rp
10,000,000
2.02
0.29
0.29
0.29
- Comisioning
Rp
6,400,000
1.29 0.30
0.30 0.24
C
FHO
Rp
1,500,000
D
Maintenance/Pemeliharaan
Rp
3,500,000
Sub Total
3-Oct s/d 9-Oct M10
Waktu pelaksanaan
3.37
182,752,752
26-Sep s/d 2-Oct M9
0.51
3.37
150 mm diameter Gate Valve (DCI)
B
29-Aug s/d 4-Sep M5
3.37
VALVE + BOX - Gate valve ex. Amri / Toyo
22-Aug s/d 28-Aug M4
10.10
Rp
2
0.51
Agust-19 8-Aug 15-Aug s/d s/d 14-Aug 21-Aug M2 M3
Rp
127,400,000
0.71
Rp
494,961,098
100.00
1.30
0.24
0.24
Terbilang
Rencana Progress (Mingguan) (%)
7.97
12.37
24.39
24.44
10.30
9.67
7.90
2.48
0.24
0.24
-
-
Rencana Progress Komulatif (%)
7.97
20.34
44.73
69.17
79.48
89.14
97.04
99.53
99.76
100.00
100.00
100.00
f:\Schedule Pekerjaan Pipa HDPE - Suryacipta