PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No.
0.1
Revision Page
dari
7
Date
ELT
Location : KONDARA_KLU Site ID : 25KLU018
= Yes = No
RECTIFIER SYSTEM Rectifier Series
:HUAWEI
System Propose:: Indoor
Outdoor PS 2.3kW
Area :SULSEL
PS 3.3kW
PS5.3KW
Rectifier Type
: Rectifier ELTEK FP2 3000W
Rectifier Capacity
: 3x 63A/ 230 V VoltageInput
: 220V(Linetoneutral)
I.
VISUAL CHECK INDOOR CABINET
NO.
DESCRIPTION
1.
Dimension
2.
Outdoor cabinet
Traybatteryadjustable Adjustablebatterybeltor 4. stopper battery Indoor cabinetshall have IP 20 5. Indoor cabinetusingmaterial 6. steel oraluminium Cabinetshall bepowder coating 7. Cableentryindoor viathetop 8. behind GroundingbarCabinet 9. GroundingCableuseNYAF 10. 35mm(Green-Yellow) 3.
STATUS
CAPACITY
RESULT
H xWxD
600 mmW x 600mmD x 2000mmH (+/- 3%)
600 x 550 x 2000
OK NOK
OK NOK
OK NOK
OK NOK
OK NOK
OK NOK
OK NOK
OK NOK
OUTDOOR CABINET NO. 1.
DESCRIPTION Dimension
2.
Outdoor cabinet (H xWxD)
3.
Innerdepth outdoor
4.
Traybatteryadjustable Adjustablebatterybeltor stopper battery Outdoor cabinethavefreespace 17U,19”forBTS transmission
5. 6.
STATUS
CAPACITY
RESULT
H xWxD
H xWxD
2060x800x770mm
2060x800x770mm
Min 580mm
Min 580mm
OK OK
NOK NOK
OK
NOK
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page
0.1 dari
Date
outdoor cabinetshall have IP 55 outdoor cabinet usingmaterial aluminium Cabinetshall bepowder coating
7. 8. 9.
Cableentryoutdoor viathe 10. bottom of baseplinth 11. Gasketoutdoor cabinet 12. FanAxial 48VDC 13. Grounding Bar Cabinet 14. GroundingCable GSW3x25
OK OK
NOK NOK
OK
NOK
OK NOK OK NOK OK NOK OK NOK OK NOK
INSTALLATION QUALITY CHEKLIST NO. 1. 2. 3. 4. 5. 6.
7.
8. 9. 10. 11. 12. 13.
14. 15. 16.
DESCRIPTION ACPDBCableEntriessealedwith IP cablegland ACcablefrom AC PDBtoservice cabinet protectedinapproved conduit ACcableburied>=minimum required depth(60cm) Verifythat allACpower Cables/ wiringuses correct phasecolours Verifyusescrimpedferrules/cable shoesonwire terminations ACPower Cablemusthave an appropriatesizeofconduit andfitted to theglandcorrectly Anchorhardwaremustbe12mm diameter,andHD galvanisedor stainless steelandinstalledinall4 corner ofthecabinet base Confirmthatnumber ofFaninstalled as per specificationandrunning properly(2fansforWestindoand3 fansfor Hariff)faultymotor bearings Groundingwireconnectedtodoor Groundingbar inCabinetis installed properly Groundingbar inplinthbaseis installedcorrectly Rear Groundingis usecorrect material 3xGSW25mm Groundingcable oftheservice cabinetroutedwithgoingdown directiontotheBusbar.(noupward direction) Rear Groundinglugis properly Integrated tosite's Main Earth Terminal Cables areprotectedfromsharp objects Noloose,unconnectedcables
STATUS
SEVERITY
OK NOK NA OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA OK NOK NA
MAJOR
MAJOR
MAJOR
OK NOK NA OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MINOR
OK NOK NA
MAJOR
REMARK
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision
0.1
Page
POWERSUPPLY INDOSAT
dari
Date
All Power supplymodules& 17. replaceableunitshave Indosatbarcodes
OK NOK NA
18. All Baterrieshave Indosatbar-codes ACcableinsulationjacketmustcome 19. allthewayup totheAC board Rectifier canbeeasily withdrawn on 20. rails 21. fullsetofDC MCBsinstalled 2x4xBatteries(Standard External 22. Cabinet). Brand of batteries(Narada,Shoto, 23. Enersys,Northstar) 24. Rectifier moduleis asAs plan All Rectifier moduleisworking 25. properly All baterrycableconnectionis done 26. properly Timeanddatesettingaccordingto 27. specification(real time) All batteryconnectionsare tightand 28. covers are notdamaged and replaced correctly Bothbatterybankshave thebatteries 29. labelled1to4 Cabinet Ambienttemperaturesensor 30. locatedinplinth. Batterytemperaturesensor #1fixed 31. betweenbattery2 and 3 Batterytemperaturesensor #2fixed 32. betweenlower battery2 and3(or in theslavecainet) Cabinetsensor isfixedsecurelyto 33. thecabinetonthelefthandsideat thetop.
OK NOK NA OK NOK NA
MINOR
OK NOK NA
MAJOR
OK NOK NA OK NOK NA
MAJOR
OK NOK NA
MINOR
OK NOK NA OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
OK NOK NA
MAJOR
II.
MINOR
MINOR
MAJOR
MAJOR
VOLTAGE INPUT
NO. 1.
DESCRIPTION ACInput: - ACInputR –S - ACInputS–T - ACInput T –R - ACInputR –N - ACInputS–N - ACInput T –N
SPECIFICATION/ CONDITION
RESULT
350Volt ~ 410Volt 350Volt ~ 410Volt 350Volt ~ 410Volt 90Volt ~ 242Volt 90Volt ~ 242Volt 90Volt ~ 242Volt
382Vac 380Vac 385Vac 221Vac 220Vac 220Vac
2.
VoltageN–G
0 Volt ~ 2Volt
5,28Vac
3.
Frequency
50Hz~ 60Hz
52Hz
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No.
0.1
Revision Page
POWERSUPPLY INDOSAT
7
dari
Date
III.
RECTIFIER MODULE
NO. 1. 2.
IV.
DESCRIPTION Part number of rectifier modules
P/N : WPSU50A05
Serial number of rectifier modules : Rectifier 1st Rectifier 2nd Rectifier 3rd Rectifier 4th Rectifier 5th Rectifier 6th Rectifier 7th Rectifier 8th
S/N 1: 2102310FFAHVK5007326 S/N 2: 2102310FFAHVK5007354 S/N 3: 2102310FFAHVK5007281 S/N4:_____________________ S/N 5:_____________________ S/N 6:_____________________ S/N 7:_____________________ S/N 8:_____________________
SYSTEMVOLTAGELEVELTEST
NO. 1.
DESCRIPTION
SPECIFICATION/ CONDITION
Rectifier Setting: - NominalFloat - BoostVolt - RectifierStandbyVoltage - BatteryDisconnect - BatteryReconnect - Load Disconnect - LoadReconnect - BatteryChargeCurrentLimit
2.
LoadCurrent
3.
Back UpBattery
V.
ALARM CONTROL
NO
RESULT
DESCRIPTION
54,48 Vdc 56,40 Vdc 45,0 Vdc 43,2 Vdc 47,0 Vdc 46,0 Vdc 47,0 Vdc 10%x 190Ah 0Amp~200 Amp
RESULT
51.52Vdc 52.13Vdc 45.17Vdc 43.12Vdc 49.39Vdc 45.52Vdc 52.39Vdc 19Ah 27 Amp
OK/NOTOK
RELAYALARM MAPPING
ACTIVE LEVEL
RELAY STATE
RELAYTEST
1.
Relay1
st
Mainsfail
Energize
NC
ActiveRelay1
st
2.
Relay2
nd
Rectifier Fail
Energize
NC
ActiveRelay 2
3.
Relay3
rd
High Temp
Energize
NC
ActiveRelay3
4.
Relay4
th
PLVDFail
Energize
NC
ActiveRelay4
th
5.
Relay5
th
Arrester Fail
Energize
NC
ActiveRelay5
th
6.
Relay6
th
DoorOpen
Energize
NC
ActiveRelay6
th
7.
Relay7
th
FuseFail
Energize
NC
ActiveRelay7
th
nd
rd
RESULT
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No.
0.1
Revision Page
POWERSUPPLY INDOSAT
dari
Date
VI.
BATTERY
NO.
SPECIFICATION/ CONDITION
DESCRIPTION
RESULT
1.
Total batteryper bank
2.
Total batterybank
1/2/3/4/5
3.
Voltagenominal per battery
2 Vdc/12Vdc
Vdc
4.
Capacitynominalper battery
100/170/ 180Ah
Ah
5.
Voltagenominal per bank
6.
Total batterycapacity
NO.
4/8/12/16/20
48Vdc
Vdc
Bank xAh
DESCRIPTION
RESULT
7.
BatteryPartNumber
P/N :6-FMX-170
8.
BatterySerial Number: BatteryCell1 BatteryCell2 BatteryCell3 BatteryCell4 BatteryCell5 BatteryCell6 BatteryCell7 BatteryCell8 BatteryCell9 BatteryCell10 BatteryCell 11 BatteryCell12
S/N :EE1314200890 Battery Vot 13,2 OK NOK S/N :EE1823434865 Battery Vot 13,2 OK NOK S/N :EE1307844098 Battery Vot 13,2 OK NOK S/N : EE1961983144 Battery Vot 13,2 OK NOK S/N :EE1497105037 Battery Vot 13,2 OK NOK S/N :EE1781171169 Battery Vot 13,2 OK NOK S/N :EE1918336492 Battery Vot 13,2 OK NOK S/N :EE1607260137 Battery Vot 13,2 OK NOK
Ah
DE S
RESULT
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No.
0.1
Revision Page
POWERSUPPLY INDOSAT
dari
Date
VII. REMAKS
TestDate :…………………………………. Approvedby,
Testedby, PT.
PT. INDOSAT
(
)
(
Huawei Tech. Investment
)
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 1.Foto Team Di Site
Comment
2.Site Name Plate/Site ID
Comment 3.Tampak Tower
Comment
4.Site Tampak Dari Depan (Over View)
Comment 5.Cabinet Rectifier Tertutup
Comment
6.Cabinet Rectifer Terbuka
Comment
7.Foto Kabel Grounding di Pintu ke Cabinet Rectifier 8.Foto Gland Cable Bagian Belakang
13.Foto Module (belakang All ) 11.Foto 15.Busbar Gland Grounding KabelRectifier bagian Cabinet
Comment
Comment Comment
16.Busbargrounding inBattery Base Plate 12.Foto 14.Fan cabinet Bank 1 & 2
Comment
Comment Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page Date
9.Foto Module Rectifier (All)
Comment
10.Foto Battery Bank 1 & 2 (All)
Comment 11.Fan Cabinet
Comment 13.Busbar Grounding in Base Plate
Comment 15.Pengukuran Vtotal Bank Battery (All) #Bank 2
Comment
12.Busbar Grounding Cabinet
Comment 14.Pengukuran Vtotal Bank Battery (All) #Bank 1
Comment 16.Pengukuran Vtotal Bank Battery (All) #Bank 3
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 17.Pengukuran Vtotal Bank Battery (All) #Bank 4
Comment 19.Sensor Temperature di atas kiri Rectifier
Comment 21..Sensor Temperature yang diletakan di base plit
Comment
18.DDF alarm yang diberi label
Comment 20..Sensor Temperature pada Bank1 (Diantara Block 2&3)
Comment 22.Koneksi G Wire ke Cabinet Rectifier
Comment 24..Label Kapasitas Battery
23.Akses Kabel Power di Gland Rectifier sebelah kanan depan yang sudah di flash band
Comment
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 25.Barcode Module 1
Comment
26.Barcode Module 2
Comment 27.Barcode Module 3
Comment 29.Smartpack/Display Monitoring (tampak depan)
Comment 31.Barcode Battery Bank 1 Block 2
Comment
28.Barcode Module 4
Comment 30.Barcode Battery Bank 1 Block 1
Comment 32.Barcode Battery Bank 1 Block 3
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 33.Barcode Battery Bank 1 Block 4
Comment 35.Barcode Battery Bank 2 Block 2
Comment 37.Barcode Battery Bank 2 Block 4
Comment 39.Barcode Battery Bank 3 Block 2
Comment
34.Barcode Battery Bank 2 Block 1
Comment 36.Barcode Battery Bank 2 Block 3
Comment 38.Barcode Battery Bank 3 Block 1
Comment 40.Barcode Battery Bank 3 Block 3
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 41.Barcode Battery Bank 3 Block 4
Comment 43 Barcode Battery Bank 4 Block 2
Comment 46. Barcode Battery Bank 4 Block 4
Comment 48.Pengukuran Tegangan Fasa R-N di MCB Input
Comment
42.Barcode Battery Bank 4 Block 1
Comment 44 Barcode Battery Bank 4 Block 3
Comment 47.Input Kabel Power Ke ACPDB (melalui kabel gland)
Comment 49.Pengukuran Tegangan Fasa S-N di MCB Input
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page Date
50.Pengukuran Tegangan Fasa T-N di MCB Input
Comment
51.Pengukuran Tegangan Fasa R-S di MCB Input
Comment
52.Pengukuran Tegangan Fasa R-T di MCB Input
Comment
53.Pengukuran Tegangan Fasa S-T di MCB Input
Comment 54.Pengukuran N-G di Rectifier
Comment
55.Foto Jalur Kabel Input
Comment
56.Koneksi G-Wire ke Busbar Grounding
Comment
57.Posisi Penempatan Rectifier
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
Date 58.Foto Bak Kontrol Dalam Keadaan Terbuka
Comment
59.Foto Dynabolt Depan Kanan
Comment 60Foto Dynabolt Depan Kiri
Comment
61.Foto Dynabolt Belakang Kanan
Comment 62.Foto Dynabolt Belakang Kiri
Comment
63.Barcode Smartpack/Monitoring Control
Comment 64.Barcode Smartnode
Comment
65.Barcode Subrack Rectifier
Comment
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision
0.1
Page
POWERSUPPLY INDOSAT
dari
Date 66Barcode Cabinet Rectifier
Comment
Comment
68.Koneksi Kabel Alarm Arrester di MCB Output
Comment
Comment
71.Pengukuran Tegangan Battery Bank 1 Block 3
Comment
72.Pengukuran Tegangan Battery Bank 1 Block 4
15.Busbar Grounding Cabinet
Comment
69.Pengukuran Tegangan Battery Bank 1 Block 1
Comment
70.Pengukuran Tegangan Battery Bank 1 Block 2
Comment
67.Koneksi Kabel Alarm Arrester (dibawah Arrester)
73.Pengukuran Tegangan Battery Bank 2 Block.1
16.Busbargrounding in Base Plate
Comment
Comment
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
0.1 dari
Date 74.Pengukuran Tegangan Battery Bank 2 Block 2
Comment 76.Pengukuran Tegangan Battery Bank 2 Block 4
Comment 78.Pengukuran Tegangan Battery Bank 3 Block 2
Comment 80.Pengukuran Tegangan Battery Bank 3 Block 4
Comment
75.Pengukuran Tegangan Battery Bank 2 Block 3
Comment 77.Pengukuran Tegangan Battery Bank 3 Block 1
Comment 79.Pengukuran Tegangan Battery Bank 3 Block 3
Comment 81.Pengukuran Tegangan Battery Bank 4 Block 1
Comment
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP)
Doc. No. Revision Page
POWERSUPPLY INDOSAT
0.1 dari
Date 82 Pengukuran Tegangan Battery Bank 4 Block 2
Comment 84 Pengukuran Tegangan Battery Bank 4 Block 4
Comment 86. Pengukuran Pondasi Rectifier (kiri)
Comment 88..Simulasi Pemanasan Temperature Shelter
Comment
83 Pengukuran Tegangan Battery Bank 4 Block 3
Comment 85 .Pengukuran Pondasi Rectifier (Depan)
Comment 87.Pengukuran Pondasi Rectifier (Kanan)
Comment 89.Foto Capture Alarm Temperature
Comment
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page Date
Capture Active Module (Home)
Capture Active Module (Monitoring – Rectifier 3 /Module Rectifier 1)
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page Date
Capture Active Module (Monitoring – Rectifier 4 /Module Rectifier 2)
Capture Active Module (Monitoring – Rectifier 5/Module Rectifier 3)
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page Date
Capture Active Module (Monitoring – Rectifier 6 / Module Rectifier 4)
0.1 dari
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page
0.1 dari
7
Date
ATP TRANSMITTAL
Site ID
:
KONDARA_KLU
Site Name
:
25KLU018
ATP Date
:
ATP Scope
\
Applicable
Vendor
Mini CME
Ericsson / Huawei / NSN / Other:....................
CME
Hariff/ Westindo / Other: ..............................
Transmission
Ericsson / NSN / ALU / NEC / Other: ................
RAN
Ericsson / Huawei / NSN / Other:....................
PUNCHLIST
NO 1 2 3 4 5 6
Punchlist Item
Responsible Company
Remarks Accept
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page
0.1 dari
Date
PHOTO REVISI ITEM PUNCHIST AFTER
BEFORE
Comment 20..Sensor Temperature pada Bank1 (Diantara Block 2&3)
Comment
Comment 24.
Comment
BEFORE
Label Kapasitas Batterai BEFORE
Comment 31.Barcode Battery Bank 1 Block 2 BEFORE
Comment 33.Barcode Battery Bank 1 Block 4
23.Akses Kabel Power di Gland Rectifier sebelah kanan depan yang sudah di flash band AFTER
30.Barcode Battery Bank 1 Block 1 AFTER
Comment 32.Barcode Battery Bank 1 Block 3 AFTER
Comment 34.Barcode Battery Bank 2 Block 1
7
PT.HUAWEI TECH INVESTMENT ACCEPTANCE TEST PROTOCOL (ATP) POWERSUPPLY INDOSAT
Doc. No. Revision Page
0.1 dari
Date
BEFORE
Comment 35.Barcode Battery Bank 2 Block 2 BEFORE
36.Barcode Battery Bank 2 Block 4
AFTER
Comment 36.Barcode Battery Bank 2 Block 3 AFTER
47.Input Kabel Power Ke ACPDB (melalui kabel gland)
7